DRIVAGE OF INCLINES IN MANDLA NORTH COAL MINE

1 / 20
About This Presentation
Title:

DRIVAGE OF INCLINES IN MANDLA NORTH COAL MINE

Description:

DRIVAGE OF INCLINES IN MANDLA NORTH COAL MINE of Jaiprakash Associates Limited, Noida by M N Jha & M S Sandhu * – PowerPoint PPT presentation

Number of Views:13
Avg rating:3.0/5.0
Slides: 21
Provided by: ms12154

less

Transcript and Presenter's Notes

Title: DRIVAGE OF INCLINES IN MANDLA NORTH COAL MINE


1
  • DRIVAGE OF INCLINES IN
    MANDLA NORTH COAL MINE
  • of
  • Jaiprakash Associates Limited, Noida
  • by
  • M N Jha M S Sandhu

2
COAL MINING SCENARIO
  • Coal mines were nationalized during 1971-73.
  • 80 of coal production came from underground mine
    during that era.
  • Emphasis was given to develop Opencast mining to
    meet rising demand.
  • This trend continued with high level of
    mechanization resulting into only 10 share of
    coal production from underground mines as of now.
  • Ministry of Coal identified Coal blocks for
    allocation to be developed scientifically through
    underground method only.

3
GENERAL INFORMATION
  • Mandla North coal block with coal seams at a
    depth varying from 210 to 300 m was allotted to
    M/S Jaiprakash Associates Ltd.
  • It covers an area of 10.41 sq. km.
  • Coal seams are highly disturbed with 29 faults in
    the property. The major fault (F2A) with 100m
    throw divides the property in two parts.
  • The mine has been planned to extract 1.5 mtpa
    deploying 3 sets of Continuous Miner.
  • One set of inclines with one ventilation shaft
    are proposed to access coal seams.

4
COAL SEAMS
  • Barakar formation contains 5 coal seams splitted
    in to 19 workable/non-workable seams occurring at
    a depth varying from 173-350m.
  • The following distinct horizons formed by coal
    seams are found workable.

COAL HORIZON COAL SEAM
TOP SET
1 Seam I B
2 Seam I C
3 Seam II
4 Seam III B
BOTTOM SET
5 Seam IVA/A2
6 Seam VA/A1
7 Seam VB/B1
5
METHOD OF WORKING
  • It is planned to develop Seam IC initially having
    found in all 24 sectors with Gross reserve of
    45.48 mt since Seam IA has not developed into
    workable thickness and Seam IB coalesced with
    Seam IC at various places.
  • Life span for extraction of IB/IC is estimated at
    25 years _at_ 1.5 mtpa.
  • Extraction of II/IIIB shall be planned after a
    lapse of 5 years on completion of depillaring of
    the first panel of Seam IB/IC. This sequence will
    be followed for the remaining lower seams.
  • It has been decided to work this mine by Bord
    Pillar method with deployment of Continuous Miner
    for driving Trunk headings along rise and dip of
    the property.
  • Panels comprising a set of 5 headings with cross
    connecting galleries will be opened on either
    side of the main trunk roadway for lateral
    development.
  • 3 sets of Continuous Miners will be deployed to
    achieve the targeted Mine capacity of 1.5 mtpa.

6
METHOD OF WORKING (Contd)
  • VENTILATION
  • The proposed Mandla North Coal Mine has been
    considered as Degree-II Gassy Mine for assessment
    and planning of ventilation requirements.
  • 18000cum/minute of air is required to be produced
    by Mechanical system installed in Ventilation
    shaft.
  • 3.3 kv, 350kw motors shall be installed.
  • These figures has been arrived taking into
    account all relevant DGMS requirements.

7
METHOD OF WORKING (Contd)
  • EVACUATION OF COAL
  • Continuous Miner shall convey the coal into
    Shuttle cars through its bridge conveyor.
  • Loaded Shuttle car will discharge coal onto the
    feeder-breaker via coal hopper.
  • Coal will be discharged uniformly onto the gate
    belt conveyor from feeder breaker.
  • The gate belt in turn will discharge the coal
    onto the trunk belt conveyor and to bunker on the
    surface.
  • Mechanically covered trucks will carry the coal
    from bunker to Railway siding for loading into
    the railway wagons.

