Title: Cavity WorkPackage in EDR phase


1
Cavity Work-Package in EDR phase
  • H. Hayano 01282008 for Lutz Lilje

2
Cavity Work-Package Definition
  • WP-C1 Gradient performance
  • WP-C2 Fabrication
  • WP-C3 Preparation
  • WP-C4 Cavity Design

3
WP-C1 Gradient performance
  • Tight-loop effort
  • Production-like effort
  • Preparation for ultimate cavity batch
  • Single cell program
  • Common performance evaluation
  • Gradient proposal for EDR

4
WP-C1-1 Tight-loop effort
  • Finalize the tight-loop process
  • Package should demonstrate repeatability with in
    each participating lab. Then an inter-laboratory
    comparison should follow facilitated by cavity
    exchange. Re-evaluation whether second loop is
    needed.
  • Cavity treatment and testing. Measurement data.
    Data comparison.
  • 2-3 SCRF labs(FNAL, JLab, KEK, DESY), 3 cavities
    per lab, 3 tests each cavity.
  • milestones
  • All cavities tested by mid of 2008.
  • Data comparison by fall 2008.
  • Re-evaluation by fall 2008.

5
WP-C1-2 Production-like effort
  • 1. Treat 30 cavities with EP ethanol process
  • Repeat process (If needed in case of
    underperformance) at least once. Apply T-map on
    as many cavities as possible, at least all
    cavities below 30 MV/m.
  • Deliverables Cavity treatment and testing.
    Measurement data.
  • SCRF labs(FNAL, DESY), 30 cavities.
  • Milestones All cavities tested by end of 2008.
  • 2. Treat 20-30 cavities with EP Degrease
  • Repeat process.(same above)
  • Deliverables (same above)
  • SCRF labs(FNAL, Jlab, KEK, DESY), 20-30 cavities.
  • Milestones All cavities tested by end of 2008.
  • 3. Treat 10-20 cavities with EP fresh EP
  • Repeat process (same above)
  • Deliverables (same above)
  • SCRF labs(Jlab, KEK), 10 cavities.
  • Milestones All cavities tested by end of 2009.

6
WP-C1-3 Preparation for ultimate cavity batch
  • 1. Evaluate data from tight-loop and production
    data
  • Overall evaluation of data available by end of
    2009.
  • Deliverables Report on data comparison.
    Recommendation for ILC cavity process.
  • Candidate labs(FNAL), by Database and Scientist.
  • Milestones Report and recommendation by end of
    2009.
  • 2. Treat 30 cavities with ILC process
  • Repeat process (If needed in case of
    underperformance) at least once. Apply T-map on
    as many cavities as possible, at least all
    cavities below 30 MV/m.
  • Deliverables Cavity treatment and testing.
    Measurement data.
  • Candidate labs(FNAL, KEK), 30 cavities.
  • Milestones All cavities tested by end of 2010.

7
WP-C1-4 Single cell Program
  • 1. To be discussed.

8
WP-C1-5 Common performance evaluation
  • 1. Database setup
  • Develop basis for an ILC database. Review
    existing database. Choose common database system.
  • Deliverables Database for cavity process and
    testing data.
  • Candidate labs(FNAL, Jlab, KEK, DESY), by
    Scientist and IT engineer.
  • Milestones Evaluation by end of 2007. Choice of
    database by spring 2008, Database in place by mid
    2008.
  • 2. Data evaluation between laboratory
  • Develop schemes for inter-laboratory data
    evaluation. Evaluation of data sets available.
    Define data sets requested from labs. Compare
    data analysis done by participating labs.
    Evaluate data relevant for ILC project.
  • Deliverables Report on evaluation of existing
    data sets. Proposal for data sets.
  • Candidate labs(FNAL, Jlab, KEK, DESY), by
    Scientist.
  • Milestones Report on evaluation by end of 2007.
    Proposal for database by mid 2008.

9
WP-C1-6 Gradient proposal for the EDR
  • 1. Definition of vertical test gradient
    specification for ILC
  • Re-visit Snowmass and S0 specification. Take into
    account more flexible power distribution. Develop
    a final specification for vertical test assuming
    an operational gradient of 31.5MV/m in the
    machine.
  • Deliverables Report on tolerable gradient spread
    in ILC (together with Main Linac and LLRF). Final
    specification.
  • by Scientists.
  • Milestones Report on tolerable gradient spread
    by end of 2007. Final ILC specification for
    gradient spread in vertical tests by mid 2008.
  • 2. Final proposal for ILC gradient
  • Data evaluation of all existing data by end of
    2009. Report with proposal for ILC gradient by
    end of 2009.
  • Deliverables Report.
  • by S0 task force.
  • Milestones Report by end of 2009.

