Title: Cavity WorkPackage in EDR phase
1Cavity Work-Package in EDR phase
- H. Hayano 01282008 for Lutz Lilje
2Cavity Work-Package Definition
- WP-C1 Gradient performance
- WP-C2 Fabrication
- WP-C3 Preparation
- WP-C4 Cavity Design
3WP-C1 Gradient performance
- Tight-loop effort
- Production-like effort
- Preparation for ultimate cavity batch
- Single cell program
- Common performance evaluation
- Gradient proposal for EDR
4WP-C1-1 Tight-loop effort
- Finalize the tight-loop process
- Package should demonstrate repeatability with in
each participating lab. Then an inter-laboratory
comparison should follow facilitated by cavity
exchange. Re-evaluation whether second loop is
needed. - Cavity treatment and testing. Measurement data.
Data comparison. - 2-3 SCRF labs(FNAL, JLab, KEK, DESY), 3 cavities
per lab, 3 tests each cavity. - milestones
- All cavities tested by mid of 2008.
- Data comparison by fall 2008.
- Re-evaluation by fall 2008.
5WP-C1-2 Production-like effort
- 1. Treat 30 cavities with EP ethanol process
- Repeat process (If needed in case of
underperformance) at least once. Apply T-map on
as many cavities as possible, at least all
cavities below 30 MV/m. - Deliverables Cavity treatment and testing.
Measurement data. - SCRF labs(FNAL, DESY), 30 cavities.
- Milestones All cavities tested by end of 2008.
- 2. Treat 20-30 cavities with EP Degrease
- Repeat process.(same above)
- Deliverables (same above)
- SCRF labs(FNAL, Jlab, KEK, DESY), 20-30 cavities.
- Milestones All cavities tested by end of 2008.
- 3. Treat 10-20 cavities with EP fresh EP
- Repeat process (same above)
- Deliverables (same above)
- SCRF labs(Jlab, KEK), 10 cavities.
- Milestones All cavities tested by end of 2009.
6WP-C1-3 Preparation for ultimate cavity batch
- 1. Evaluate data from tight-loop and production
data - Overall evaluation of data available by end of
2009. - Deliverables Report on data comparison.
Recommendation for ILC cavity process. - Candidate labs(FNAL), by Database and Scientist.
- Milestones Report and recommendation by end of
2009. - 2. Treat 30 cavities with ILC process
- Repeat process (If needed in case of
underperformance) at least once. Apply T-map on
as many cavities as possible, at least all
cavities below 30 MV/m. - Deliverables Cavity treatment and testing.
Measurement data. - Candidate labs(FNAL, KEK), 30 cavities.
- Milestones All cavities tested by end of 2010.
7WP-C1-4 Single cell Program
8WP-C1-5 Common performance evaluation
- 1. Database setup
- Develop basis for an ILC database. Review
existing database. Choose common database system. - Deliverables Database for cavity process and
testing data. - Candidate labs(FNAL, Jlab, KEK, DESY), by
Scientist and IT engineer. - Milestones Evaluation by end of 2007. Choice of
database by spring 2008, Database in place by mid
2008. - 2. Data evaluation between laboratory
- Develop schemes for inter-laboratory data
evaluation. Evaluation of data sets available.
Define data sets requested from labs. Compare
data analysis done by participating labs.
Evaluate data relevant for ILC project. - Deliverables Report on evaluation of existing
data sets. Proposal for data sets. - Candidate labs(FNAL, Jlab, KEK, DESY), by
Scientist. - Milestones Report on evaluation by end of 2007.
Proposal for database by mid 2008.
9WP-C1-6 Gradient proposal for the EDR
- 1. Definition of vertical test gradient
specification for ILC - Re-visit Snowmass and S0 specification. Take into
account more flexible power distribution. Develop
a final specification for vertical test assuming
an operational gradient of 31.5MV/m in the
machine. - Deliverables Report on tolerable gradient spread
in ILC (together with Main Linac and LLRF). Final
specification. - by Scientists.
- Milestones Report on tolerable gradient spread
by end of 2007. Final ILC specification for
gradient spread in vertical tests by mid 2008. - 2. Final proposal for ILC gradient
- Data evaluation of all existing data by end of
2009. Report with proposal for ILC gradient by
end of 2009. - Deliverables Report.
- by S0 task force.
- Milestones Report by end of 2009.
