Title: Wastewater Coalition Meeting 92500 Power Point
1(No Transcript)
2(No Transcript)
3(No Transcript)
4Sewer System Issues Existing Today
Norman Utilities Authority
September 25, 2000
5Introduction
- Tonights presentation will review the following
- Development of Normans Sewer System
- Components of Wastewater Flow
- Wastewater Master Plan Development
- Development Ordinance Sec. 19-415(g)
- Wastewater System Defects - Public and Private
- Overview of Problems Faced
- General Comments
6Development of Normans Sewer System
- Normans first sewerlines were installed around
statehood. Very few of these lines exist today. - Normans sewer system has grown to include about
two million feet of pipe ranging in size from 4
inches to 42 inches in diameter. - The majority of the lines installed since 1940
are still in service.
7Development of Normans Sewer System
- The existing wastewater collection system today
includes over 8,400 manholes. - Manholes allow access for sewerline maintenance.
- Various materials have been used over time to
construct manholes. Brick and cast concrete are
the two most common materials historically used.
8Wastewater Flow Components
- Normans wastewater system carries unwanted
stormwater (Inflow/Infiltration) following
periods of rain due to defects existing in the
public and private portions of the system. - Stormwater inflow overloads our major
interceptors.
9Master Plan Development
- The Wastewater Master Plan was initiated with
prime objectives targeted - Understand our current collection system capacity
limitations - Identify necessary improvements existing today in
Norman - Identify improvements necessary in Normans
future - A hydraulic model of Normans wastewater
interceptor system was developed to identify
existing and future infrastructure needs
101998 Flow Monitoring Locations
11Master Plan Development - Flow Monitoring
- Flow monitoring occurred during 100 days of the
spring and fall of 1998. - Twenty-four meters collected data every 15
minutes during this time. - Four rain gauges were used in measuring rainfall
rates during this period. - Over 230,000 data readings occurred during this
period.
12Master Plan Development - Design Conditions
- The Oklahoma Department of Environmental Quality
requires Peak design flow must be based on an
acceptable Infiltration/Inflow (I/I) study - In Normans case, a 5-year storm has been
historically accepted as representing conditions
by which sanitary sewers are to be designed.
13Master Plan Development - Model Results
- Model results identified serious sewer capacity
problems existing in many of the major
interceptors serving the City of Norman
14Master Plan Development - Model Results
Ground Surface
Manhole
Pipe
15Master Plan Development - Model Results
Overflows Identified by Model Analysis
16Master Plan Development - Model Results
System Surcharges Identified by Model Analysis
17Master Plan Development - Critical Impacts
- Manhole surcharging can allow sewage to back up
and cause damage to personal property. - In Normans past, and occasionally today,
significant storm events result in wastewater
flows severe enough to create backups.
18Development Ordinance Sec. 19 - 415(g)
Whenever ninety-five (95) percent of the design
capacity of a wastewater collection system is
allocated through approval of final plats, as
determined by the City Engineer, no additional
plats shall be approved for that collection
system until such time as the capacity of said
waste water collection system is increased or
until the City Council has approved, as a part of
the program of improvements for a final plat, an
increase in the capacity of the collection
system. It is the intention of this section to
prohibit new plats until such time as the
capacity is increased or until said increase has
been approved as a condition for the filing of
the plat.
19Resolution Provisions - Current Platted Lots
Residential Industrial Commercial
20Questions Raised by the Public
- Why Not Repair the Aged Portion of Our System?
Since 1990 Norman has performed the following - Imhoff and Normandy Creek Interceptor
Replacements, cost over 10 Million - Annual Sewer Replacements by Fiscal Year, cost
over 3 Million to date - CDBG Funded Projects, cost over 550 Thousand to
date - Line Maintenance Annual Responsibility, cost over
160 Thousand to date on materials alone
21Performance Problems?
22Wastewater System Performance
- During periods of heavy rain Normans sewer
system experiences capacity limitations due to
stormwater entering into the system from one of
two sources. - Public Sector Defects
- Private Sector Defects
- System performance is limited due to a dramatic
increase in wastewater flow following a
significant storm event.
23Wastewater System Performance
30
25
20
Flow Depth (inch)
Typical Flow
15
10
5
012
157
342
527
712
857
1042
1227
1412
1557
1742
1927
2112
2257
Storm Flow
Average Day Flow
24System Defects Identification
- Since 1992 Norman has investigated and identified
defects in our sewer system using Smoke Testing. - Smoke Testing readily identifies defects where
stormwater can enter into the sewer system.
