Title: St' Anthony Falls I35W Bridge
1St. Anthony Falls (I-35W) Bridge June 12, 2008
2The former Bridge - 9340
- Opened to traffic in 1967
- Steel truss bridge design
- Concrete deck and pier footings
- Expected life span 50 years
- Fracture critical bridge
- If certain components fail, bridge can fail
- Bridge and Roadway Repair Project Underway at
time of collapse
3The Collapse
- Bridge Collapsed at 605 p.m. Wednesday, August
1, 2007 - Plunged nearly 100 vehicles into the Mississippi
River - 13 fatalities
- 145 injuries
4Responses after the collapse
5Traffic Management Response
Initial traffic response (first ½ hour) is very
similar to many other major traffic incidents to
which the groups in the RTMC respond frequently
- Deployed 20 changeable message signs activated
within 3 minutes of collapse - Continuous coverage on KBEM-FM
- FIRST units provided initial traffic control
- Information provided directly to media and to
travelers via - 511 telephone and website
- RTMC traveler Information page
No loss of communications to RTMC due to
redundancy
6Emergency Responders
Minneapolis Incident Command Center at
Minneapolis City Hall
7Metro Transit Response
- Assigned 25 extra buses to north and east metro
area, results in - Ridership jumps 25-50
- Advised public to buy bus passes, stagger work
hours, and carpool - Free rides from strategic Park-n-Ride Lots
- Began studying additional service enhancements
Park-and-Ride use jumps after I35W bridge collapse
8Traffic Project Framework
- Guidelines for project managers on TR projects
- Must increase capacity, improve safety, and/or
manage traffic (ITS) - Must build in a weekend or on weeknights
- No traffic impact for peak periods allowed
- Must be within circle of impact
- Must be let before end of September
- Most must be done by end of August
- Designers have one week from concept to
construction - Goal Get traffic back to normal
- Final Tally 30 projects at less then 7M
9Bridge Removal
- Force Account
- Approx. Cost - 7 million
- Coordination with NTSB
- Coordination with Bridge Replacement
10HISTORY OF SITE Date1935
11Bridge Description
- Variable depth superstructure 25 to 11
- Concrete piers supported by footings and drilled
shafts socketed into rock
330
504
242
147
12Bridge Description
- Two parallel bridges, each with two box girders
- Striped for 5 lanes each direction (10 total)
with 13 and 14 shoulders (actual design
loading considers for 7 lanes each direction) - Future configuration of 4 lanes each direction
plus light rail line or bus transit lane
11
904
13Drilling at Abutment 5on the north side
January 14, 2008
14Aerial view of south side
15Pier 3 construction
16Aerial view of north side
17Pier 2 Mar. 5, 2008
18Erect Temporary Supports
19Apr. 1, 2008
South side falsework
20South Approach spans May 5, 2008
21Approach span, south side, one box girder Apr.
1, 2008
22Casting Yard, I-35Wsouth side, Washington Avenue
23Casting yard May 5, 2008
24Pre-cast segments
Apr. 1, 2008
25Erect Cantilevered Main-Span
26Segments on West River ParkwayJune 10, 2008
27Segment storage May 5, 2008
28Victory BridgeMiddlesex County, NJ
First segment, May 25, 2008
29Sagadahoc Bridge, Maine
Flatiron FIGG Maines 1st Design/Build
30June 10, 2008 North side roadwork
31More than 200 people showed up on April 19, 2008
Sidewalk Talks every Saturday
32WEBSITEwww.mndot.gov
33WEBCAM
34Questions?