Title: Habitat Based Shoreline Stabilization
1Habitat Based Shoreline Stabilization
- Practical Techniques for Landowners
2Key Features of Stabilization
- Slope
- Habitat/Structure
- Soil Containment
- Toe Protection
3Key Features of Stabilization
- Slope
- Where feasible reduce slope to a minimum of 21
and a preferred 4 or 51 - Pull back of slope is preferable
- Cut and fill (minimized) to reach preferred slope
is permissible
4Slope
5Slope
6Key Features of Stabilization
- Habitat/Structure
- Vegetation of newly sloped back
- Native vegetation preferable
- Plant appropriate species and various inundation
levels - Add large woody debris at toe and along slope to
add bank complexity and anchoring structure for
future vegetation - Root wads and logs can be used for this purpose
7Habitat
8Habitat
9Key Features of Stabilization
- Soil Containment
- Use non-woven filter fabric under rip-rap to
contain soils from erosion - Water can still remove soils from projects
without use of filter fabrics - Filter fabrics can be easily planted through to
add vegetative components
10Soil Containment
11Soil Containment
12Key Features of Stabilization
- Toe Protection
- Use rip-rap to protect toe erosion and bank over
steepening - Plant the interstitial spaces of riprap to add
vegetative complexity - Use of rip-rap over the entire bank is not
necessary to protect shoreline erosion
13Toe Protection
14Toe Protection
15Cost Estimating
- Factors affecting estimation and costs
- Bank height
- Severity of condition (vertical or stepped)
- Existing vegetation on site
- Accessibility for heavy equipment
- Proximity to structures/ability to slope banks
- Contractor knowledge
- Contractor availability
- Material variability and cost volatility
16Cost Estimating
- Rip-rap - 30 per Yard _at_ up to 1 yd/linear ft. of
shoreline - Filter Fabric - 2 per foot _at_ 12 foot wide
- Staples - 50 per box (good for about 100)
- Plants - free to 10 each depending on size and
species - LWD free to ? Depends on location,
transportation costs, mill or local, etc - Labor - 13 to 20 per hour
- Heavy Equipment costs - 60 to 100 per hour
depending on type needed
17Cost Estimating
- Typical 100 foot section
- Low end - 25/linear foot
- High end - 90/linear foot
- Avg. cost 50/linear foot
- Typical 100 homeowner looking at an investment
of about 5,000 on average
18Project Example Tacoma Creek
19Project Example Tacoma Creek
20Project Example Tacoma Creek
21Project Example Hoodoo Creek
22Project Example Hoodoo Creek
23Project Example Hoodoo Creek
24Project Example Middle Creek
25Project Example Middle Creek
26Project Example Middle Creek