Title: MRWA Specification No 0403 Trench Backfill
1MRWA Specification No 04-03 Trench Backfill
2Outline of presentation
- Background
- Principles of compaction
- Selected definitions
- General backfill requirements
- Traffic areas
- Cohesionless soils
- Cohesive soils
- Drives, shafts, tunnels and bores
- Concluding remarks
3Background
- 2002
- CWW introduced mechanical compaction requirement
- flooding in practice was prohibited
- to eliminate risks associated with subsidence and
collapse of sewer trench backfill - 2003?
- SEW develop specification
- Higher standards than WSAA previously specified
- Some resistance from industry
- 2004
- SEW ask Golder to review
- Following review, Golder asked (2005) to redraft
SEW specification - 2006
- CWW ask Golder to assess whether SEW document can
be adopted without change by CWW - Only minor drafting changes
- Some comments re reactive ground and rock
- Three Melbourne Retail Water Agencies adopted
MRWA Backfill Specification No. 04-03.1 for all
MRWA Capital Works and Land Development projects
on 1 September 2006.
4Need For Control of Trench Backfill
- Historically trench backfill often poorly
controlled - Negligible compaction, or only at surface
- Watering in of clay (and sand) assumed effective
- The inevitable steps/depressions in pavements
- Heightened OH S issues
- Litigation from trips and damage
5Need For Control of Trench Backfill
- Need to consider requirements early in project
planning and implementation - MRWA Specification No 04-03 intended to provide
guidance, as well as minimum requirements - Need reliable records
- We live in a litigious world
6Application
Specification No 04-03 only intended for
Trenchfill zone, and not Embedment zone
7Principles of Compaction
- Compaction
- The process whereby the density of a soil mass
is increased by mechanical (usually dynamic)
means, by rearrangement of the soil particles and
expulsion of air, usually with little alteration
to water content - Consolidation
- The process whereby the density of a soil mass
increases under the natural action of gravity (a
static force) due to self weight or an applied
surcharge. Water usually expelled, and the
process is time dependent. - Two very different processes. Should not be
interchanged in Specifications or in discussion. - Note, nevertheless, the dependence of compaction
on moisture content at time of compaction.
8Compaction
- Specified to provide-
- higher shear strength
- more predictable strength
- lower compressibility
- lower permeability
- reduced susceptibility to water content changes
(eg softening, swelling) - Desirable properties are mostly achieved at high
density. - May not be the case in relation to reactivity
- Hence there is a need to understand the moisture
- density relationship
9The compaction process
- At the risk of seeming gratuitous-
- low moisture- shearing resistance to movement of
soil particles relative to each other is high,
density increase difficult to achieve - increasing moisture- progressively easier to
disturb the soil structure, and for same
compactive effort higher density can be achieved
up to a certain point - get peak in dry density - moisture relationship,
after which simply increase void ratio, as voids
fill with water - Hence the well known compaction curve and
associated MDD and OMC
10Compaction Curve
Note difficult to achieve better than about 2
air voids
11Compaction
- Maximum dry density and optimum moisture content
are not unique properties of a given soil. - Are dependent
- upon the energy input during compaction
- the nature of the compactive effort.
- Different soils will respond differently to the
same compactive effort. - Hence, roller optimum will vary from laboratory
optimum.
12Laboratory Compaction
- Cohesionless soils (clean sands) will not produce
a compaction curve. -
- For these soils can measure a maximum and
minimum density using standardized procedures,
and then relate this to field density as Density
Index, or relative density - Again maximum and minimum are not unique or
extreme values.
13Field Density Testing
- To allow comparison of achieved compaction with
laboratory values, need to be able to reliably
assess field dry density and moisture content - Nuclear density gauges most common
- Rapid, reasonably repeatable
- Need to be calibrated
- Moisture content usually in laboratory
- Not non destructive as often assumed
- In trenches need to get background count to
provide for the confined space and possible
influence of trench walls.
14Relative Compaction
- Usually reference to minimum dry density ratio
(AS1289.5.4.1) - Ratio of FDD and MDD as DDR
- Moisture variation from OMC may also be reported
- Beware!
- 2 OMC is wet for Standard
- 2 variation is dry for Hilf
- Can have moisture ratio also
- Perth Sand Penetrometer may be used in
cohesionless materials
15Relative Compaction cont.
