Title: By John Liedig
1Tower Crane
- By John Liedig Jouline Nour
2(No Transcript)
3Counter Weight
Cables
Main Tower
4Jib
5Introduction
- Tower cranes are a common fixture at any major
construction site. - They often rise hundreds of feet into the air,
and can reach out just as far. - Tower cranes are used to lift steel, concrete,
large tools like acetylene torches and
generators, and a wide variety of other building
materials.
6Arm and Tower Sections
Tower Section
Jib section
7Dimensions
- The tower crane is approximately 120m tall
- 10m wide
- The counter weighted arm is 60m long
- And the main jib can be as long as 90m
8Modelled Tower Crane
- Looked at 2 scenarios
- 2d
- 3d
- The aim was to determine the differences in both
2D and 3D cases in relation to displacement and
stress analysis
9Objectives
- To use Strand 7 on a complicated structure such
as a tower crane - Model the tower crane to the dimensions given
from relevant data - Determine stresses and displacements associated
from various locations of loads on the structure - Try and improve the structure
10Objectives
- To see if there was a better way of modelling the
tower crane on Strand 7 - Through using different materials
- Modifying the shape
11Method
- Determined the dimensions of the tower crane
using data from the internet and other relevant
crane construction guides - Determined various components involved in the
tower crane - Identified the materials for each of the various
components and then selected these from the
strand 7 library
12Method
- Drew a 2D representation of the tower then the
arm and then used strand 7 commands to convert
into a 3D structure - Entered various loading scenarios
- Ran analysis
- Modified the elements accordingly to meet
acceptable limits in the results.
13Materials
- The materials used were predominantly structural
steel of various sizes - The cable also is made from steel with a free
length ranging from 50 to 80m - All sections are circular hollow sections
14Load Cases
- Taken a variety of load cases
- Loads were placed at individual nodes along the
arm of the tower crane - In the final report the natural frequency is also
going to be considered but hasnt been included
now due to time constraints
15Simplifications
- The main simplifications were
- Simplifying the concrete counterweights into a
few point loads - Not having a pivoting base. I.e. the nodes at the
bottom of the tower are fixed in all directions
and rotations - The 3d case didnt incorporate the service crane
and the extra cables
162D Tower Crane
Service Crane
Cables
173D Tower Crane
Cables
Loads
Fixed Nodes
182D Displacement Analysis Case1
192D Displacement Analysis Case 2
20Displacement Analysis
1ST Case load at the end of the jib Maximum
displacement 1.5m
Loads counterweight 3x 30kN Jib 150kN
21Displacement Analysis 3D
Load case 2 Maximum Displacement 0.41m
Loads counterweight 4x 20kN Jib 150kN
22Displacement Analysis 3D
Third Load Case Maximum Displacement 0.6m
Loads counterweight 4x 20kN Jib 150kN
23Displacement Analysis
- The 2 and 3D cases give quite similar
displacements - Up to 1.5m depending on the loads applied
- The worst case is when the load is applied at the
end of the jib, which is what is to be expected.
24Stress Analysis
The stresses observed are not realistic ie. In
the thousands of MPa This result is evident in
all of the load cases
252D Stress Analysis Case 1
262D Stress Analysis Case 2
27Stress Analysis
- In all cases the stress is beyond the yield
strength of the steel used. - Therefore there are errors that need to be
corrected. - This will be done by making the critical tension
members solid and looking at the weights of each
member.
28Errors
- The main errors involved so far have been in
relation to the units associated with the loads
applied to the structure. - The high stress involved may be due to the weight
of the structure as a whole. - Initially we were faced with problems relating to
the stiffness matrix K. - This involved, free or unconnected elements and
also defining an element more than once in the
same position.
29Modifications
- Main modification factors are
- Modifying the cross-sections of some members to
decrease the high stresses observed - Wind load scenario
- Natural frequency analysis
- Seeing the effect of other materials and how they
affect the results.
30Thank you for listeningAny Questions??