Wastewater Coalition Meeting 92500 Power Point - PowerPoint PPT Presentation

1 / 41
About This Presentation
Title:

Wastewater Coalition Meeting 92500 Power Point

Description:

A hydraulic model of Norman's wastewater interceptor system was developed to ... City Engineer, no additional plats shall be approved for that collection system ... – PowerPoint PPT presentation

Number of Views:58
Avg rating:3.0/5.0
Slides: 42
Provided by: CDM49
Category:

less

Transcript and Presenter's Notes

Title: Wastewater Coalition Meeting 92500 Power Point


1
(No Transcript)
2
(No Transcript)
3
(No Transcript)
4
Sewer System Issues Existing Today
Norman Utilities Authority
September 25, 2000
5
Introduction
  • Tonights presentation will review the following
  • Development of Normans Sewer System
  • Components of Wastewater Flow
  • Wastewater Master Plan Development
  • Development Ordinance Sec. 19-415(g)
  • Wastewater System Defects - Public and Private
  • Overview of Problems Faced
  • General Comments

6
Development of Normans Sewer System
  • Normans first sewerlines were installed around
    statehood. Very few of these lines exist today.
  • Normans sewer system has grown to include about
    two million feet of pipe ranging in size from 4
    inches to 42 inches in diameter.
  • The majority of the lines installed since 1940
    are still in service.

7
Development of Normans Sewer System
  • The existing wastewater collection system today
    includes over 8,400 manholes.
  • Manholes allow access for sewerline maintenance.
  • Various materials have been used over time to
    construct manholes. Brick and cast concrete are
    the two most common materials historically used.

8
Wastewater Flow Components
  • Normans wastewater system carries unwanted
    stormwater (Inflow/Infiltration) following
    periods of rain due to defects existing in the
    public and private portions of the system.
  • Stormwater inflow overloads our major
    interceptors.

9
Master Plan Development
  • The Wastewater Master Plan was initiated with
    prime objectives targeted
  • Understand our current collection system capacity
    limitations
  • Identify necessary improvements existing today in
    Norman
  • Identify improvements necessary in Normans
    future
  • A hydraulic model of Normans wastewater
    interceptor system was developed to identify
    existing and future infrastructure needs

10
1998 Flow Monitoring Locations
11
Master Plan Development - Flow Monitoring
  • Flow monitoring occurred during 100 days of the
    spring and fall of 1998.
  • Twenty-four meters collected data every 15
    minutes during this time.
  • Four rain gauges were used in measuring rainfall
    rates during this period.
  • Over 230,000 data readings occurred during this
    period.

12
Master Plan Development - Design Conditions
  • The Oklahoma Department of Environmental Quality
    requires Peak design flow must be based on an
    acceptable Infiltration/Inflow (I/I) study
  • In Normans case, a 5-year storm has been
    historically accepted as representing conditions
    by which sanitary sewers are to be designed.

13
Master Plan Development - Model Results
  • Model results identified serious sewer capacity
    problems existing in many of the major
    interceptors serving the City of Norman

14
Master Plan Development - Model Results
Ground Surface
Manhole
Pipe
15
Master Plan Development - Model Results
Overflows Identified by Model Analysis
16
Master Plan Development - Model Results
System Surcharges Identified by Model Analysis
17
Master Plan Development - Critical Impacts
  • Manhole surcharging can allow sewage to back up
    and cause damage to personal property.
  • In Normans past, and occasionally today,
    significant storm events result in wastewater
    flows severe enough to create backups.

18
Development Ordinance Sec. 19 - 415(g)
Whenever ninety-five (95) percent of the design
capacity of a wastewater collection system is
allocated through approval of final plats, as
determined by the City Engineer, no additional
plats shall be approved for that collection
system until such time as the capacity of said
waste water collection system is increased or
until the City Council has approved, as a part of
the program of improvements for a final plat, an
increase in the capacity of the collection
system. It is the intention of this section to
prohibit new plats until such time as the
capacity is increased or until said increase has
been approved as a condition for the filing of
the plat.
19
Resolution Provisions - Current Platted Lots
Residential Industrial Commercial
20
Questions Raised by the Public
  • Why Not Repair the Aged Portion of Our System?
    Since 1990 Norman has performed the following
  • Imhoff and Normandy Creek Interceptor
    Replacements, cost over 10 Million
  • Annual Sewer Replacements by Fiscal Year, cost
    over 3 Million to date
  • CDBG Funded Projects, cost over 550 Thousand to
    date
  • Line Maintenance Annual Responsibility, cost over
    160 Thousand to date on materials alone

21
Performance Problems?
22
Wastewater System Performance
  • During periods of heavy rain Normans sewer
    system experiences capacity limitations due to
    stormwater entering into the system from one of
    two sources.
  • Public Sector Defects
  • Private Sector Defects
  • System performance is limited due to a dramatic
    increase in wastewater flow following a
    significant storm event.