10
WP-C2 Fabrication
  • Material
  • Alternative materials
  • Fabrication method
  • HPV regulation

11
WP-C2-1 Material
  • 1. Material specification
  • Develop full specification for ILC baseline
    fine-grain niobium material. Review XFEL
    specification.
  • Deliverables specification for cavity material.
  • by Scientists, engineer of FNAL, Jlab, KEK, DESY.
  • Milestones Specification ready by 2011.

12
WP-C2-2 Alternative Materials
  • 1. Large grain cost evaluation
  • Review available material on large grain niobium
    material cost. Investigate cost effective cutting
    methods.
  • Deliverables Report on cost difference for
    large-grain material.
  • by Scientists, engineer of FNAL, Jlab, KEK, DESY.
  • Milestones Report ready by 2008.
  • 2. Large grain multi-cell cavity development and
    testing
  • Built and test several multi-cell cavities.
    Repeat process (If needed in case of
    underperformance) at least once. Apply T-map on
    as many cavities as possible, at least all
    cavities below 30 MV/m. Comparison of different
    surface treatments on multi-cell cavities.
  • Deliverables Cavity treatment and testing.
    Measurement data. Report of data comparison with
    baseline material. Material specification.
  • Candidate labs(Jlab, DESY), 10-20 cavities. 2
    tests each cavity.
  • Milestones All cavities tested by mid of 2010.
    Data comparison by fall 2010. Final report by end
    2010.

13
WP-C2-3 Fabrication method
  • 1. Analysis of EBW performance
  • Evaluate available data on performance of EB
    welds by both established and new cavity vendors.
    Include laboratory in-house fabrications where
    appropriate. Implementation of sufficient
    diagnostic capability in participating labs (e.g.
    temperature mapping). Development of cavity
    autopsy for the weld region on defective cavities
    (destructive or non-destructive).
  • Deliverables Report on performance of EB welds.
    T-mapping for diagnostics. Method of defect
    detection in weld region.
  • by Scientists, engineer, and SCRF labs.
  • Milestones Report until mid 2008. T-mapping
    diagnostics by mid 2008. Method by 2009.
  • 2. EBW specification
  • Review XFEL specification for EBW. Develop
    additional qulity control for EBW at companies.
    Write specification.
  • Deliverables Specification.
  • by scientists.
  • Milestones specification by end of 2008.

14
WP-C2-4 HPV regulation
  • 1. HPV regulation
  • Develop common understanding of requirements to
    fulfil high-pressure vessel code regulations
    especially for how to deal with niobium material.
  • Deliverables
  • by .
  • Milestones

15
WP-C3 Preparation
  • Baseline process
  • Alternatives

16
WP-C3-1 Baseline process
  • 1. Process specification
  • Develop full specification for ILC surface
    process. Review XFEL cavity surface process.
  • Deliverables specification for cavity process.
    EP, HPR, assembly and QA thereof.
  • by Scientists engineer at FNAL, Jlab, KEK, DESY.
  • Milestones Specification ready by 2011.
  • 2. Surface Analysis in support of baseline
    process
  • Review ongoing RD activities on niobium RF
    surfaces. Develop program to improve QC for ILC
    surface process.
  • Deliverables Development of an RD program.
    Managing program with supporting institutes.
  • by Scientists engineer at Jlab, Cornell.
  • Milestones Program ready by mid 2008.

17
WP-C3-2 Alternatives
  • 1. Tumbling
  • Evaluate whether tumbling as an additional
    intermediate process step for a cavity is
    necessary to achieve more homogeneous
    performance.
  • Deliverables Comparative study on cavities with
    and without tumbling (possibly on single cells).
  • by Scientists of KEK, by single cell program.
  • Milestones Report by end of 2008.
  • 2. Dry-Ice
  • Evaluate whether dry-ice cleaning as an
    additional intermediate process step for a cavity
    with main coupler is feasible. Demonstrate
    proof-of-principle.
  • Deliverables Report on feasibility.
    Proof-of-principle.
  • by Scientists.
  • Milestones Report by end of 2008.

18
WP-C4 Cavity Design
  • Specification of outer envelope
  • Preparation for the cavity shape decision
  • Lorentz detuning concept
  • Beam dynamics

19
WP-C4-1 Specification of outer envelope
  • 1. Outer diameter, length
  • Evaluation of existing designs. Technical
    comparisons of the designs. Define the outer
    boundary of the cavity.
  • Deliverables specification.
  • by Engineer.
  • Milestones Complete specification by Sendai
    meeting.
  • 2. Sealing technology
  • Review existing seal designs. Make technical
    comparison. Make recommendation for common
    interface. Finalise specification.
  • Deliverables Review report. Recommendation.
    Specification.
  • by Engineer.
  • Milestones Complete review report by Sendai
    meeting.
  • 3. Input port diameter
  • Review existing port design and high power
    couplers. Make technical comparison (needs
    definition of criteria). Make recommendation for
    common coupler port. Finalise specification.
  • Deliverables Review report. Recommendation.
    Specification.
  • by Engineer.
  • Milestones Complete review report by Sendai
    meeting.