10WP-C2 Fabrication
- Material
- Alternative materials
- Fabrication method
- HPV regulation
11WP-C2-1 Material
- 1. Material specification
- Develop full specification for ILC baseline
fine-grain niobium material. Review XFEL
specification. - Deliverables specification for cavity material.
- by Scientists, engineer of FNAL, Jlab, KEK, DESY.
- Milestones Specification ready by 2011.
12WP-C2-2 Alternative Materials
- 1. Large grain cost evaluation
- Review available material on large grain niobium
material cost. Investigate cost effective cutting
methods. - Deliverables Report on cost difference for
large-grain material. - by Scientists, engineer of FNAL, Jlab, KEK, DESY.
- Milestones Report ready by 2008.
- 2. Large grain multi-cell cavity development and
testing - Built and test several multi-cell cavities.
Repeat process (If needed in case of
underperformance) at least once. Apply T-map on
as many cavities as possible, at least all
cavities below 30 MV/m. Comparison of different
surface treatments on multi-cell cavities. - Deliverables Cavity treatment and testing.
Measurement data. Report of data comparison with
baseline material. Material specification. - Candidate labs(Jlab, DESY), 10-20 cavities. 2
tests each cavity. - Milestones All cavities tested by mid of 2010.
Data comparison by fall 2010. Final report by end
2010.
13WP-C2-3 Fabrication method
- 1. Analysis of EBW performance
- Evaluate available data on performance of EB
welds by both established and new cavity vendors.
Include laboratory in-house fabrications where
appropriate. Implementation of sufficient
diagnostic capability in participating labs (e.g.
temperature mapping). Development of cavity
autopsy for the weld region on defective cavities
(destructive or non-destructive). - Deliverables Report on performance of EB welds.
T-mapping for diagnostics. Method of defect
detection in weld region. - by Scientists, engineer, and SCRF labs.
- Milestones Report until mid 2008. T-mapping
diagnostics by mid 2008. Method by 2009. - 2. EBW specification
- Review XFEL specification for EBW. Develop
additional qulity control for EBW at companies.
Write specification. - Deliverables Specification.
- by scientists.
- Milestones specification by end of 2008.
14WP-C2-4 HPV regulation
- 1. HPV regulation
- Develop common understanding of requirements to
fulfil high-pressure vessel code regulations
especially for how to deal with niobium material.
- Deliverables
- by .
- Milestones
15WP-C3 Preparation
- Baseline process
- Alternatives
16WP-C3-1 Baseline process
- 1. Process specification
- Develop full specification for ILC surface
process. Review XFEL cavity surface process. - Deliverables specification for cavity process.
EP, HPR, assembly and QA thereof. - by Scientists engineer at FNAL, Jlab, KEK, DESY.
- Milestones Specification ready by 2011.
- 2. Surface Analysis in support of baseline
process - Review ongoing RD activities on niobium RF
surfaces. Develop program to improve QC for ILC
surface process. - Deliverables Development of an RD program.
Managing program with supporting institutes. - by Scientists engineer at Jlab, Cornell.
- Milestones Program ready by mid 2008.
17WP-C3-2 Alternatives
- 1. Tumbling
- Evaluate whether tumbling as an additional
intermediate process step for a cavity is
necessary to achieve more homogeneous
performance. - Deliverables Comparative study on cavities with
and without tumbling (possibly on single cells). - by Scientists of KEK, by single cell program.
- Milestones Report by end of 2008.
- 2. Dry-Ice
- Evaluate whether dry-ice cleaning as an
additional intermediate process step for a cavity
with main coupler is feasible. Demonstrate
proof-of-principle. - Deliverables Report on feasibility.
Proof-of-principle. - by Scientists.
- Milestones Report by end of 2008.
18WP-C4 Cavity Design
- Specification of outer envelope
- Preparation for the cavity shape decision
- Lorentz detuning concept
- Beam dynamics
19WP-C4-1 Specification of outer envelope
- 1. Outer diameter, length
- Evaluation of existing designs. Technical
comparisons of the designs. Define the outer
boundary of the cavity. - Deliverables specification.
- by Engineer.
- Milestones Complete specification by Sendai
meeting. - 2. Sealing technology
- Review existing seal designs. Make technical
comparison. Make recommendation for common
interface. Finalise specification. - Deliverables Review report. Recommendation.
Specification. - by Engineer.
- Milestones Complete review report by Sendai
meeting. - 3. Input port diameter
- Review existing port design and high power
couplers. Make technical comparison (needs
definition of criteria). Make recommendation for
common coupler port. Finalise specification. - Deliverables Review report. Recommendation.
