MRWA Specification No 0403 Trench Backfill - PowerPoint PPT Presentation

1 / 37
About This Presentation
Title:

MRWA Specification No 0403 Trench Backfill

Description:

to eliminate risks associated with subsidence and collapse of sewer trench backfill ... Hence, roller optimum will vary from laboratory optimum. Laboratory Compaction ... – PowerPoint PPT presentation

Number of Views:359
Avg rating:3.0/5.0
Slides: 38
Provided by: Patrick527
Category:

less

Transcript and Presenter's Notes

Title: MRWA Specification No 0403 Trench Backfill


1
MRWA Specification No 04-03 Trench Backfill
  • Presented by
  • Max Ervin

2
Outline of presentation
  • Background
  • Principles of compaction
  • Selected definitions
  • General backfill requirements
  • Traffic areas
  • Cohesionless soils
  • Cohesive soils
  • Drives, shafts, tunnels and bores
  • Concluding remarks

3
Background
  • 2002
  • CWW introduced mechanical compaction requirement
  • flooding in practice was prohibited
  • to eliminate risks associated with subsidence and
    collapse of sewer trench backfill
  • 2003?
  • SEW develop specification
  • Higher standards than WSAA previously specified
  • Some resistance from industry
  • 2004
  • SEW ask Golder to review
  • Following review, Golder asked (2005) to redraft
    SEW specification
  • 2006
  • CWW ask Golder to assess whether SEW document can
    be adopted without change by CWW
  • Only minor drafting changes
  • Some comments re reactive ground and rock
  • Three Melbourne Retail Water Agencies adopted
    MRWA Backfill Specification No. 04-03.1 for all
    MRWA Capital Works and Land Development projects
    on 1 September 2006.

4
Need For Control of Trench Backfill
  • Historically trench backfill often poorly
    controlled
  • Negligible compaction, or only at surface
  • Watering in of clay (and sand) assumed effective
  • The inevitable steps/depressions in pavements
  • Heightened OH S issues
  • Litigation from trips and damage

5
Need For Control of Trench Backfill
  • Need to consider requirements early in project
    planning and implementation
  • MRWA Specification No 04-03 intended to provide
    guidance, as well as minimum requirements
  • Need reliable records
  • We live in a litigious world

6
Application
Specification No 04-03 only intended for
Trenchfill zone, and not Embedment zone
7
Principles of Compaction
  • Compaction
  • The process whereby the density of a soil mass
    is increased by mechanical (usually dynamic)
    means, by rearrangement of the soil particles and
    expulsion of air, usually with little alteration
    to water content
  • Consolidation
  • The process whereby the density of a soil mass
    increases under the natural action of gravity (a
    static force) due to self weight or an applied
    surcharge. Water usually expelled, and the
    process is time dependent.
  • Two very different processes. Should not be
    interchanged in Specifications or in discussion.
  • Note, nevertheless, the dependence of compaction
    on moisture content at time of compaction.

8
Compaction
  • Specified to provide-
  • higher shear strength
  • more predictable strength
  • lower compressibility
  • lower permeability
  • reduced susceptibility to water content changes
    (eg softening, swelling)
  • Desirable properties are mostly achieved at high
    density.
  • May not be the case in relation to reactivity
  • Hence there is a need to understand the moisture
    - density relationship

9
The compaction process
  • At the risk of seeming gratuitous-
  • low moisture- shearing resistance to movement of
    soil particles relative to each other is high,
    density increase difficult to achieve
  • increasing moisture- progressively easier to
    disturb the soil structure, and for same
    compactive effort higher density can be achieved
    up to a certain point
  • get peak in dry density - moisture relationship,
    after which simply increase void ratio, as voids
    fill with water
  • Hence the well known compaction curve and
    associated MDD and OMC

10
Compaction Curve
Note difficult to achieve better than about 2
air voids
11
Compaction
  • Maximum dry density and optimum moisture content
    are not unique properties of a given soil.
  • Are dependent
  • upon the energy input during compaction
  • the nature of the compactive effort.
  • Different soils will respond differently to the
    same compactive effort.
  • Hence, roller optimum will vary from laboratory
    optimum.

12
Laboratory Compaction
  • Cohesionless soils (clean sands) will not produce
    a compaction curve.
  • For these soils can measure a maximum and
    minimum density using standardized procedures,
    and then relate this to field density as Density
    Index, or relative density
  • Again maximum and minimum are not unique or
    extreme values.

13
Field Density Testing
  • To allow comparison of achieved compaction with
    laboratory values, need to be able to reliably
    assess field dry density and moisture content
  • Nuclear density gauges most common
  • Rapid, reasonably repeatable
  • Need to be calibrated
  • Moisture content usually in laboratory
  • Not non destructive as often assumed
  • In trenches need to get background count to
    provide for the confined space and possible
    influence of trench walls.