23
Wastewater System Performance
30
25
20
Flow Depth (inch)
Typical Flow
15
10
5
012
157
342
527
712
857
1042
1227
1412
1557
1742
1927
2112
2257
Storm Flow
Average Day Flow
24
System Defects Identification
  • Since 1992 Norman has investigated and identified
    defects in our sewer system using Smoke Testing.
  • Smoke Testing readily identifies defects where
    stormwater can enter into the sewer system.
    These defects are on both public and private
    properties.

25
System Defects Identification
Phase 1 Phase 2 Phase 3 Phase 4
26
System Defects
  • The four phases have identified 13,782 defects
    within Normans sewer system.
  • 12,552 of the defects identified were from Public
    Sources.
  • 1,230 of the defects identified were from Private
    Sources.

27
System Defects - Public and Private Sources
28
System Defects - Public Sources
  • To date over 4,866 manholes have been inspected
    for defects.
  • Many manholes have been repaired or replaced as
    necessary.

29
System Defects - Public Sources
  • Over 1,200,000 linear feet of sewerline have been
    tested for defects.
  • Numerous line replacements and point repairs have
    occurred.
  • City of Norman Line Maintenance Crews clean
    and/or replace lines systematically.

30
System Defects - Public Sources
  • To date, four phases of investigation have been
    completed. Only three phases have been
    constructed.
  • It is projected that 79 of the public defects
    will have been addressed upon completion of the
    fourth phase of construction.
  • Remaining items are not considered critical and
    will be systematically addressed in the Capital
    Budget in future years.

31
System Defects - Private Sources
  • Private sources of stormwater entering into
    Normans wastewater system were also identified
    during the smoke testing investigations.
  • Each defect was categorized
  • Uncapped Sewer Cleanouts
  • Defective Service Lines
  • Roof Downspouts
  • Area Drains

32
System Defects - Private Sources (Cleanouts)
  • A cleanout is an access point into the property
    owners service line which connects to Normans
    wastewater system. It provides access for
    cleaning if the service line becomes obstructed
    or blocked.
  • Over 840 cleanouts have been identified as
    defective.

33
System Defects - Private Sources (Service Line)
  • Over time many different materials have been used
    to connect buildings to the City of Normans
    sewer system.
  • Some of the materials have withstood the test of
    time and some have not.
  • Defective service lines contribute to the amount
    of stormwater entering the system and are costly
    to correct.

34
System Defects - Private Sources (Downspout)
  • In some cases a buildings rain gutter is
    connected directly to the sanitary sewer system.
  • In the past this was an accepted practice. Today
    it is not allowed.
  • This defect is not common. To date only eight
    have been identified, with some being corrected
    shortly after discovery.

35
System Defects - Private Sources (Area Drains)
  • In some locations, inappropriate drains have been
    connected to Normans wastewater system.
  • A total of 37 locations have been identified at
    which area, driveway, or basement drains have
    been connected to the sewer.

36
Private Defects - System Performance Impact?
  • In the past it has been reported that 16 of the
    stormwater entering into the system is from
    private sources.
  • This value was derived in 1994 during the Phase 1
    Sewer Study.
  • The data reviewed in developing this number
    considered only the most severe problem areas in
    town, as identified by the initial flow
    monitoring efforts.
  • The consideration that all of Norman contributes
    flow equal to most severe locations is an
    erroneous assumption.

37
Private Defects - System Performance Impact?
  • Considering that the initial study reported that,
    in a worst case scenario, a defective or broken
    cleanout would contribute 1 gallon per minute
    (1440 gallons per day).
  • The initial report stated that a defective
    service line contribute 2 gallons per minute
    (2880 gallons per day).
  • The initial report stated that a roof or area
    drain contributed a maximum of 6.4 gallons per
    minute (9,200 gallons per day).

38
Private Defects - System Performance Impact?
  • Assuming that all defects known to exist at this
    time contribute at the average rate reported in
    the initial study then the flow from these
    locations would total 1.06 Million Gallons during
    a design storm event.
  • This rate equates to 2.8 of the maximum
    wastewater flows recorded at Normans wastewater
    treatment plant.
  • If the defect numbers are projected to represent
    all of Norman a total of 1.7 Million Gallons
    would result. This total equals 4.5 of the
    maximum flows observed.

39
Private Defects - System Performance Impact?
  • The removal of any percentage of stormwater is
    important, but a reduction of the magnitude
    discussed will not solve the capacity issues
    existing today.
  • 16 of the maximum daily flow of 38 Million
    Gallons per Day would represent over 6 Million
    Gallons of flow originating from private sources.
  • This large amount is not believed to be practical
    and it is certainly not believed to represent our
    system during storm events.

40
Summary
  • Past efforts to eliminate defects where
    stormwater enters the system have effectively
    reduced capacity related problems.
  • The sewer interceptors serving Norman today are
    still beyond capacity during a 5-year storm.
  • Improvements will continue to be made to remove
    defects from the sewer system.
  • Line maintenance activities will continue to
    address items that allow stormwater to enter into
    the sewer system.

41
Sewer System Issues Existing Today
Norman Utilities Authority
September 25, 2000
Write a Comment
User Comments (0)
About PowerShow.com