Title: Installation Process for Family Nutrition Kit
1(No Transcript)
2Installation Process for Family Nutrition Kit
Packed FNK
3Installation Process for Family Nutrition Kit
2
- Unpacked FNK
- 20 Ltrs. Water Bag.
- Siphon Supply line with Siphon Pump, Filter
Element On/Off Valve. - Assembled Sub-main Line with Four Laterals (5
meters long) and 44 nos. pre-installed micro-tube
emitters.
1
3
4Installation Process for Family Nutrition Kit
- Layout of Sub-main line with Four Lateral Line
5Installation Process for Family Nutrition Kit
- Layout of Laterals with pre-installed Micro-tube
Emitters
6Installation Process for Family Nutrition Kit
- Connect the Siphon Line (Main Supply Line) to the
Tee Connector Located at the Center of Sub-main
Line
7Installation Process for Family Nutrition Kit
- Fix of a Stand Frame of Bamboo/Wood or Metal.
- Hang the Water Bag keeping distance ½ Meter from
the ground level.
½ Meter
8Installation Process for Family Nutrition Kit
- Put the Siphon Line (Main Supply) Line into the
Water Bag. - See that Filter Element should placed inside
bottom of the Water Bag and tie the siphon
line with stand frame to keep in position.
9Installation Process for Family Nutrition Kit
10Installation Process for Family Nutrition Kit
- Before pressing the siphon pump, make sure that
on/off valve is in close position. Press siphon
pump 2 to 3 times and then open the on/off valve.
The water will start flowing slowly from water
bag to sub-main line lateral lines. The flow
of water will cause the lay flat tubes to get
inflated .
11Installation Process for Family Nutrition Kit
- Water will start to flow out from all micro tube
emitters. There are eleven number of micro tubes
pre installed in each lateral. The length of
each lateral line is 5meter. The micro tube
emitters are fixed to the lateral at distance of
45cm. The inside diameter of each micro tube is
1.2mm and length of each micro tube is 20cm.
12Installation Process for Laterals Micro-tube
Emitters
- Hold the Lateral line and insert the 16 mm lock
sleeve (cut piece of 1 mm thick Lateral Tube)
16 mm Lock Sleeves
13Installation Process for Laterals Micro-tube
Emitters
- Slide the Lateral over the Tee Connector
(already fixed in sub-main line). Then move the
lock sleeve over the Tee Connector. This process
will lock the lateral with sub-main Line.
14Installation Process for Laterals Micro-tube
Emitters
- The Laterals are required to be punched before
inserting micro-tube emitters. And before
punching hole the laterals required to be
inflated with water. Use plastic punch or thorn
to punch hole.
15Installation Process for Laterals Micro-tube
Emitters
- Insert the micro-tube emitters into Lateral
towards downward stream. Ensure the micro-tube
emitters should be 50 cm inside the lateral.