THE GREEN LIGHT PLANPROGRAM UPDATE
  • August 23, 2006

2
Purpose of Presentation
  • Early Accomplishments
  • Prioritization of Projects
  • Final Allocation of 125M Bond

3
Program Development Timeline
  • Notice to Proceed March 10, 2006
  • 1st Draft Project Concept May 18, 2006
  • Reports
  • DPW Review Comments June 16, 2006
  • Final Project Concept July 17, 2006
  • Reports

4
Program Development Timeline
  • Present Program Priority July 24, 2006
  • Allocation of Bond Sale August 10, 2006
  • Presentation to Council August 23, 2006

5
Program Development Report
  • Comprehensive Project Assessments
  • Traffic Modeling
  • Alignment Alternatives
  • Hydraulic Assessment
  • Environmental Assessment
  • Utility Relocation
  • ROW Estimating
  • Construction Estimating

6
Existing Engineering Contracts
  • McHugh Road
  • Stumberg Extension
  • Sullivan Road
  • N. Harrells Ferry Road
  • Fairchild-Badley Road

7
New Engineering Contracts
  • Burbank Drive Segment 1
  • Veterans Memorial Boulevard Ext.
  • Downtown Signalization
  • Burbank Drive Segment 2
  • Elm Grove Garden

8
Right of Way Committee
  • City/State Agreement for ROW Purchases on DOTD
    Routes
  • Corridor Preservation Plan
  • 42 Permits, 28 Signs, 76 For Sale
  • Proactive Communication w/ Developers

9
Program Optimization
  • 3.5M - Early ROW Acquisition
  • Contractor Packaging
  • Combined Bike Paths/Pedestrian Sidewalks
  • Boulevard Section vs. 5-Lane Section

10

11
Boulevard Advantages
  • Aesthetics
  • Cost Savings
  • Long Term Safety

12

13
Program Priority Matrix
  • Projects Funded by Early Bond Sales
  • Recognized Tool for Prioritization
  • Outside of Political Influence
  • Commitment to Prior Projects

14
Program Priority Matrix
  • 6 Factors
  • Scoring values 1 thru 5
  • Weighting values 1 thru 6
  • Highest Score

15
Program Priority Matrix
  • Factors Weightings
  • Accident Data 6
  • Data collected from City, Sheriff,
  • LSU, and State Police Departments
  • Highest score to highest number of
  • accidents for period 2004 and 2005
  • Utilization 5
  • Average Daily Traffic (ADT) for 2030
  • from Trans-Model was used
  • Highest score given to highest ADT

16
Program Priority Matrix
  • Factors Weightings
  • Right-of-Way 4
  • Availability of ROW to construct
  • the proposed section
  • Highest score to projects where ROW
  • exists
  • Project Cost 3
  • Total Project Cost was determined
  • Highest score to projects with lowest
  • Total Project Cost

17
Program Priority Matrix
  • Factors Weightings
  • Funding Potential 2
  • Potential for future funding from FHWA,
  • State, LaDOTD Swap, Urban Systems, CMAQ
  • Highest score to lowest funding potential
  • Environmental Permitting 1
  • Environmental and Permitting concerns were
  • evaluated
  • Highest score to projects with no concern

18
Priority Matrix
19
Initial Allocation of 125M Bond Sale
  • 6 Projects Funded for Construction
  • Central Thruway
  • Comite Drive
  • ONeal Lane
  • Picardy Avenue
  • South Choctaw Drive
  • South Harrells Ferry Road

20
Final Allocation of 125M Bond Sale
  • 5 Projects Funded for Construction
  • Burbank Drive Segment 1
  • Burbank Drive Segment 2
  • Downtown Signalization
  • Foster _at_ Government
  • Veterans Memorial Boulevard Extension

21
Final Allocation of 125M Bond Sale
  • 8 Projects Funded for ROW Acquisitions
  • Coursey _at_ Sherwood Forest
  • Essen Lane _at_ I-10
  • Lobdell Improvements
  • McHugh Road

22
Final Allocation of 125M Bond Sale
  • 8 Projects Funded for ROW Acquisitions
  • North Harrells Ferry Road
  • Perkins _at_ Stanford/Acadian
  • South Harrells Ferry Road
  • Stumberg Extension

23
Final Allocation of 125M Bond Sale
  • 11 Projects Funded for Engineering
  • Brightside Lane
  • Elm Grove Garden
  • Fairchild-Badley Road
  • Ford Street
  • Highland Road
  • Old Hammond Highway Segment 2

24
Final Allocation of 125M Bond Sale
  • 11 Projects Funded for Engineering
  • ONeal Lane Segment 1
  • Siegen Lane
  • Staring Lane
  • Staring Lane Extension 1
  • Sullivan Road

25
  • Green Light Program has
  • recommended over 125M in appropriations through
  • the end of 2007

26
(No Transcript)
27
  • http//greenlight.csrsonline.com

28
BUILDING BETTER ROADS FOREAST BATON ROUGE