These defects are on both public and private
properties.
25System Defects Identification
Phase 1 Phase 2 Phase 3 Phase 4
26System Defects
- The four phases have identified 13,782 defects
within Normans sewer system. - 12,552 of the defects identified were from Public
Sources. - 1,230 of the defects identified were from Private
Sources.
27System Defects - Public and Private Sources
28System Defects - Public Sources
- To date over 4,866 manholes have been inspected
for defects. - Many manholes have been repaired or replaced as
necessary.
29System Defects - Public Sources
- Over 1,200,000 linear feet of sewerline have been
tested for defects. - Numerous line replacements and point repairs have
occurred. - City of Norman Line Maintenance Crews clean
and/or replace lines systematically.
30System Defects - Public Sources
- To date, four phases of investigation have been
completed. Only three phases have been
constructed. - It is projected that 79 of the public defects
will have been addressed upon completion of the
fourth phase of construction. - Remaining items are not considered critical and
will be systematically addressed in the Capital
Budget in future years.
31System Defects - Private Sources
- Private sources of stormwater entering into
Normans wastewater system were also identified
during the smoke testing investigations. - Each defect was categorized
- Uncapped Sewer Cleanouts
- Defective Service Lines
- Roof Downspouts
- Area Drains
32System Defects - Private Sources (Cleanouts)
- A cleanout is an access point into the property
owners service line which connects to Normans
wastewater system. It provides access for
cleaning if the service line becomes obstructed
or blocked. - Over 840 cleanouts have been identified as
defective.
33System Defects - Private Sources (Service Line)
- Over time many different materials have been used
to connect buildings to the City of Normans
sewer system. - Some of the materials have withstood the test of
time and some have not. - Defective service lines contribute to the amount
of stormwater entering the system and are costly
to correct.
34System Defects - Private Sources (Downspout)
- In some cases a buildings rain gutter is
connected directly to the sanitary sewer system. - In the past this was an accepted practice. Today
it is not allowed. - This defect is not common. To date only eight
have been identified, with some being corrected
shortly after discovery.
35System Defects - Private Sources (Area Drains)
- In some locations, inappropriate drains have been
connected to Normans wastewater system. - A total of 37 locations have been identified at
which area, driveway, or basement drains have
been connected to the sewer.
36Private Defects - System Performance Impact?
- In the past it has been reported that 16 of the
stormwater entering into the system is from
private sources. - This value was derived in 1994 during the Phase 1
Sewer Study. - The data reviewed in developing this number
considered only the most severe problem areas in
town, as identified by the initial flow
monitoring efforts. - The consideration that all of Norman contributes
flow equal to most severe locations is an
erroneous assumption.
37Private Defects - System Performance Impact?
- Considering that the initial study reported that,
in a worst case scenario, a defective or broken
cleanout would contribute 1 gallon per minute
(1440 gallons per day). - The initial report stated that a defective
service line contribute 2 gallons per minute
(2880 gallons per day). - The initial report stated that a roof or area
drain contributed a maximum of 6.4 gallons per
minute (9,200 gallons per day).
38Private Defects - System Performance Impact?
- Assuming that all defects known to exist at this
time contribute at the average rate reported in
the initial study then the flow from these
locations would total 1.06 Million Gallons during
a design storm event. - This rate equates to 2.8 of the maximum
wastewater flows recorded at Normans wastewater
treatment plant. - If the defect numbers are projected to represent
all of Norman a total of 1.7 Million Gallons
would result. This total equals 4.5 of the
maximum flows observed.
39Private Defects - System Performance Impact?
- The removal of any percentage of stormwater is
important, but a reduction of the magnitude
discussed will not solve the capacity issues
existing today. - 16 of the maximum daily flow of 38 Million
Gallons per Day would represent over 6 Million
Gallons of flow originating from private sources. - This large amount is not believed to be practical
and it is certainly not believed to represent our
system during storm events.
40Summary
- Past efforts to eliminate defects where
stormwater enters the system have effectively
reduced capacity related problems. - The sewer interceptors serving Norman today are
still beyond capacity during a 5-year storm. - Improvements will continue to be made to remove
defects from the sewer system. - Line maintenance activities will continue to
address items that allow stormwater to enter into
the sewer system.
41Sewer System Issues Existing Today
Norman Utilities Authority
September 25, 2000