Title: Outline
1(No Transcript)
2Outline
- SAGD
- Plant Scenarios
- Nuclear Plant Designs
- Thermo-hydraulic Analysis
- Economics
- Carbon Dioxide
- Conclusion
- Future Work
3In-situ SAGD
4- Scenario One
- Production SAGD Process Heat Only
- Electricity from off-site source
- Product Diluted bitumen
- Scenario Two
- Production SAGD Process Heat and Electricity
for on-site needs - Product Diluted bitumen
- Scenario Three
- Production SAGD Process Heat, Electricity for
on-site needs, and Hydrogen for upgrading needs - Syncrude
5Evaluation of Reactor Options
- ACR-700 (1983MWth, 731MWe)
- Primary coolant Light Water, Moderator Heavy
Water - Primary Outlet 326C, Fuel Canflex bundle
SEU(slightly enriched Uranium) 2 - PBMR (400MWth, 165MWe)
- Primary coolant Helium, Moderator Graphite
- Primary outlet 900C, Fuel Pebbles 60mm, outer
dia., encloses 11,000 C/SiC coated fuel
microspheres of UO2 - AP600 (1940MWth, 600MWe)
- Primary Coolant and Moderator Light Water
- Primary Outlet 316C, Fuel 4.20 wt 235U,
sometimes MOX (mixed oxide) fuel
6Extraction Parameters
- The conditions for extraction vary depending on
the quality of the tar sand bed - Calculations for this study were conducted using
low quality tar sand bed conditions
Based on a 100,000 Bbl/day bitumen extraction plant Based on a 100,000 Bbl/day bitumen extraction plant Pressure Pressure
Based on a 100,000 Bbl/day bitumen extraction plant Based on a 100,000 Bbl/day bitumen extraction plant 2 Mpa 6 MPa
Heat Transfer Required (MWth) Low Performance 1230 1264
Heat Transfer Required (MWth) High Performance 820 843
7Layout for Steam Cycles
- Either two ACR-700s or two AP600s in parallel
would be acceptable for this scenario
Scenario Bitumen (Bbl/day) SynCrude (Bbl/day)
1 332,000 -
2 199,000 -
3 - 114,000
8Layout for Gas Cycles
850C
- Eight PBMRs would be acceptable for this scenario
Scenario Bitumen (Bbl/day) SynCrude (Bbl/day)
1 253,000 -
2 166,000 -
3 - 98,000
9Economics
10Purpose of economic analysis
- Should natural gas or nuclear be used for the
SAGD extraction process? - Should the electricity requirements of the plant
be fulfilled by buying electricity off the power
grids, or by making it at the plant? - Should the hydrogen required for the bitumen
upgrading process be bought from private
suppliers, or produced at the plant? - This is meant to be a comparison between
nuclear and natural gas energy sources for this
application, not an estimate of the actual full
cost of the facility.
11Economic Assumptions
- All costs are in US dollars (US)
- The lifetime for the plants are assumed to be 30
years, and the Net Present Value (NPV) is
calculated for a 10 discount rate - No inflation is assumed
- Easy access to Alberta electricity power grid is
assumed, price is US0.05/kWhr - Buying price of hydrogen is assumed to be
US2.50/kg of H2 - Natural gas price is assumed to be 8.00/mmBtu
12Economic Assumptions, Contd.
