DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

1 / 32
About This Presentation
Title:

DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

Description:

Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA * * Contents Discounting Alernative Investment Criteria - Net Present Value Criteria - Benefit-Cost Ratio ... – PowerPoint PPT presentation

Number of Views:34
Avg rating:3.0/5.0

less

Transcript and Presenter's Notes

Title: DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA


1
Chapter 4
  • DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

2
Contents
  • Discounting
  • Alernative Investment Criteria
  • - Net Present Value Criteria
  • - Benefit-Cost Ratio Criteria
  • - Pay Back Period Criteria
  • - Internal Rate of Return Criteria

3
1.1 Discounting and Compounding
  • Same amount of money "today" and "in future" do
    not have the same value.
  • Finding the today value of a future amount is
    DISCOUNTING.
  • Finding the future value a current amount is
    COMPOUNDING.

4
1.1 Discounting and Compounding(contd)
  • An investment of 1, with a discount rate r
  • Value
    Value
  • Present After One Year Present
    After n-Years
  • B/(1r) B
    B/(1r)n B
  • r is the discount rate
  • 1/(1r) is the discount factor
  • (1r) is the compound factor
  • Ex Present value of 250 for 10 years at 6
    discount rate
  • 4PV 250/ (10.06)10
  • PV 250/ 1.79 139.6 or 250 1/(10.06)10
    139.6

5
Example of Discounting
  • Year 0 1 2 3 4
  • Net Cash Flow -1000 200 300 350 1440

6
1.1Discounting and Compounding(contd)
  • Discounting Net Benefits
  • - the period (number of years)
  • - the size of the discount (r)
  • NPVr0 (B0-C0)/(1r)0 (B1-C1)/(1r)1 ---
  • (Bn-Cn)/(1r)n

7
1.1Discounting and Compounding(contd)
  • In ranking projects, the particular point in time
    to which all the net benefits in each period are
    discounted does not matter.
  • Instead of discounting all the net benefit flows
    to the initial year (year 0), they can be
    dicounted to year k NPV at year k will be a
    constant multiple of NPV in year 0. It will be
    multiplied with (1r). This will not change the
    ranks of the projects, as all projects NPVs in
    year 0 will be multiplied with the same constant
    (1r).

8

Table 4-1. Calculating the present value of net
benefits from an investment project
9
1.2 Variable Discount Rate
  • Discount rates may vary through time.
  • Funds may be very scarce at the beginning of the
    project and the discount rates may be very high.
  • This will fall in the following years as the
    supply and demand for funds return to normal

10
1.2 Variable Discount Rates
  • Adjustment of Cost of Funds Through Time
  • For variable discount rates r1, r2, r3 in years
    1, 2, and 3, the discount factors are,
    respectively, as follows

1/(1r1), 1/(1r1)(1r2)
1/(1r1)(1r2)(1r3)
11
1.3 Factors Affecting the Discount Rates for
Public Projects
  • Discount rate for a private investment is the
    weighted average of
  • Rate of return from the sale of equity
  • The cost of borrowed funds
  • Discount rate for a public sector investment is
    the Economic Opportunity Cost of Capital (EOCK).
    This rate reflects the opportunity forgone for
    not using the funds in an alternative public
    project. It considers the lost opportunity for
    the whole economy. It reflects the true cost of
    the resources (funds) used.
  • EOCK is taken as 12 by the World Bank for
    developing countries.

12
1.3 Factors Affecting the Discount Rates for
Public Projects (cont)
  • If significant market distortions exits i.e.
    domestic distortions (taxes and subsidies), and
    external distortions (tariffs and subsidies for
    exports), the market price of inputs and outputs
    of the projects do not reflect the true costs of
    the resources. Their economic (shadow) prices
    should be used in public projects.
  • For public sector projects, economic analysis
    (rather than financial analysis) is more
    relevant. Economic analysis uses the EOCK (rather
    than the discount rate) and the economic values
    (rather than the market prices).

13
1.3 Factors Affecting the Discount Rates for
Public Projects (cont)
  • Financial Analysis
    Economic Analysis
  • Financial discount rates
    EOCK
  • Market prices Economic values
  • More relevant to private sector More rel.
    to public sector
  • Owners and bankers point of view
    Economy point of view

14
2. Alternative Investment Criteria
  • First Criterion Net Present Value (NPV)
  • What does net present value mean?
  • Measures change in wealth
  • Use as a decision criterion to answer following
  • a. When to reject projects?
  • b. Select project (s) under a budget constraint?
  • c. Compare mutually exclusive projects?

