Chapter 9 Part I Mediating Large Disputes - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

Chapter 9 Part I Mediating Large Disputes

Description:

Raw water treatment facility. Designed, owned and operated by the Denver Water Board (DWB) ... Expand Denver's treatment facilities, but not raw water supply system ... – PowerPoint PPT presentation

Number of Views:65
Avg rating:3.0/5.0
Slides: 21
Provided by: slk5
Category:

less

Transcript and Presenter's Notes

Title: Chapter 9 Part I Mediating Large Disputes


1
Chapter 9 Part IMediating Large Disputes
  • Case Study Foothills Water Treatment Project
  • Stephanie Lang
  • 6/19/07

2
Significance of the Case
  • Large, complex dispute involving many different
    parties
  • Tests the proposition that some environmental
    disputes are too complex to be negotiated
  • Mediation was attempted twice one attempt was
    successful, the other was not.

3
Background What is it?
  • Raw water treatment facility
  • Designed, owned and operated by the Denver Water
    Board (DWB)
  • Includes a concrete diversion dam and reservoir
    on the South Platte River (25 mi SW of Denver)
    linked by a tunnel
  • 490 acres of undeveloped grassland

4
Background What is it?
  • By design, the reservoir would contain a
    hydroelectric turbine that would create much more
    power than it would need to operate
  • Expand Denvers treatment facilities, but not raw
    water supply system
  • If the new system exceeds 125 mgd, new water
    supplies from the west slope would be needed

5
Timeline
  • 1952 DWB begins studies of the project
    additional capacity needed by 1977
  • 1967 Obtained Federal Rights of Way (some
    Federal land is used)
  • 1972 Voters asked for bond to increase capacity
    -- rejected
  • 1973 Issue put to voters again, but this time
    with large advertising campaign and does not
    specifically mention Foothills project --
    approved
  • 1974 Begins construction process
  • 1974-1979 2 lawsuits, 4 environmental impact
    statements (EIS) and millions of dollars
  • 1979 Construction begins

6
Proponents
  • DWB
  • Army Corps of Engineers
  • Governors Office
  • Colorado Department of Health
  • Citizens had voted for bond
  • Water for Colorado
  • Several local politicians

7
Why?
  • Provide water for growing communities
  • Against further water rationing
  • High Quality drinking water
  • Technically best solution for providing water for
    growing area

8
Opponents
  • Various Environmental Groups
  • EPA
  • Bureau of Land Management (BLM)
  • United States Forest Service (USFS)
  • United States Fish and Wildlife Service (FWS)
  • Local politicians

9
Why?
  • Alters the ecology of the region
  • Promotes urban sprawl and therefore numerous
    other environmental problems
  • Alternative solutions had not been thoroughly
    investigated

10
Obstacles to Mediation
  • Polarization
  • DWBs unwillingness to compromise
  • Personal animosity
  • Scope and complexity of the dispute

11
Mediation 1st Attempt
  • Congresswoman Schroeder suggested mediation early
    on, but the notion was rejected
  • She was an environmentalist and was assumed to be
    anti-Foothills
  • Immediately publicized the idea
  • Agreeing to mediation appeared to mean you were
    siding with Schroeder
  • Little was known about the Office of
    Environmental Mediation
  • The idea was introduced to early in the dispute
  • The DWB had no reason to enter into mediation

12
404 Permit Dispute
  • EPAs main leverage they could veto the 404
    Permit
  • Delay costed DWB 630,000/month that construction
    was not started
  • Both sides feared court decision
  • Carter administration against water development
  • Bad publicity for the EPA and court decisions are
    always unpredictable

13
404 Permit Dispute
  • Under public pressure, the EPA announces that it
    will not block construction, but would attach
    stipulations
  • Held public hearing on both east and west slope
  • Water conservation
  • Impact mitigation
  • Recommended that the Corps reject the 404 permit

14
Mediation 2nd Attempt
  • Tim Wirth (congressional representative)
    initiated mediation
  • Timing was better (neither side was certain of a
    satisfactory victory)
  • Perceived as pro-Foothills, so DWB was more
    likely to participate
  • Started with private conversations
  • Personal relationship with EPA
  • As mediation became public, it became more
    difficult to withdraw without damaging public
    perception

15
Mediation 2nd Attempt
  • Learned that the EPA wanted alternative solutions
    and environmental impacts were investigated
  • Corps would complete a study
  • EPA not happy about this choice, but realized
    that they were the most qualified to complete
    this type of study
  • DWB assumed the Corps would agree with them

16
Role of the Corps
  • Complete the alternative and environmental impact
    study
  • EPA and DWB were both involved in the design of
    the study
  • Gave the study more legitimacy

17
Role of the Public
  • EPA favored a strong public presence
  • The Corps wished to keep the public out of the
    process until its study was complete and reviewed
    by both sides

18
Results of the Study
  • Need for the Plant
  • Treatment capacity will be exceeded in 1980
  • With water conservation efforts 1995
  • With some economic and environmental costs
  • Plant Impacts
  • No relationship between water supply and sprawl

19
Alternatives
  • Strontia Dam (original proposal)
  • Built quickly
  • Hydroelectric generator
  • Provide water for Aurora
  • Lower operating costs
  • Canyon Mouth Dam (best alternative)
  • More time to design/build
  • Section of the canyon has already been impacted
  • Aurora would have to build its own dam
  • Lower construction costs
  • Higher operating costs

20
Conclusion of the Study
  • EPA still disagreed with the assessment of the
    viability of conservation as an alternative
  • EPA also disagreed with the lack of emphasis on
    the environmental impacts
  • DWB refused to agree to the Canyon Mouth site
    because of time and operating costs
Write a Comment
User Comments (0)
About PowerShow.com