Title: MIPAS InOrbit Operations and Failure Recoveries
1MIPAS In-Orbit Operations and Failure Recoveries
- J. Frerick
- Rhea Systems S.A. c/o ESA-ESTEC
2Content
- Introduction
- The MIPAS experiment
- Interferometer layout
- Operational experience
- Phase I Launch April 2004
- Phase II Anomaly investigation
- Interferometer Speed control
- Classification of Velocity Errors
- Investigation Objectives
- Special tests
- Investigation summary
- Phase III Since January 2005
- Summary
- The Team
3Introduction (1)The MIPAS experiment
- Michelson Interferometer for passive
atmospheric sounding - On-board ENVISAT (Launch March 2002)
- Limb sounding IR instrument
4Introduction (2)The MIPAS experiment
- Targeting atmospheric species relevant for
- Ozone chemistry
- Green house effect
5Introduction (3)The interferometer Layout
- Double slide interferometer
- 100 mm rails
- Nominal speed 25 mm/s
6Operational Experience (1)Phase I Launch until
April 2004
-
- Very reliable, autonomously working instrument
- Easy going mechanics (interferometer, Stirling
Cooler) - High data quality (very) satisfied users
- Only a few un-planned unavailabilities
- However Since April 2003 there were signs of a
degrading interferometer subsystem. - Warnings from on-board monitoring (so called
differential speed monitoring errors) with no
operational consequences. - Later Increasing number of so called velocity
errors, which forced the instrument into
Heater/Refuse mode, requiring manual recovery
from ground. - Substantial instrument unavailabilities.
- Specifically alarming in some anomaly cases the
recovery showed a risk for a permanent failure
7Operational Experience (2)Phase II The Anomaly
investigation
- Interferometer speed control
Reference Laser Fringe count (1 msec)
Absolute position sensor count (10.65 msec)
Heater refuse If v1 and/or v2 gt30 mm/s
Heater refuse If gt 15
Check Vopt
Check V1 , V2
If lt15
Check V1-V2D
Increase/Decrease currents of both, Slide 1 and
Slide 2
Increase/Decrease currents of Slide 1 and Slide
2 by D/2
If gt4, differential speed monitoring error
8Operational Experience (3)Phase II The Anomaly
investigation
- Classification of velocity errors
- Turnaround (principally known)
- In sweep (unexpected)
- With critical initialization
- During a critical initialization, slide 2 has to
pass the former launch lock position. An
increasing number of attempts was necessary to
move the slide across this point. This was
regarded a risk of permanent failure.
9Operational Experience (4)Phase II The Anomaly
investigation
- Investigation objectives
- To eliminate the source of the problem
- Reference laser
- Absolute position sensor
- Rails
- Bearings
- Temperature effects
- Any combination of all
- To eliminate/reduce risk of permanent failure
- How to avoid getting trapped by the launch lock?
- To reduce operational effort
- How to minimize manual operations/instrument
recoveries? - To minimize outage times
10Operational Experience (5) Phase II The Anomaly
investigation
- Special tests
- Static Mode tests
- Moving the slides slowly, but individually and
monitor drive force - No conclusive results
- Reduced Resolution tests
- Better performance could have been a hint for
rail depended problem at turnaround points (i.e.
the end of the rails). - No conclusive results regarding interferometer
performance - Positive effect on avoiding critical
initializations. - Tests on instrument redundant side
- To elude error sources like the reference laser,
the absolute position sensor - Similar performance as on nominal side ? switch
back to nominal - Tests in back up mode
- Single slide operations with one slide fixed in
the middle. - Does one slide have a better performance than the
other? - Not conclusive.
11Operational Experience (6)Phase II The Anomaly
investigation
- Investigation Summary (1)
- Explanation of error
- Overall degradation of non-redundant parts
performance (most likely bearings) in combination
with inflexible control loop layout (it was
impossible to change control loop thresholds by
software). - Risk of critical initializations could be
minimized by optimization of spectral resolution. - 41 of maximum (full) resolution turned out to be
the optimum.
12Operational Experience (7)Phase II The Anomaly
investigation
- Investigation Summary (2)
- Minimization of outage times/operational effort
- By performing a planned interferometer
initialization every orbit. - By reducing the duty cycle (as the performance
indicators showed relaxation after longer periods
of outage).
13Operational Experience (8)Phase III Since
January 2005
- The concept is working
- Operations is stabilized (no more manual
intervention due to velocity errors) - The total outage due to velocity error is reduced
from former 3 orbits (best case) to lt 0.5 orbit,
nominally. - Critical initializations occurred only once in
almost 18 month. - Reduction of spectral resolution only had limited
scientific impact due to the originally
implemented over-design. - The number of interferometer errors is still high
and even showing seasonal maxima - Evidently, there is more than one error
mechanism. - However, the main conclusion remains the control
system is too inflexible to cope with a changing
environment.
14Summary
- An interferometer control problem interrupted the
so far very successful MIPAS experiment on-board
ENVISAT in April 2004. - Intense failure investigation was performed until
end 2004, taking advantage of various and
numerous special on-board test possibilities, the
most important ones being - Single slide/ backup mode tests
- Tests on redundant electronics
- Variation and finally reduction of stroke length
(i.e. spectral resolution) - Analysis concluded that a degradation in non
redundant parts in combination with the
inflexible design of the interferometer control
caused the observed problems. - A new operations scheme could be implemented
successfully - Minimizing risk of permanent failure
- Minimizing the operational effort for recoveries
- Minimizing the outage and thus leading again to a
stable mission - The new concept took advantage of a very flexible
- Instrument design
- The mandatory reduction of spectral resolution
could be compensated without significant
reduction of scientific data quality - Mission planning design
- With reasonable effort the new, campaign
oriented way replaced the former continuous
operations.
15The Team
ESA-ESTEC/PLSO Investigation/coordination
supported by Rhea Systems S.A.
ESA-ESOC Operations supported by Vega
Group SciSys GmbH
Industry/EADS-Astrium Performance
Evaluation/Investigation Supported by Officine
Galileo AEA Technology
ESA-ESRIN Data quality analysis Mission
planning supported by Rhea Systems S.A. SERCO
Spa