Implementing Wave Energy - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

Implementing Wave Energy

Description:

Our mission is to develop solutions to community based ... Seal/Sea Lion Haul Out. Electromagnetic Fields. General Issues. Decommissioning. Anchor Removal ... – PowerPoint PPT presentation

Number of Views:39
Avg rating:3.0/5.0
Slides: 15
Provided by: ScottH99
Category:

less

Transcript and Presenter's Notes

Title: Implementing Wave Energy


1
Implementing Wave Energy
  • Process and Permitting Issues

Presented by Therese Hampton February 20, 2008
2
Oregon Solutions
  • Our mission is to develop solutions to community
    based problems that support sustainability
    objectives and are built through the
    collaborative efforts of business, government and
    non-profit organizations.
  • Problem or Opportunity Defined by the Community
  • Governors Designation
  • An Oregon Solutions team
  • An Integrated Solution
  • A Declaration of Cooperation

3
Reedsport as an Oregon Solutions Project
  • September 25, 2006Reedsport as Oregon Solutions
    Project
  • The Oregon Solutions team will facilitate a
    quicker, more effective application process with
    FERC.
  • Governor Ted Kulongoski
  • June 2007 Declaration of Cooperation
  • 22 signatories Federal, state and local
    organizations
  • Defined and documented Federal and State
    Regulatory Process
  • Developed a list of issues to be addressed
  • Key parties commitment to a settlement process

4
Summary of Stakeholder Issues
  • Aquatics Issues
  • Whale Entanglement
  • Alteration of Marine Habitat
  • Seal/Sea Lion Haul Out
  • Electromagnetic Fields
  • General Issues
  • Decommissioning
  • Anchor Removal
  • Crabbing/Fishing Issues
  • Lost Productivity
  • Lost gear
  • Navigation Safety
  • Recreation/Public Safety
  • Aesthetics (including lighting)
  • Surfing, Whale watching
  • System Survivability

5
FERC Licensing Process
  • Developed for relicensing of hydro facilities.
  • Estimated to be a 5-year process.
  • Includes extensive upfront work to agree upon and
    conduct studies for potential effect.
  • Potentially 2 years of study before license
    application.

6
Key Differences from Relicensing
  • Utility applicant versus new technology
    applicants needs.
  • History of hydro relicensing in the Northwest.
  • New versus existing facilities.
  • Existing use.
  • Location specific application requirement.

7
Applicant is Different
  • Traditional Utility
  • REVENUE Existing hydro resource is generating
    revenue throughout process.
  • NO RUSH No capital investment or other
    implementation costs incurred until new license
    is issued.
  • BELOW MARKET Hydro resource is likely well
    below market, even after relicensing.
  • CAN ABSORB COSTS
  • Guaranteed recovery of process costs, assuming
    they are reasonable.
  • Utility has broad resource and customer base to
    absorb process and investment costs.

8
Applicant is Different
  • New Technology Company
  • NO REVENUE No existing facilities to generate
    revenue. Company revenue provided by investors.
  • RUSH Company revenue is dependent on a project
    specific Power Purchase Agreement that doesnt
    generate revenue until the resource is
    operational.
  • ABOVE MARKET New resource, independent of
    process and implementation costs, is likely well
    above market.
  • CANT ABSORB COSTS
  • Company is actively investing capital in
    technology development.
  • No guaranteed recovery of process costs. Process
    costs will be absorbed into overall cost of
    resource, which is already above market.
  • At this point in development, there is no place
    to absorb costs.

9
Applicant is Different
  • Impact
  • New technology company has a desire for a much
    faster pace for settlement and permitting.
  • New technology company is more cost conscious
    relative to studies and operational measures.

10
Recent History in Relicensing
  • Many Northwest hydro relicensing projects have
    been long and adversarial. The relicensing
    process is characterized by
  • Lack of trust of the applicant
  • High process costs
  • Extensive studies
  • For some, discussion of removal of the project
  • Impact
  • Applicant is assumed to have utility
    characteristics.
  • The high process costs and extensive studies
    impacts the cost-conscious developer.
  • Discussion of project removal can impact investor
    confidence.

11
New versus Existing Facilities
  • The current FERC process is premised on
    multi-year studies to inform participants prior
    to license conditions.
  • A new facility/technology cannot be studied in
    this way
  • With wave energy, there are no existing
    structures to evaluate.
  • Further, there is very limited empirical data.
  • Methods for study arent clear.
  • Impact
  • Requires qualitative analysis with a
    forward-looking view of information needs.
  • Difficult for resource agencies to make long-term
    decision.
  • Requires a rigorous adaptive management program
    to address impacts once study results are known.

12
Existing Use
  • Existing ocean use by crabbing and fishing
    industry.
  • Existing ocean use by recreation.
  • Impact
  • Either opposition to the project or concern about
    level of overall development.
  • Interest in minimizing potential effect to
    existing uses.

13
Application is Location Specific
  • The FERC permit must be specific about location.
  • Further, the FERC permitting process grants
    priority to first applicant.
  • Given the impact to existing industry and
    recreation, stakeholders want to have input into
    site selection.
  • Impact
  • Encourages filing of preliminary permit to secure
    location.
  • Limits ability to engage collaboratively.
  • Tillamook has submitted a permit with multiple
    sites

14
Recommendations
  • Get to know the community engage with the
    locals and know what is important to them.
  • Be flexible in site location if possible, let
    the community play a role in the decision about
    where the site will be located.
  • Support regional environmental analysis the
    factors and impacts are fluid. Recognize this
    and encourage a process to address the Coastline.
  • Partnership Given the uncertainty, expect and
    plan to be in an ongoing collaborative process
    for many years.
Write a Comment
User Comments (0)
About PowerShow.com