20
WP-C4-2 Preparation of the cavity shape decision
  • 1. Definition of tests
  • Review existing cavity design. Define required
    testing based on Cavity KOM discussion. Develop a
    detailed schedule to prove a cavity shape can be
    used in ILC.
  • Deliverables Review report, report on required
    testing, Schedule.
  • by Scientists, engineer.
  • Milestones Review report by end of 2007. Report
    on required testing by 2007. Detailed schedule by
    mid 2008.
  • 2. Testing of cavity shape alternatives
  • Design ILC-compatible alternative shape cavity.
    Build and test compatible cavities with
    alternative shapes. Preparation and surface
    preparation of a number of cavities required by
    WP above. Repeat vertical tests (if needed in
    case of underperformance) at least once. Apply
    T-map on as many cavities as possible, at least
    all cavities below 30 MV/m.
  • Deliverables Design of an ILC compatible
    alternative shape cavity. Cavity treatment and
    testing. Measurement data.
  • One SCRF lab (Jlab, KEK, Cornell) per cavity
    shape, .
  • Milestones Alternative design by beginning of
    2008. Additional milestones according to what has
    been defined.

21
WP-C4-3 Lorentz detuning concept
  • 1. Evaluation of tests
  • Review existing Lorentz-force compensation
    concepts. Comparison of technical concepts
    including the relevant tuner design. Proposal for
    a common concept.
  • Deliverables Review report. Proposal for a
    common concept.
  • by Scientists, engineer.
  • Milestones Review report by end of 2007.
    Proposal by mid 2008.

22
WP-C4-4 Beam dynamics
  • 1. HOM concept
  • 2. Wake fields
  • 3. Alignment
  • 4. Straightness

23
DESY activity status
  • 1. S0 cavity treatment
  • 5-th product batch 15 ZANON, 15 ACCEL -gt EP
    training of HENKEL and ACCEL.
  • Helium tank welding before vertical test (XFEL
    scenario). Final process will be compared for
    Short etch and EPethanol rinse.
  • 3 batch 10 cavities Short etch, 10 cavities
    EP ethanol, 10 decide later.
  • 30 cavities testing by mid 2008. Two cavity
    vendors comparison.
  • AC71,AC74,AC80 are put into tight-loop.
  • 2. Cavity package alternatives
  • 8 new large-grain cavities are available in late
    2008, will be tested by end of 2008.
  • 11 large-grain cavities( 8 new 3 existing) will
    receive final process of EPethanol rinse.

24
DESY activity status (cont.)
  • 3. S1 module tests
  • A series of modules will be assembled and/or
    tested
  • 1. M3 (TTF 2 type cryostat) in early 2008
  • Test to conform with pressure
    vessel code (possibly destructive)
  • 2. M8 (TTF 3 ) in spring 2008 ( plan was
    changed to go Saclay first, back to DESY later)
  • Normal module test including
    piezo tuners, Transport,
  • Second test to check
    performance
  • 3. M3
  • After repair with a gradient
    goal of at least 25 MV/m as spare for FLASH.
  • Piezo tuners added
  • 4. M10 (XFEL Prototype) assembly autumn 2008,
  • gradient goal gt25 MV/m
  • At least the M8 string could deliver ILC-like
    performance. The test will be made by mid 2008,
    so that additional input for S1 would be
    available.
  • Independent of the module performance tests, both
    the transport test for M8,
  • and the test for the pressure vessel code with
    M3 are of major importance for the ILC.

25
US activity status
  • 1. S0 cavity treatment
  • Jlab 30 cycle of EP/VT per year.
    AC6(38MV/m),AC7(32MV/m) 4 cycles as S0. AC8
    started as S0.
  • KEK Ichiro5(30-20MV/m) started as S0.
    AES001,002,003,004 evaluation(16-32MV/m).
  • Cornell 1 cycle per month. AC8(28MV/m),AC9(25MV/m
    ) are under qualified. 9-cell re-entrant work.
    AES new EBW qualification with five 1 cell
    (425MV/m, 117MV/m).
  • New cavity plan AC10-17(8 cavities),
    AES005-010(6 cavities) delivery end of 2007.
  • AES011-016(6 cavities)
    are ordered.
  • 2. S1 module tests
  • First cryomodule is ready for test. Next
    cryomodule ?
  • 3. Infra-structure
  • ANL-EP commissioned with 1 cell. FNAL HPR under
    construction.
  • CAF-ICB (cryomodule assembly facility at ICB)
    two assembly fixtures.
  • FNAL VT commissioned with AES001 cavity.
  • AES new EBW is qualified.
  • New cavity vender PAVAC (Canada) is under
    qualifying.