8
INCLINE DRIVAGE
  • A single set of inclines measuring 5.2mX3.5m at a
    gradient of 1 in 4.5 are being driven in the
    centre of the property.
  • The above parameters will restrict the length of
    the inclines to 903mx2 with optimum level of
    efficiency both for evacuation of coal and man
    riding system.
  • The inclines will pass through Deccan Traps
    (495mx2) and Moturs (348mx2) before intersecting
    the coal bearing Barakars.

9
INCLINE DRIVAGE (Contd)
  • TECHNOLOGY
  • Deployment of Road header - This option was not
    considered because of its unsuitability in Basalt
    having hardness gt8.
  • Drilling, blasting with combination of SDL and
    conveyor belt The frequent shifting of Conveyor
    belt along with high level of maintenance makes
    this option unviable.
  • Deployment of Jumbo drill, SDL and 150kw haulage
    with 10t skips This has been adopted being the
    most suitable for Indian condition and
    subsequently to be used for man riding.

10
INCLINE DRIVAGE (Contd)
  • EQUIPMENTS-HAULAGE
  • Haulage with man riding provision with following
    specifications have been installed.
  • Haulage rating 150 kw
  • Rope Speed 2.2 to 2.5 m/sec
  • Rope pull 20 Tonnes in 1 in 4.5 gradient
  • Rope diameter 25 mm
  • Motor RPM 1000
  • Drum diameter 1500 mm
  • Rope length 1200 m

11
INCLINE DRIVAGE (Contd)
  • EQUIPMENTS-JUMBO DRILL
  • One Jumbo drill capable of drilling both face and
    roof holes in two inclines with following
    specifications has been deployed.
  • Make Sandvik HL 510
  • Percussion pressure 120-175 bar
  • Rotation (max) 175 bar
  • Impact power 16 kw
  • Feed length 3900mm860mm
  • Feed force 9 Kn/120 bar
  • Water pump 1 x Water booster pump
  • Length 8015 mm
  • Width 1700 mm
  • Height (without canopy) 1800 mm

12
INCLINE DRIVAGE (Contd)
  • EQUIPMENTS-SIDE DISCHARGE LOADER
  • Two SDLs to load the broken rock into the 10 t
    skip with following specifications.
  • Overall length 5428 mm
  • Height over canopy 1850-2100 mm
  • Ground clearance 205 mm
  • Bucket capacity 0.66 cum (side tipping rock
    bucket)
  • Gradient to be negotiated 1 in 4.5
  • Track width (grouser pads) 330 mm

13
INCLINE DRIVAGE (Contd)
  • EQUIPMENTS-VENTILATION FAN
  • In order to get air flow of 8cum/sec at the face
    end of 900 m long drift, fans of 37.5 kw with
    following specifications are installed in
    respective inclines.
  • Fan Pressure 3200 Pa
  • RPM 2950
  • Voltage 415 V
  • Rating of fan motor 37.5 kw

14
INCLINE DRIVAGE (Contd)
  • BLASTING PATTERN

15
INCLINE DRIVAGE (Contd)
  • BLASTING PATTERN

16
INCLINE DRIVAGE (Contd)
Time Study Time Study
Activity Total Time (In minutes)
Tramming 05
Water connection 15
Scaling (Dressing) 20
Face Drilling 52
Roof Drilling 20
Roof bolting 50
Water dis-connection 15
Tramming 07
Face charging 60
Blasting 10
Entry after blast 20
Face clearance after blast 30
Mucking(Blasting muck clearance) 240
General work(Ducting, lighting etc) 60
Total Time 604 (Say 600 minutes) i.e 10 hours.
17
CONCLUSION
  • We expect to achieve a progress of 90m per month
    in each incline to touch coal seam within a time
    span of 10-12 months.
  • Continuous Miner will be deployed to drive trunk
    heading and for formation of panels.
  • 3 set of Continuous Miner along with allied
    equipments shall be commissioned to achieve the
    target production of 1.5 mtpa.

18
(No Transcript)
19
(No Transcript)
20
(No Transcript)
Write a Comment
User Comments (0)