Title: THE GREEN LIGHT PLAN PROGRAM UPDATE
1THE GREEN LIGHT PLANPROGRAM UPDATE
2Purpose of Presentation
- Early Accomplishments
- Prioritization of Projects
- Final Allocation of 125M Bond
3Program Development Timeline
- Notice to Proceed March 10, 2006
- 1st Draft Project Concept May 18, 2006
- Reports
- DPW Review Comments June 16, 2006
- Final Project Concept July 17, 2006
- Reports
4Program Development Timeline
- Present Program Priority July 24, 2006
- Allocation of Bond Sale August 10, 2006
- Presentation to Council August 23, 2006
5Program Development Report
- Comprehensive Project Assessments
- Traffic Modeling
- Alignment Alternatives
- Hydraulic Assessment
- Environmental Assessment
- Utility Relocation
- ROW Estimating
- Construction Estimating
6Existing Engineering Contracts
- McHugh Road
- Stumberg Extension
-
- Sullivan Road
-
- N. Harrells Ferry Road
- Fairchild-Badley Road
7New Engineering Contracts
-
- Burbank Drive Segment 1
- Veterans Memorial Boulevard Ext.
-
- Downtown Signalization
- Burbank Drive Segment 2
-
- Elm Grove Garden
8Right of Way Committee
- City/State Agreement for ROW Purchases on DOTD
Routes - Corridor Preservation Plan
- 42 Permits, 28 Signs, 76 For Sale
- Proactive Communication w/ Developers
9Program Optimization
- 3.5M - Early ROW Acquisition
- Contractor Packaging
- Combined Bike Paths/Pedestrian Sidewalks
- Boulevard Section vs. 5-Lane Section
10 11Boulevard Advantages
- Aesthetics
- Cost Savings
- Long Term Safety
12 13Program Priority Matrix
- Projects Funded by Early Bond Sales
- Recognized Tool for Prioritization
- Outside of Political Influence
- Commitment to Prior Projects
14Program Priority Matrix
- 6 Factors
- Scoring values 1 thru 5
- Weighting values 1 thru 6
- Highest Score
15Program Priority Matrix
- Factors Weightings
- Accident Data 6
- Data collected from City, Sheriff,
- LSU, and State Police Departments
- Highest score to highest number of
- accidents for period 2004 and 2005
- Utilization 5
- Average Daily Traffic (ADT) for 2030
- from Trans-Model was used
- Highest score given to highest ADT
16Program Priority Matrix
- Factors Weightings
- Right-of-Way 4
- Availability of ROW to construct
- the proposed section
- Highest score to projects where ROW
- exists
- Project Cost 3
- Total Project Cost was determined
- Highest score to projects with lowest
- Total Project Cost
17Program Priority Matrix
- Factors Weightings
- Funding Potential 2
- Potential for future funding from FHWA,
- State, LaDOTD Swap, Urban Systems, CMAQ
- Highest score to lowest funding potential
- Environmental Permitting 1
- Environmental and Permitting concerns were
- evaluated
- Highest score to projects with no concern
-
18Priority Matrix
19Initial Allocation of 125M Bond Sale
- 6 Projects Funded for Construction
- Central Thruway
- Comite Drive
- ONeal Lane
- Picardy Avenue
- South Choctaw Drive
- South Harrells Ferry Road
20Final Allocation of 125M Bond Sale
- 5 Projects Funded for Construction
- Burbank Drive Segment 1
- Burbank Drive Segment 2
- Downtown Signalization
- Foster _at_ Government
- Veterans Memorial Boulevard Extension
21Final Allocation of 125M Bond Sale
- 8 Projects Funded for ROW Acquisitions
- Coursey _at_ Sherwood Forest
- Essen Lane _at_ I-10
- Lobdell Improvements
- McHugh Road
22Final Allocation of 125M Bond Sale
- 8 Projects Funded for ROW Acquisitions
- North Harrells Ferry Road
- Perkins _at_ Stanford/Acadian
- South Harrells Ferry Road
- Stumberg Extension
23Final Allocation of 125M Bond Sale
- 11 Projects Funded for Engineering
- Brightside Lane
- Elm Grove Garden
- Fairchild-Badley Road
- Ford Street
- Highland Road
- Old Hammond Highway Segment 2
24Final Allocation of 125M Bond Sale
- 11 Projects Funded for Engineering
- ONeal Lane Segment 1
- Siegen Lane
- Staring Lane
- Staring Lane Extension 1
- Sullivan Road
25- Green Light Program has
- recommended over 125M in appropriations through
- the end of 2007
26(No Transcript)
27- http//greenlight.csrsonline.com
28BUILDING BETTER ROADS FOREAST BATON ROUGE
PARISH
29END OF PRESENTATION