- A 90 learning curve is assumed for building
additional nuclear reactors - Costs do not include that of processing and
upgrading plants as these are held constant and
independent of heat source used. - 4 categories of cost capital, OM, fuel, and
decommissioning - 3 final types of costs looked at Cost of Process
Heat, Cost of Electricity, and Cost of Hydrogen
Production
13Nuclear Power Cost Assumptions
AP600 1 unit AP600 2 units ACR-700 1 unit ACR-700 2 units PBMR
Capital Rate (US/kW) 1687.2 1520 1693.40 1525.55 1250
Fuel Rate (US mills/kWhe) 5.0 5.0 2.6 2.6 6.0
OM Rate (US mills/kWhe) 8.0 10.0 7.05 8.82 3.0
Decommisioning Rate (US mills/kWhe) 1.25 1.0 0.6175 0.494 0.6
Operating Life (yrs) 30 30 30 30 30
14Hydrogen Production Costs
Natural Gas PBMR ACR-700 AP600
Hydrogen Cost per unit bitumen (US/Bbl) Make Hydrogen 1.754 1.636 1.901 1.811
Hydrogen Cost per unit bitumen (US/Bbl) Buy Hydrogen 2.506 2.506 2.506 2.506
15Cost Comparison of Natural Gas v. Nuclear
16Sensitivity of Total Cost to Changes in Capital
Cost
PBMR ACR-700 AP600
Change in Total Cost for a 25 increase in Capital Cost 11.3 13.9 12.5
- Capital cost is an initial fixed cost, unlike
natural gas cost which is a recurring cost over
the lifetime, i.e. capital cost has no future
volatility - For a 25 increase in the price of natural gas,
the gas extraction costs rise 18.
17Economic Conclusions
- Given current natural gas costs, nuclear is a
viable alternative for producing process heat for
SAGD. - Producing electricity using nuclear power is more
cost-effective than buying it off the Alberta
power grid or producing it using natural gas. - While Steam-Methane Reforming has historically
been a cheaper process than High Temperature
Steam Electrolysis, the cost of HTSE with nuclear
power is now comparable to SMR due to high
natural gas cost. - Overall, using nuclear power is a competitive
alternative to natural gas due to high prices and
volatility of natural gas, and new compliance
regulations of the Kyoto protocol
18Kyoto Protocol
- Canada has agreed to reduce greenhouse gas
emissions by 6 relative to the 1990 level of 612
Mt by 2012. (575 Mt) - Canadas Climate Change Plan (2002/2005)
- Reduce emissions to 305 Mt by 2012
- In 2012 (at 100Mt CO2) oil sands emissions would
represent 17 of the total Kyoto target (575 Mt),
and 29 of Climate Change Plan target (305 Mt)
19Conclusions
- Nuclear Process Heat applications in Oil Recovery
from Tar Sands are possible for steam production,
electricity generation and syncrude refining with
hydrogen production at costs that are lower than
natural gas. - Canadian Kyoto agreements will be challenged
without the use of nuclear energy in oil sands
extraction processes. Approximately 100 Mt CO2
emissions are avoided. - Additional site specific analyses are needed to
refine the nuclear energy applications to meet
industry needs.
20Updates Extensions Needed
- Updated process requirements
- Updated nuclear capital costs
- Hard look at practical implementation challenges
- Safety implications
- More in-depth CO2 analysis
- More in-depth natural gas displacement analysis
- Regulatory needs and insurance issues
- Conceptual business plan possibilities
21Acknowledgements
- This study was prepared as an MIT class design
project in the Department of Nuclear Science
Engineering. The authors of the original study
included -
- G. Becerra, E. Esparza, E. Helvenston, S.
Hembrador, K. Hohnholt, T. Khan, D. Legault, M.
Lyttle, C. Murray, N. Parmar, S. Sheppard, C.
Sizer, E. Zakszewski, K. Zeller - Assistance and information were also provided by
- Ryan Hannink of MIT, Dr. Julian Lebenhaft of
AECL, William Green of MIT, The Canadian Nuclear
Safety Commission, Westinghouse Electric Company,
James Fong of Petro-Canada, Bilge Yildiz of
Argonne National Laboratory, Brian Rolfe of AECL,
Michael Stawicki and Professor Mujid Kazimi of
the MIT Nuclear Science and Engineering
Department, Thomas Downar of Purdue, Daniel
Bersak of DRB photography, MIT alumnus Curtis
Smith of INL, and the faculty members of the MIT
Department of Nuclear Science and Engineering.
22Questions