14
Relative Compaction
  • Usually reference to minimum dry density ratio
    (AS1289.5.4.1)
  • Ratio of FDD and MDD as DDR
  • Moisture variation from OMC may also be reported
  • Beware!
  • 2 OMC is wet for Standard
  • 2 variation is dry for Hilf
  • Can have moisture ratio also
  • Perth Sand Penetrometer may be used in
    cohesionless materials

15
Relative Compaction cont.
  • 04-03 generally calls up minimum dry density
    ratio
  • Not one test to fail criteria (as adopted by
    AS3798) has stood the test of time
  • empirically based performance criteria
  • allows for inherent variability
  • good supervision essential to have confidence in
    representative data
  • judgment necessary in interpretation
  • 04-03 provides guidance on interpretation of
    results

16
Rigour in Control Testing
  • If insufficient material able to be recovered
    from FDT site (eg shallow test)-
  • Additional material should be recovered from
    around the FDT site
  • Square sided hole
  • Sampling from elsewhere is unacceptable
  • Combining bulk samples is unacceptable

17
Rigour in Control Testing
  • A reference density should be established for
    each FDT
  • unless material is sufficiently uniform in its
    properties and compaction characteristics that
    any variability is solely due to test method
  • unlikely except for crushed rock from hard rock
    source
  • assigned value AS1289.5.4.2 then may be
    applicable

18
Rigour in Control Testing
  • AS1289 allows for removal of (and correction for)
    up to 20 coarse material in lab compaction test
  • A and B moulds
  • Does not recognise possible changes in compaction
    characteristics
  • More than this and test will lack relevance. A
    potential issue where ordinary fill being used
    in basalt rock country, for example, and may
    contain gt20 coarser than 37.5 mm

19
Properties of Compacted Fill - Reactivity
  • Reactive Soils Clay soils, for which a change in
    moisture content may result in sufficient change
    in volume to affect the engineering performance
    of any structures (including pavements)
    influenced by this soil.
  • Compacted clay fill may be more reactive than
    natural source material
  • Higher DDR, same relative moisture higher
    reactivity
  • Drier placement moisture, same DDR higher
    reactivity
  • Possibly need to consider specifying maximum DDR
  • Not easy to enforce

20
Properties of Compacted Fill - Reactivity
  • Increased reactivity when placed dry
  • Should aim to place at expected long term
    equilibrium
  • Not so easy in surface zone of seasonal moisture
    variation
  • Sand in embedment zone can allow deeper soils to
    wet up or dry out (swell or shrink)
  • Caution required when placing pipes near to
    houses or movement sensitive structures

21
Specn. 04-03- Selected definitions
  • Cohesionless Soils Poorly graded sand and gravel
    mixtures, generally with less than 5 fines (ie
    finer than 75 µm), which are non-plastic and
    which do not exhibit a well-defined
    moisture-density relationship when tested in
    accordance with AS 1289.5.1.1 or AS 1289.5.2.1.
    These will typically be clean sands.
  • Cohesive Soils Those materials which have a
    well-defined moisture-density relationship when
    tested in accordance with AS 1289.5.1.1 or AS
    1289.5.2.1. Whilst cohesive soils are typically
    clayey in nature, for the purpose of this
    definition these may also include well-graded
    granular materials such as crushed rock.
  • Ordinary Fill Material obtained from excavation,
    or imported, that contains not more than 20 by
    mass of rock fragments with size between 75 mm
    and 150 mm, with no rock or clay fragments
    greater than 150 mm.
  • SettlementSettlement is a downwards displacement
    of the ground surface, relative to either the
    surrounding ground (differential settlement) or a
    stable bench mark (total settlement). It is the
    result of a volume reduction in the ground
    beneath the surface, due to any of several
    possible mechanisms. (e.g. collapse,
    consolidation, (traffic) compaction). Sometimes
    called subsidence

22
Section 2. General Backfill Requirements
  • Contractor to be responsible for compliant
    backfill methodology, and for consequences (eg
    subsidence)
  • Alternative materials or methods subject to
    Superintendent prior approval
  • Safe working environment for testing
  • Testing by NATA accredited lab
  • Tester to choose test locations randomly
  • Contractor may only direct where he needs
    additional tests.
  • No testing above pipe within 500 mm of top of
    pipe. Otherwise beside pipe.
  • Superintendent to record test location. No work
    until tests show compliance

23
Section 3 Traffic Areas
  • Application- backfill material for trenches in
    all Traffic Areas, including
  • the full width of any existing or proposed road
    carriageway plus shoulders, and extending to one
    metre beyond the shoulders/kerb.
  • the full width of any property access driveway,
    and extending one metre either side.
  • the full length of any constructed footpath
    (including, but not limited to concrete, asphalt,
    crushed rock footpaths).
  • the full width of any median strip.
  • any other areas that are used as Traffic Areas.
  • Road authority requirements govern if they are
    more stringent