Specification. - by Engineer.
- Milestones Complete review report by Sendai
meeting.
20WP-C4-2 Preparation of the cavity shape decision
- 1. Definition of tests
- Review existing cavity design. Define required
testing based on Cavity KOM discussion. Develop a
detailed schedule to prove a cavity shape can be
used in ILC. - Deliverables Review report, report on required
testing, Schedule. - by Scientists, engineer.
- Milestones Review report by end of 2007. Report
on required testing by 2007. Detailed schedule by
mid 2008. - 2. Testing of cavity shape alternatives
- Design ILC-compatible alternative shape cavity.
Build and test compatible cavities with
alternative shapes. Preparation and surface
preparation of a number of cavities required by
WP above. Repeat vertical tests (if needed in
case of underperformance) at least once. Apply
T-map on as many cavities as possible, at least
all cavities below 30 MV/m. - Deliverables Design of an ILC compatible
alternative shape cavity. Cavity treatment and
testing. Measurement data. - One SCRF lab (Jlab, KEK, Cornell) per cavity
shape, . - Milestones Alternative design by beginning of
2008. Additional milestones according to what has
been defined.
21WP-C4-3 Lorentz detuning concept
- 1. Evaluation of tests
- Review existing Lorentz-force compensation
concepts. Comparison of technical concepts
including the relevant tuner design. Proposal for
a common concept. - Deliverables Review report. Proposal for a
common concept. - by Scientists, engineer.
- Milestones Review report by end of 2007.
Proposal by mid 2008.
22WP-C4-4 Beam dynamics
- 1. HOM concept
- 2. Wake fields
- 3. Alignment
- 4. Straightness
23DESY activity status
- 1. S0 cavity treatment
- 5-th product batch 15 ZANON, 15 ACCEL -gt EP
training of HENKEL and ACCEL. - Helium tank welding before vertical test (XFEL
scenario). Final process will be compared for
Short etch and EPethanol rinse. - 3 batch 10 cavities Short etch, 10 cavities
EP ethanol, 10 decide later. - 30 cavities testing by mid 2008. Two cavity
vendors comparison. - AC71,AC74,AC80 are put into tight-loop.
- 2. Cavity package alternatives
- 8 new large-grain cavities are available in late
2008, will be tested by end of 2008. - 11 large-grain cavities( 8 new 3 existing) will
receive final process of EPethanol rinse.
24DESY activity status (cont.)
- 3. S1 module tests
- A series of modules will be assembled and/or
tested - 1. M3 (TTF 2 type cryostat) in early 2008
- Test to conform with pressure
vessel code (possibly destructive) - 2. M8 (TTF 3 ) in spring 2008 ( plan was
changed to go Saclay first, back to DESY later) - Normal module test including
piezo tuners, Transport, - Second test to check
performance - 3. M3
- After repair with a gradient
goal of at least 25 MV/m as spare for FLASH. - Piezo tuners added
- 4. M10 (XFEL Prototype) assembly autumn 2008,
- gradient goal gt25 MV/m
- At least the M8 string could deliver ILC-like
performance. The test will be made by mid 2008,
so that additional input for S1 would be
available. - Independent of the module performance tests, both
the transport test for M8, - and the test for the pressure vessel code with
M3 are of major importance for the ILC.
25US activity status
- 1. S0 cavity treatment
- Jlab 30 cycle of EP/VT per year.
AC6(38MV/m),AC7(32MV/m) 4 cycles as S0. AC8
started as S0. - KEK Ichiro5(30-20MV/m) started as S0.
AES001,002,003,004 evaluation(16-32MV/m). - Cornell 1 cycle per month. AC8(28MV/m),AC9(25MV/m
) are under qualified. 9-cell re-entrant work.
AES new EBW qualification with five 1 cell
(425MV/m, 117MV/m). - New cavity plan AC10-17(8 cavities),
AES005-010(6 cavities) delivery end of 2007. - AES011-016(6 cavities)
are ordered. - 2. S1 module tests
- First cryomodule is ready for test. Next
cryomodule ? - 3. Infra-structure
- ANL-EP commissioned with 1 cell. FNAL HPR under
construction. - CAF-ICB (cryomodule assembly facility at ICB)
two assembly fixtures. - FNAL VT commissioned with AES001 cavity.
- AES new EBW is qualified.
- New cavity vender PAVAC (Canada) is under
qualifying.