- 04-03 generally calls up minimum dry density
ratio - Not one test to fail criteria (as adopted by
AS3798) has stood the test of time - empirically based performance criteria
- allows for inherent variability
- good supervision essential to have confidence in
representative data - judgment necessary in interpretation
- 04-03 provides guidance on interpretation of
results
16Rigour in Control Testing
- If insufficient material able to be recovered
from FDT site (eg shallow test)- - Additional material should be recovered from
around the FDT site - Square sided hole
- Sampling from elsewhere is unacceptable
- Combining bulk samples is unacceptable
17Rigour in Control Testing
- A reference density should be established for
each FDT - unless material is sufficiently uniform in its
properties and compaction characteristics that
any variability is solely due to test method - unlikely except for crushed rock from hard rock
source - assigned value AS1289.5.4.2 then may be
applicable
18Rigour in Control Testing
- AS1289 allows for removal of (and correction for)
up to 20 coarse material in lab compaction test - A and B moulds
- Does not recognise possible changes in compaction
characteristics - More than this and test will lack relevance. A
potential issue where ordinary fill being used
in basalt rock country, for example, and may
contain gt20 coarser than 37.5 mm
19Properties of Compacted Fill - Reactivity
- Reactive Soils Clay soils, for which a change in
moisture content may result in sufficient change
in volume to affect the engineering performance
of any structures (including pavements)
influenced by this soil. - Compacted clay fill may be more reactive than
natural source material - Higher DDR, same relative moisture higher
reactivity - Drier placement moisture, same DDR higher
reactivity - Possibly need to consider specifying maximum DDR
- Not easy to enforce
20Properties of Compacted Fill - Reactivity
- Increased reactivity when placed dry
- Should aim to place at expected long term
equilibrium - Not so easy in surface zone of seasonal moisture
variation - Sand in embedment zone can allow deeper soils to
wet up or dry out (swell or shrink) - Caution required when placing pipes near to
houses or movement sensitive structures
21Specn. 04-03- Selected definitions
- Cohesionless Soils Poorly graded sand and gravel
mixtures, generally with less than 5 fines (ie
finer than 75 µm), which are non-plastic and
which do not exhibit a well-defined
moisture-density relationship when tested in
accordance with AS 1289.5.1.1 or AS 1289.5.2.1.
These will typically be clean sands. - Cohesive Soils Those materials which have a
well-defined moisture-density relationship when
tested in accordance with AS 1289.5.1.1 or AS
1289.5.2.1. Whilst cohesive soils are typically
clayey in nature, for the purpose of this
definition these may also include well-graded
granular materials such as crushed rock. - Ordinary Fill Material obtained from excavation,
or imported, that contains not more than 20 by
mass of rock fragments with size between 75 mm
and 150 mm, with no rock or clay fragments
greater than 150 mm. - SettlementSettlement is a downwards displacement
of the ground surface, relative to either the
surrounding ground (differential settlement) or a
stable bench mark (total settlement). It is the
result of a volume reduction in the ground
beneath the surface, due to any of several
possible mechanisms. (e.g. collapse,
consolidation, (traffic) compaction). Sometimes
called subsidence
22Section 2. General Backfill Requirements
- Contractor to be responsible for compliant
backfill methodology, and for consequences (eg
subsidence) - Alternative materials or methods subject to
Superintendent prior approval - Safe working environment for testing
- Testing by NATA accredited lab
- Tester to choose test locations randomly
- Contractor may only direct where he needs
additional tests. - No testing above pipe within 500 mm of top of
pipe. Otherwise beside pipe. - Superintendent to record test location. No work
until tests show compliance
23Section 3 Traffic Areas
- Application- backfill material for trenches in
all Traffic Areas, including - the full width of any existing or proposed road
carriageway plus shoulders, and extending to one
metre beyond the shoulders/kerb. - the full width of any property access driveway,
and extending one metre either side. - the full length of any constructed footpath
(including, but not limited to concrete, asphalt,
crushed rock footpaths). - the full width of any median strip.
- any other areas that are used as Traffic Areas.
