Title: THE UPGRADING OF THE JOHN ROSS HIGHWAY
1KWAZULU-NATAL DEPARTMENT OF TRANSPORT
THE UPGRADING OF THE JOHN ROSS HIGHWAY SARF
REGIONAL SEMINAR - 20 MAY 2009
2KWAZULU-NATAL DEPARTMENT OF TRANSPORT
1 Background 2 Project Scope
3 Socio-Economic Objectives 4
Engineering Features 5 Environmental
Management
3KWAZULU-NATAL DEPARTMENT OF TRANSPORT
1. BACKGROUND
4Planning History
- Existing John Ross Highway constructed in 1972 to
serve the proposed new harbour development.
5Planning History
- Existing John Ross Highway constructed in 1972 to
serve the proposed new harbour development. - In 1983 the recorded traffic on the JRH through
Empangeni Rail was 14 150 vehicles per day and at
the Alton intersection was 8 400 vpd.
6Planning History
- Existing John Ross Highway constructed in 1972 to
serve the proposed new harbour development. - In 1983 the recorded traffic on the JRH through
Empangeni Rail was 14 150 vehicles per day and at
the Alton intersection was 8 400 vpd. - During 1984 planning for capacity improvements
started as a traffic growth of 8 pa was
predicted.
7Planning History
- Existing John Ross Highway constructed in 1972 to
serve the proposed new harbour development. - In 1983 the recorded traffic on the JRH through
Empangeni Rail was 14 150 vehicles per day and at
the Alton intersection was 8 400 vpd. - During 1984 planning for capacity improvements
started as a traffic growth of 8 pa was
predicted. - A Basic Planning Report for the Doubling of the
JRH that would serve the future development of
Empangeni and Richards Bay was completed in 1985.
8Planning History
- Existing John Ross Highway constructed in 1972 to
serve the proposed new harbour development. - In 1983 the recorded traffic on the JRH through
Empangeni Rail was 14 150 vehicles per day and at
the Alton intersection was 8 400 vpd. - During 1984 planning for capacity improvements
started as a traffic growth of 8 pa was
predicted. - A Basic Planning Report for the Doubling of the
JRH that would serve the future development of
Empangeni and Richards Bay was completed in 1985. - A dual carriageway facility was planned that
would link a proposed northern bypass of
Empangeni to a proposed Harbour Arterial near
Alton at km 10.
9Mhlathuze Floodplain
- The 1985 Basic Planning Report predicted large
settlements beneath the fill across the
Mhlathuze Floodplain due to soft compressible
subsoils.
10Mhlathuze Floodplain
- The 1985 Basic Planning Report predicted large
settlements beneath the fill across the
Mhlathuze Floodplain due to soft compressible
subsoils. - Silty fine sands with clay and peat lenses overly
granites at depths varying between 10 and 100 m.
11Mhlathuze Floodplain
- The 1985 Basic Planning Report predicted large
settlements beneath the fill across the
Mhlathuze Floodplain due to soft compressible
subsoils. - Silty fine sands with clay and peat lenses overly
granites at depths varying between 10 and 100 m. - Settlements of up to 2 m were predicted and to
safeguard the integrity of the existing road it
was proposed to increase the median width to 52m.
12Mhlathuze Floodplain
- The 1985 Basic Planning Report predicted large
settlements beneath the fill across the
Mhlathuze Floodplain due to soft compressible
subsoils. - Silty fine sands with clay and peat lenses overly
granites at depths varying between 10 and 100 m. - Settlements of up to 2 m were predicted and to
safeguard the integrity of the existing road it
was proposed to increase the median width to 52m. - An early start and a slow rate of earthworks
construction together with a surcharge was
proposed.
13Mhlathuze Floodplain
- The 1985 Basic Planning Report predicted large
settlements beneath the fill across the
Mhlathuze Floodplain due to soft compressible
subsoils. - Silty fine sands with clay and peat lenses overly
granites at depths varying between 10 and 100 m. - Settlements of up to 2 m were predicted and to
safeguard the integrity of the existing road it
was proposed to increase the median width to 52m. - An early start and a slow rate of earthworks
construction together with a surcharge was
proposed. - It was subsequently decided to construct a 1,2 km
long bridge across the entire length of the
floodplain.
14Project Cost
- The original estimated construction cost was R
11,6 million (1985 Rands), and escalated at 12
pa over 25 years would now be R 197 million.
15Project Cost
- The original estimated construction cost was R
11,6 million (1985 Rands), and escalated at 12
pa over 25 years would now be R 197 million. - Despite the high traffic growth and predicted
good internal rate of return the provincial road
authority was not able to fund the project.
16Project Cost
- The original estimated construction cost was R
11,6 million (1985 Rands), and escalated at 12
pa over 25 years would now be R 197 million. - Despite the high traffic growth and predicted
good internal rate of return the provincial road
authority was not able to fund the project. - In 2001 the road was de-proclaimed as a
provincial road and DOT together with SANRA
proceeded to plan a toll road.
17Project Cost
- The original estimated construction cost was R
11,6 million (1985 Rands), and escalated at 12
pa over 25 years would now be R 197 million. - Despite the high traffic growth and predicted
good internal rate of return the provincial road
authority was not able to fund the project. - In 2001 the road was de-proclaimed as a
provincial road and DOT together with SANRA
proceeded to plan a toll road. - The 2002 construction cost estimate was then R
218 m but the toll road option was abandoned and
the road reverted back to the province.