15
2.1 Net Present Value Criterion
  • a. When to Reject Projects?
  • Rule Do not accept any project unless it
    generates a positive net present value when
    discounted by the opportunity cost of funds
  • Examples
  • Project A Present Value Costs 1 million, NPV
    70,000
  • Project B Present Value Costs 5 million, NPV -
    50,000
  • Project C Present Value Costs 2 million, NPV
    100,000
  • Project D Present Value Costs 3 million, NPV -
    25,000
  • Result
  • Only projects A and C are acceptable. The
    country is made worse off if projects B and D are
    undertaken.

16
2.1 Net Present Value Criterion (Contd)
  • b. When You Have a Budget Constraint?
  • Rule Within the limit of a fixed budget,
    choose that subset of the available projects
    which maximizes the net present value
  • Example
  • If budget constraint is 4 million and 4 projects
    with positive NPV
  • Project E Costs 1 million, NPV 60,000
  • Project F Costs 3 million, NPV 400,000
  • Project G Costs 2 million, NPV 150,000
  • Project H Costs 2 million, NPV 225,000
  • Result
  • Combinations FG and FH are impossible, as they
    cost too much. EG and EH are within the budget,
    but are dominated by the combination EF, which
    has a total NPV of 460,000. GH is also possible,
    but its NPV of 375,000 is not as high as EF.

17
2.1 Net Present Value Criterion (Contd)
  • c. When You Need to Compare Mutually Exclusive
    Projects?
  • Rule In a situation where there is no budget
    constraint but a project must be chosen from
    mutually exclusive alternatives, we should always
    choose the alternative that generates the largest
    net present value
  • Example
  • Assume that we must make a choice between the
    following three mutually exclusive projects
  • Project I PV costs 1.0 million, NPV 300,000
  • Project J PV costs 4.0 million, NPV 700,000
  • Projects K PV costs 1.5 million, NPV 600,000
  • Result
  • Projects J should be chosen because it has the
    largest NPV.

18
2.1 Net Present Value Criterion (Contd)
  • Constraints of Using NPV
  • NPV, not only tells you whether the project will
    be accepted or rejected but also gives you the
    present value of the surplus or the deficit of
    the project. This is an advantage for NPV.
  • If the life periods of the strickly alternative
    projects are not the same, adjustments have to be
    made, so that the projects will be compared for
    the same lenght of lives.
  • It is not correct to compare the NPV of a gas
    turbine plant with a life of 10 years, to a coal
    plant with a life of 30 years. Their lenght of
    lives should be equated by repeating the gas
    plant for three times.

19

2.2 Benefit-Cost Ratio
  • It is a widely used by the analysts. Should be
    very careful, otherwise incorrect and misleading
    decisions can be made.
  • Benefit-Cost Ratio (R) Present Value
    Benefits/Present Value Costs
  • Basic rule
  • If benefit-cost ratio (R) gt1, then the project
    should be undertaken.
  • Problems?
  • Sometimes it is not possible to rank projects
    with the Benefit-Cost Ratio
  • Mutually exclusive projects of different sizes
  • Mutually exclusive projects and recurrent costs
    subtracted out of benefits or benefits reported
    gross of operating costs
  • Not necessarily true that RAgtRB that
    project A is better

20
2.2 Benefit-Cost Ratio (Contd)
  • First Problem
  • The Benefit-Cost Ratio Does Not Adjust for
    Mutually Exclusive Projects of Different Sizes.
  • For example
  • Project A PV0of Costs 5.0 M, PV0 of
    Benefits 7.0 M
  • NPVA 2.0 M RA 7/5 1.4
  • Project B PV0 of Costs 20.0 M, PV0 of
    Benefits 24.0 M
  • NPVB 4.0 M RB 24/20 1.2
  • According to the Benefit-Cost Ratio criterion,
    project A should be chosen over project B because
    RAgtRB, but the NPV of project B is greater than
    the NPV of project A.
  • So, project B should be chosen