-
- Road authority requirements govern if they are
more stringent
24Section 3 Traffic Areas (cont)
- Backfill material
- In traffic areas, other than footpaths
- For trenches less than 1.5 metres deep
- 20 mm Class 2 Plant Mixed Wet Mix Crushed Rock,
for the full depth. - For trenches 1.5 metres deep or greater,
- 20 mm Class 2 Plant Mixed Wet Mix Crushed Rock
for the top 600 mm. - 20 mm Class 4 (or better) Crushed Rock for the
remainder, or other backfill material
specifically approved by the Road Authority. - For trenches under footpaths
- 20 mm Class 4 (or better) Crushed Rock, or other
backfill material specifically approved by the
Road Authority. - Backfill to be placed and compacted in layers
200 mm loose thickness
25Section 3 Traffic Areas (cont)
- Compaction Testing
- All road crossings to be tested
- Base Course and Sub-base
- For every 50 metre length of trench (or part
thereof) three tests shall be taken - Within the top 100 mm (ie within the base course)
of an existing road. - In the depth range 100 mm to 300 mm depth (ie
within the pavement sub-base). - Backfill Under Roads, Road Shoulders, Median
Strips (below sub-base) - For every 40 metre length of trench (or part
thereof) one test shall be taken per two layers
of backfill - Layers to be tested shall be selected randomly,
in accordance with Clause 2.6. The position of
the layer to be tested, and the location of the
test, shall vary from test to test. - Adjacent layers shall not be selected for
testing. - Backfill Under Footpaths
- As for roads, except that the testing shall be
for every 100 metre length of trench (or part
thereof). - Note overall Contractor responsibility for
performance (Cl. 2.2)
26Section 3 Traffic Areas (cont)
- Required Relative Compaction
- Modified compaction for reference density
- Minimum dry density ratio (AS 1289.5.4.1)
required- - The top 100 mm of pavement 98 (existing roads
only) - Below 100 mm from surface, where crushed rock
95 - Below 300 mm from surface, where permitted to be
sand min 85 Density Index, or 10 blows/300 mm
PSP - Local Authority requirements over-ride if more
stringent
27Compaction
- Interpretation of test results
- Action to be taken according to following
- If a layer is rejected it is to be re-excavated,
backfilled with new material, compacted and
re-tested for compliance
28Cohesionless Soils (Sand)
- Sand fill, except beneath Traffic Areas
- Use of water
- Flooding not permitted
- Jetting only permitted where surrounding soil is
also cohesionless - Approved ITP in place
- Must achieve required compaction
- Pay for the water used
- Contain sediment
- 24 hour delay before testing
- For mechanical compaction, layers 400 mm, but
as required to achieve compaction over full depth
of layer
29Cohesionless Soils (Sand)
- Required Relative Compaction
- Road Reserves (other than Traffic Areas)
- Minimum Density Index of 65, or
- Minimum PSP resistance of 8 blows per 300 mm
- Other Areas
- Minimum Density Index of 60, or
- Minimum PSP resistance of 7 blows per 300 mm
- Review of test outcome (Section 4.6) similar to
above - Note possible need to static roll surface layer,
and to test penultimate layer
30Cohesionless Soils (Sands)
- Testing Frequency
- Where testing using PSP
- Where using conventional testing
31Cohesive Soils (clays and clayey soils)
- Application
- Soils which will behave like a clay when placed
and compacted - Anywhere except Traffic Areas
- Flooding or jetting not permitted (ever)
- Fill to be moisture conditioned as necessary to
allow compliant compaction - In any event within range 85 to 115 of SOMC
- Contractor may need to trial layer thickness,
etc. - Some Ordinary Fill (e.g. from basalt rock
excavation) may be acceptable backfill, but be
unable to be tested - Contractor to develop method specification for
placement and compaction, and submit to
Superintendent for approval prior to use
32Cohesive Soils (clays and clayey soils)
- Required Relative Compaction
Note that test means one field test plus one
laboratory test
- Note Contractor still responsible for overall
performance
33Cohesive Soils (clays and clayey soils)
- Test result outcomes
- Test results shall be reviewed by the Contractor,
and action taken in accordance with the following
table
34Drives, Shafts , Tunnels and Bores
- Section 6 refers not part of Golder review
- Drives and tunnels must be refilled above the
embedment zone using the following materials and
methods - 20 mm Class 4 crushed rock, or embedment concrete
sand or 5 mm minus, pneumatically placed (blowing
backfill into the excavation using compressed air
through temporary piping that can be retracted as
the excavation fills). - Grouting, either by gravity, or under pressure.
(Gravity grouting should only be used for tunnels
where there is sufficient head.) - etc
35Concluding Remarks
- Control of trench backfill important
- Watering in is not appropriate compaction,
despite folklore - Specification 04-03 represents a higher but
necessary standard - Keeping of records important
- Beware possible influence of granular fill in
embedment zone, in reactive clay areas
36 Thank You for your attention
37