18Project Cost
- The original estimated construction cost was R
11,6 million (1985 Rands), and escalated at 12
pa over 25 years would now be R 197 million. - Despite the high traffic growth and predicted
good internal rate of return the provincial road
authority was not able to fund the project. - In 2001 the road was de-proclaimed as a
provincial road and DOT together with SANRA
proceeded to plan a toll road. - The 2002 construction cost estimate was then R
218 m but the toll road option was abandoned and
the road reverted back to the province. - In 2005, after a number of commitments from other
funding sources the province agreed to proceed
with the project. The 2005 estimate was then R
308 m.
19KWAZULU-NATAL DEPARTMENT OF TRANSPORT
2. PROJECT SCOPE
20CBD
HARBOUR
KWAZULU-NATAL DEPARTMENT OF TRANSPORT
21Fact Sheet
- Description Upgrading of the John Ross
Highway between Empangeni and
Richards Bay - Design 4-lane dual carriageway urban
arterial, upgradable to 6-lane configuration
- Scope Construct new Eastbound
Carriageway - Rehabilitate Westbound Carriageway
- Total Length 16 km
- Total Project Cost R 877 million
- Spent to date R 388 million
- 2009/10 budget allocation R 170 m
- Completion Date 2011
22Funding Plan
23KWAZULU-NATAL DEPARTMENT OF TRANSPORT
3. SOCIO-ECONOMIC OBJECTIVES
24 Socio-Economic Objectives
- - Comply with EPWP requirements
- - Maximize opportunities for emerging
contractors and support their development - Maximize job opportunities for the local
unemployed - Develop the technical skills of contractors by
providing mentorship and training - - Give priority to the employment of women,
youth and people with disabilities
25Implementation Strategy
- Maximize the use of all stages of Vukuzakhe
contractors - Use hired plant for site preparations and to
maintain continuity of construction activities - Use labour contracts for ad hoc construction
activities - Purchase materials for grade 1 contractors using
KZN DOT annual contracts - Use experienced contractors in JV with emerging
contractors for the advanced construction
activities such as layerworks and major
structures
26EPWP LABOUR-INTENSIVE CONSTRUCTION
27GRADE 1 VUKUZAKHE CONTRACTOR
28EARTHWORKS BY VUKUZAKHE CONTRACTORS
29GRADE 4CEPE VUKUZAKHE CONTRACTOR
30VUKUZAKHE CONTRACTOR IN JV
31JV PARTNER GRADE 3 VUKUZAKHE CONTRACTOR
32Socio-Economic Outputs To Date
33 Skills Development Objectives
- To expose school learners to a construction
project that encourages them to consider a career
in engineering, and more specifically the road
construction industry. - To provide appropriate classroom and on site
practical training over 24 months to 15
learnership students. They are sponsored by KZN
DOT as part of the EPWP Vukuphile Learnership
Programme rolled out by DPW. - To present short courses such as carpentry, steel
fixing, shuttering, concreting, kerb laying,
concrete-lined drains, manholes and pipe laying
for local youth (NYS Programme) and for the
emerging contractors. - To provide opportunities for experiential
training for technikon students (8 students have
received inservice training to date) - Promote JV arrangements that facilitate the
transfer of skills in the workplace
34SCHOOL GROUPS
35ON SITE TRAINING
36HANDS ON TRAINING COURSES
37KWAZULU-NATAL DEPARTMENT OF TRANSPORT
4. ENGINEERING FEATURES
38MHLATHUZE FLOODPLAIN
39910 m
( 28 Spans )
up to 60 m deep piles
MHLATHUZE FLOODPLAIN BRIDGE
40MHLATHUZE FLOODPLAIN BRIDGE
41(No Transcript)
42LINK BRIDGE - PLAN
43300m
( 13 Spans )
NSEZI RIVER BRIDGE - PLAN
44NSEZI RIVER BRIDGE
45(No Transcript)
46Bridge Contracts
47(No Transcript)
48(No Transcript)
49(No Transcript)
50LAYERWORKS TO BE DONE BY JV CONTRACTORS
51 Access to the CBD and Harbour
52(No Transcript)
53(No Transcript)
54DIFFICULT GROUND CONDITIONS
55(No Transcript)
56(No Transcript)
57(No Transcript)
58Materials Used To Date
5918TH CULVERT
60(No Transcript)
61KwaMbonambi
Richards Bay
Empangeni
KFC
Gingindlovu
Proposed Improvements at Empangeni
62KWAZULU-NATAL DEPARTMENT OF TRANSPORT
5. ENVIRONMENTAL MANAGEMENT
63KWAMBONAMBI GRASSLAND
64REHABILITATION OF SAND BORROW PIT
65REHABILITATION OF CONSTRUCTION TRACKS
66(No Transcript)
67(No Transcript)
68(No Transcript)
69(No Transcript)
70KWAZULU-NATAL DEPARTMENT OF TRANSPORT
THANK YOU TO THE SOUTH AFRICAN ROAD
FEDERATION FOR GIVING US THE OPPORTUNITY TO SHARE
OUR EXPERIENCE WITH YOU