Title: Electricity Network Connectivity
1Electricity Network Connectivity Between the GCC
Countries
Presented By Adnan I. Al-Mohaisen May 17, 2005
2BIRTH OF THE GCC POWER GRID
- Originated in the early 1980s by a local GCC
committee from the electricity sector. - In 1986 the first project study was conducted by
a committee from the GCC in coordination with
the Kuwait Research Institute and King Fahad
University of Petroleum and Minerals. - The study was updated in 1990 by Gulf Investment
Bank and SNC-Lavalin to confirm the
interconnection was economical and financially
viable. - In 2003 another study update was undertaken as a
final preparation for the project financing and
tendering, in which the following topics were
covered - Techno-Economic Analysis
- Market Study
- Financial Analysis
- Interconnection Agreement
- Implementation Strategy
3GCC INTERCONNECTION AUTHORITY
- Established in July 2001 by a Royal Decree No.
M/21. - Owned by the six GCC Countries the authorized
share capital is - (US 1,100,000,000) divided into (1,100,00)
shares of (US 1,000) each share. - The Authority is managed by a (twelve member)
Board of Directors each member country is
represented by two members. The Chairmanship is
rotated among the member states every three
years. - The official domicile of the Authority is
Dammam, with the Control Center to be located in
Ghunan, Saudi Arabia. - The primary objective of the Authority is to
- link up the power grids of the six GCC countries
- operate and maintain the interconnection
4INTERCONNECTION SHARE CAPITAL
Based on the 1990 Project Study it was determined
that the share of the cost of the interconnection
will be the present worth of the capacity savings.
5INTERCONNECTION LINK
- The interconnection is to be constructed in 3
phase, namely
Phase II
Phase I
Phase III
- Phase I will interconnect Al-Zour (Kuwait),
Al-Fadhili, Ghunan, Salwa (KSA) and Doha South
(Qatar) with a 400 kV OHL, and a 400 kV Land
Submarine cable with Al-Jasra (Bahrain).
- Phase II will integrate the UAE system with a
400 kV OHL from Shuwaihat to Al-Ouhah.
- Phase III will interconnect Salwa and Shuwaihat
with 400 kV OHL and Al-Ouhah and Al-Waseet in
Oman with a 220 kV OHL.
6INTERCONNECTION CRITERIA
7SINGLE-LINE DIAGRAM
8BENEFITS COSTS
Upon the completion of Phase-I and the reduction
of generation capacity the total cost savings
rate of return after 4 years from operations is
2.5 billion US Dollars.
9BENEFITS COSTS
Upon the completion of Phase-III the total cost
savings rate of return after 3 years from
operations is 3.35 billion US Dollars.
10PROJECT ECONOMICS
- The capital cost of constructing Phase I
estimated at US 1,189 million is depicted below
- It is further estimated that it will cost
approximately 30 million annually to operate
and maintain the Grid
- The estimated cost for constructing Phase III is
US 137 million. -
- Although the construction of Phase II is not
under GCCIA task it is estimated that its
construction to be approximately US 300 million.
11PROJECT ECONOMICS
- The GCC Grid is expected to reduce the amount of
new generation capacity required by the GCC
member states by sharing the reserve capacity
that needs to be maintained by each system to
ensure reliability and provide protection against
outages. The capacity benefits to Year 2028 are
shown below
Isolated System
Interconnected System
- The cumulative benefit in MW of the
interconnected system as opposed to isolated
systems will be 5,113 MW.
12INTERCONNECTION BENEFITS
- Reduce generation reserves
- Provide power exchange and strengthens supply
reliability - Improve the economic efficiency of the
electricity power systems - Strengthens operational efficiency
- Promoting utilities to construct larger
generation units to share extra generated power - Provide opportunities for industrial customers
and utilities to shop around for more attractive
supply of power - Adopt technological development and use the best
modern technologies - Providing long-term environmental advantages by
reducing waste emissions from increasing
generation plants.
13GLOBAL INTEGRATION
- The technical and economical feasibility study
for the GCC Interconnection has been proven. - The GCC Interconnection will enhance the Power
Systems of the GCC Countries. - The GCC Countries will be a significant part of
the Pan-Arab Grid. - The GCC Interconnection is the main gateway
towards a Regional and Pan-Arab Power Pools. - The Power Grid is a fundamental step leading to
the liberalization of regional power market.
14PROJECT STATUS
- September 2004 SNC-Lavalin of Canada was hired
to perform the Tendering and Adjudication for the
Phase I Project. - Thirty three (33) out of the sixty five (65)
companies were pre-qualified where some
companies qualified for only one lot and some
qualified for all five lots.
- Pre-qualified companies were from local GCC and
international countries. - GCCIA will engage an international consulting
firm affiliated with a local GCC firm for the
Supervision of the Construction of the Phase-I
Project.
15PROJECT SCHEDULE
16For further information you can access our
website at www.gccia.com.sa THANK YOU