24
Section 3 Traffic Areas (cont)
  • Backfill material
  • In traffic areas, other than footpaths
  • For trenches less than 1.5 metres deep
  • 20 mm Class 2 Plant Mixed Wet Mix Crushed Rock,
    for the full depth.
  • For trenches 1.5 metres deep or greater,
  • 20 mm Class 2 Plant Mixed Wet Mix Crushed Rock
    for the top 600 mm.
  • 20 mm Class 4 (or better) Crushed Rock for the
    remainder, or other backfill material
    specifically approved by the Road Authority.
  • For trenches under footpaths
  • 20 mm Class 4 (or better) Crushed Rock, or other
    backfill material specifically approved by the
    Road Authority.
  • Backfill to be placed and compacted in layers
    200 mm loose thickness

25
Section 3 Traffic Areas (cont)
  • Compaction Testing
  • All road crossings to be tested
  • Base Course and Sub-base
  • For every 50 metre length of trench (or part
    thereof) three tests shall be taken
  • Within the top 100 mm (ie within the base course)
    of an existing road.
  • In the depth range 100 mm to 300 mm depth (ie
    within the pavement sub-base).
  • Backfill Under Roads, Road Shoulders, Median
    Strips (below sub-base)
  • For every 40 metre length of trench (or part
    thereof) one test shall be taken per two layers
    of backfill
  • Layers to be tested shall be selected randomly,
    in accordance with Clause 2.6. The position of
    the layer to be tested, and the location of the
    test, shall vary from test to test.
  • Adjacent layers shall not be selected for
    testing.
  • Backfill Under Footpaths
  • As for roads, except that the testing shall be
    for every 100 metre length of trench (or part
    thereof).
  • Note overall Contractor responsibility for
    performance (Cl. 2.2)

26
Section 3 Traffic Areas (cont)
  • Required Relative Compaction
  • Modified compaction for reference density
  • Minimum dry density ratio (AS 1289.5.4.1)
    required-
  • The top 100 mm of pavement 98 (existing roads
    only)
  • Below 100 mm from surface, where crushed rock
    95
  • Below 300 mm from surface, where permitted to be
    sand min 85 Density Index, or 10 blows/300 mm
    PSP
  • Local Authority requirements over-ride if more
    stringent

27
Compaction
  • Interpretation of test results
  • Action to be taken according to following
  • If a layer is rejected it is to be re-excavated,
    backfilled with new material, compacted and
    re-tested for compliance

28
Cohesionless Soils (Sand)
  • Sand fill, except beneath Traffic Areas
  • Use of water
  • Flooding not permitted
  • Jetting only permitted where surrounding soil is
    also cohesionless
  • Approved ITP in place
  • Must achieve required compaction
  • Pay for the water used
  • Contain sediment
  • 24 hour delay before testing
  • For mechanical compaction, layers 400 mm, but
    as required to achieve compaction over full depth
    of layer

29
Cohesionless Soils (Sand)
  • Required Relative Compaction
  • Road Reserves (other than Traffic Areas)
  • Minimum Density Index of 65, or
  • Minimum PSP resistance of 8 blows per 300 mm
  • Other Areas
  • Minimum Density Index of 60, or
  • Minimum PSP resistance of 7 blows per 300 mm
  • Review of test outcome (Section 4.6) similar to
    above
  • Note possible need to static roll surface layer,
    and to test penultimate layer

30
Cohesionless Soils (Sands)
  • Testing Frequency
  • Where testing using PSP
  • Where using conventional testing

31
Cohesive Soils (clays and clayey soils)
  • Application
  • Soils which will behave like a clay when placed
    and compacted
  • Anywhere except Traffic Areas
  • Flooding or jetting not permitted (ever)
  • Fill to be moisture conditioned as necessary to
    allow compliant compaction
  • In any event within range 85 to 115 of SOMC
  • Contractor may need to trial layer thickness,
    etc.
  • Some Ordinary Fill (e.g. from basalt rock
    excavation) may be acceptable backfill, but be
    unable to be tested
  • Contractor to develop method specification for
    placement and compaction, and submit to
    Superintendent for approval prior to use

32
Cohesive Soils (clays and clayey soils)
  • Required Relative Compaction

Note that test means one field test plus one
laboratory test
  • Note Contractor still responsible for overall
    performance

33
Cohesive Soils (clays and clayey soils)
  • Test result outcomes
  • Test results shall be reviewed by the Contractor,
    and action taken in accordance with the following
    table

34
Drives, Shafts , Tunnels and Bores
  • Section 6 refers not part of Golder review
  • Drives and tunnels must be refilled above the
    embedment zone using the following materials and
    methods
  • 20 mm Class 4 crushed rock, or embedment concrete
    sand or 5 mm minus, pneumatically placed (blowing
    backfill into the excavation using compressed air
    through temporary piping that can be retracted as
    the excavation fills).
  • Grouting, either by gravity, or under pressure.
    (Gravity grouting should only be used for tunnels
    where there is sufficient head.)
  • etc

35
Concluding Remarks
  • Control of trench backfill important
  • Watering in is not appropriate compaction,
    despite folklore
  • Specification 04-03 represents a higher but
    necessary standard
  • Keeping of records important
  • Beware possible influence of granular fill in
    embedment zone, in reactive clay areas

36
Thank You for your attention
37
  • Discussion?
Write a Comment
User Comments (0)
About PowerShow.com