21
2.2. Benefit-Cost Ratio (Contd)
  • Second Problem
  • The Benefit-Cost Ratio Does Not Adjust for
    Mutually Exclusive Projects where the Costs are
    treated in different ways.
  • Project A Project B
  • PV of gross benefits 2,000 2,000
  • PV of operating Costs 500 1,800
  • PV of capital costs 1,200 100
  • B/C Ratio (Operating costs netted out of the
    benefits)
  • RA (2000-500)/1200 1.15 RB
    (2000-1800)/100 2.0
  • Project B is preferred to Project A (RB gt RA
    ).
  • 2. B/C Ratio (Operating costs added to capital
    costs) RA 2000/(1200500) 1.18 RB
    2000/(1800100) 1.05
  • Project A is preferred to Project B (RA gt RB
    ).
  • NPV of a project is not sensetive to the way the
    acountants treat costs. Thus NPV is far more
    reliable than B/C ratio as a criterion for
    project selection.
  • Conclusion The Benefit-Cost Ratio CANNOT be used
    to rank projects

22
2.3 Pay-Out or Pay-Back Period
  • It is widely used criterion as it is very easy to
    apply. Unfortunately it can give misleading
    results especially in cases of investment with a
    long life.
  • In a simplest form, it measures the number of
    years it will take for the undiscounted net
    benefits (positive net cash flow) to repay the
    investment. If the number is greater than an
    arbitrary chosen year, the project is accepted.
  • In more sophisticated form, it divides the
    discounted net benefits over a given year with
    the discounted investment costs. If the number is
    greater than 1, the project is accepted. One
    assumes that after the chosen net benefits are so
    uncertain (war and political inability) that they
    can be neglected. This assumption is not
    realistic in cases of bridges and roads, etc.

23
2.3 Pay-Out or Pay-Back Period
  • Project with shortest payback period is
    preferred by this criteria
  • There is no reason to expect that quick
    yielding projects are superior to long term
    invetments.

24
Figure 4.2 Comparison of Two Projects With
Differing Lives Using Pay-Out Period Criterion
25
2.3 Pay-Out or Pay-Back Period (Contd)
  • In such situations pay-back period criterion
    gives wrong recommendation for choice among
    investments.
  • Assumes all benefits that are produced by in
    longer life project have an expected value of
    zero after the pay-out period.
  • The criteria may be useful when project subject
    to high level of political risk.

26
2.4 Internal Rate of Return Criterion
  • IRR is the discount rate (K) at which the present
    value of benefits are just equal to the present
    value of costs for the particular
    project.....(IRR k) wkich equates the net
    benefits ti zero.
  • NPVr 0 0 (B0 - C0 ) (B1 C1 )/((1k)1
    (B2 C2 ) / (1k)2
  • Bt - Ct
  • (1 K)t
  • Note the IRR is a mathematical concept, not an
    economic or financial criterion
  • Common uses of IRR
  • (a). If the IRR is larger than the cost of funds
    then the project should be undertaken
  • (b). Often the IRR is used to rank mutually
    exclusive projects. The highest IRR project
    should be chosen
  • An advantage of the IRR is that it only uses
    information from the project
  • Another advantage of IRR is that it does not
    require the calculation of EOCK. With NPV one has
    to calculate the EOCK in the economic analysis.

0
27
2.4 Difficulties With the Internal Rate of Return
Criterion
  • First Difficulty Multiple rates of return for
    project
  • Solution 1 K 100 NPV -100 300/(11)
    -200/(11)2 0
  • Solution 2 K 0 NPV -100300/(10)-200
    /(10)2 0

28
2.4.1 Difficulties With the Internal Rate of
Return Criterion(IRR Makes Misleading Choice
under following conditions)
  • For Single Projects
  • If the net cash flow is negative in the initial
    year (due to initial investment) but all positive
    in the following years, then IRR has a unique
    solution i.e. One solution
  • If negative net cash flows take place after the
    negative net cash flow in intial year, we cannot
    have a unique solution for the IRR. You will have
    two values for IRR (figure 4.3)
  • If there is a large negative benefit in the
    final year of the project, there will not be a
    unique solution for IRR again.

29
Figure 4.3 Time Profiles of the Incremental Net
Cash Flows for Various Types of Projects
Bt - Ct

time
-
Bt - Ct

time
-
30
  • Second difficulty Projects of different sizes
    and also strict alternatives

31
2.4.3 Difficulties With The Internal Rate of
Return Criterion (Contd)
32
2.4.4 Difficulties With The Internal Rate of
Return Criterion (Contd)
Write a Comment
User Comments (0)