Title: CIVL 202 Construction Engineering I
1CIVL 202Construction Engineering I
- Tutorial 1
- T1 Mon 1100-1150
- T2 Wed 0900-0950
2Construction vs Manufacturing Process
Construction Process Manufacturing Process
Nature Service-oriented Product-based
Quantity of Production Single and unique product Mass/batches of units
Target Purchaser Clients who need a facility Without designated purchaser
Focus Planning and controlling resources within the timeframe of project Applying resources over the life of extended production run of many unit
3Construction and Manufacturing Process
- Manufacturing Process
- Construction Process
-
-
Design and Fabricate units
Units in inventory
Distribute units for sale
Preliminary Design
Final Design
Construction
4Sequence of Project Development
- Three parties
- Owner who needs for a facility
- Designer who designs the facility on the basis
of owners need - Constructor Contractor, who constructs the
facility on the basis of the design
5Sequence of Project Development
- Owner shows a need for the facility
- Designer carries out feasibility studies and cost
estimations - Obtain a conceptual design and approximate cost
estimate - Proceed with detailed design
- Advertising project
- Acceptance of proposal and construction commenced
- Project testing and maintenance of the facility
6Construction Technology and Management
- Technology
- techniques used to place physical materials and
elements of construction - Management
- 4M resources manpower, machines, materials and
money - Construction manager should consider optimum
application of 4M resources, should also consider
quality, time and money constraints
7Structure of Construction Industry
- Building
- Habitational, institutional, educational,
commercial, social, recreational, office
building, shopping centers, sports complexes - Engineered
- Highways Project and Heavy Project
- Industrial
- Highly technical projects in product
manufacturing and processing
8Management
Organizational
Project
Activity
Operations
Process
Work task
9Preparing the bid package
- Establishing Need
- Establishment of a need of certain facility for
users - Social needs? Economic needs?
- Need Evaluation
- Cost/benefit analysis
- Graphical representation of the project and a
layout diagram - Cost estimate based on the conceptual-level
information available
10Conceptual Drawings and Estimates
- Cost/benefit analysis, layout drawings, 3D models
- Cost estimate conceptual drawing
- Estimate based on specific cost indexes
11Design of a facility
- Preliminary design
- General layout, floor plan, building cladding,
finishing, heating system, foundation support,
structural frame - Detailed design
- Gives a detailed design to ensure the design is
within owners financial resources and to
evaluate bids