Title: Why Utility Maintenance Is Rarely Self-Funding
1Why Utility Maintenance Is Rarely Self-Funding
- EEI TDM Conference
- Spring 2003
- St. Louis, Mo.
Dan ONeill, Navigant Consulting
2Executives often ask, How can I spend a dollar
to save a dollar?Or, where is the point when a
dollar of PM saves a dollar of CM?
illustrative
3The answer is, Dont go there. You wont be
allowed to stayCustomers and regulators will
demand better reliability than that
illustrative
Acceptable reliability
4It normally costs 10,000 or more to avoid a
tree-caused outageThis figure usually surprises
utility executives
Cost per avoided outage
Outage reduction factor
Outage rate per mile
Trimming cost per mile
2,000 ( .40 x 50
) 10,000 Or, for comparability to capital
projects, take the present value of 2,000 every
four years at a 10 discount rate 5,700
( .40 x 50 )
28,500
- Notes
- Outage rate should be what it would be if not
trimmed at the normal end of cycle, e.g., fourth
year, which is higher than the average
tree-caused outage rate - Trimming cost is for contact trimming only, not
removal - Effectiveness rate recognizes some skips, fast
growth, limited permissions, and non-contact
outages like fallen tree/broken limb
5But, it normally costs only about 1000 to
restore an outageSo, the PM cost is nowhere near
the first-year CM savings
Resource Per Unit Need Per Resource
Resource Units Rate Outage Cost Trouble
responder 1 hour 100 1.0 100 Repair crew (2
x) 4 hours 200 0.4 320 Call taker .1
hour 30 10.0 30 Additional switching 1
hour 100 0.2 20 Additional repair crew 4
hours 200 0.1 80 Sub-total average
labor 550 Material fuse 1 50 1 50 Materia
l pole, X-arm, etc. 1 2000 .2 400 Sub-total
average material 450 Total cost 1000
- Notes
- Time for supervisor, dispatcher, etc., included
in loaded labor rate - Although some outages are more severe, often they
are not very preventable, either
6Taking credit for all future outages still
doesnt get you thereIt puts the break-even
point within sight, but still just out of reach
Present value of all future avoided CM
Discount rate
Annual avoided cost of outages
Present value of current and future PM
1,000 .10 10,000
28,500
Implies a 10-year payback
- Notes
- The discount rate reflects the weighted average
cost of capital (plus risk premium, if any) - Higher costs of capital in the past, e.g., 15,
were associated with higher rates of inflation - Dividing by the discount rate is a shorthand way
of getting the present value of a stream of
income. It assumes a perpetual annuity. For
30 years instead, divide by .106 1/9.43 - If you assume 10 includes 3 inflation for the
annual outage costs, then the discount rate would
be .07, and the PV would be almost 15,000, but
not if offset it with a 3 risk premium - Many executives are not comfortable with a
10-year payback even though the financial
analysis says that it is appropriate for a 10
cost of capital
7For URD cable replacement, the situation is just
as badEven if the repair cost is assumed to be
twice as high (unless you only replace one
section at a time when its failure rate is bad
enough)
Cost per avoided outage
Outage reduction factor
Outage rate per section
Replacement cost per 200 section
6,000 ( .40 x 100
) 15,000 Or, for entire loops or
subdivisions 6,000 ( .10
x 100 ) 60,000
- Notes
- Outage rate is based on the typical rule of
replacing a segment if it fails 3 times in the
last ten years, adjusted to 33 worse for
increasing deterioration - Replacement cost is based on 30 per foot on a
200 segment, replacing direct buried cable with
direct buried cable, plus lawn restoration.
Replacing with conduit and cable would be more
expensive. Injecting with silicon would be about
half as expensive where it is feasible, but
usually requires multiple sections, not all of
which may be failing at a high rate. - Each time one section of URD cable in a half-loop
fails, all customers in that half-loop see an
outage (and all in the other half see one during
switching), so the outage rate of the loop is
often much worse than that of any section
8Likewise for lightning mitigation, etc.And
remediation of other low-incidence pole-top
causes
Cost per avoided outage
Outage reduction factor
Outage rate per pole
Mitigation cost per pole
1,500 ( .05 x 50
) 60,000 1,500 ( .10
x 50 ) 30,000
- Notes
- Outage rate is based on 2 lightning-caused
outages per mile and 40 poles per mile - Mitigation cost is based on a three-arrester bank
and/or improved grounding - Effectiveness rate is based on reported field
experience, some of which is even lower, because
lightning will tend to find the weakest link in
mitigation - In order for the PV of the avoided CM cost to
equal the PV of the PM investment, the outage
rate per pole would have to be .3, or about every
3rd pole, or 12 per mile for that cause of outage
alone, e.g., lightning
9Part of the problem is that utilities do not
really have a sharp pencilTypical failure
rates on remediation programs are too low
5 failure rate of replaced equipment
Replace 20 units to avoid one failure
If we knew more precisely which unit or mile to
replace or remediate, we could make preventive
maintenance more cost-effective
.2 avoided outages per mile remediated
Remediate 5 miles of line to avoid one outage
5 reject rate on pole inspection
Inspect 20 poles to find one to replace
- Notes
- Outage rates per mile for worst-circuit programs
sometimes reach high levels, but if that were all
you did, overall reliability would probably keep
getting worse - Replacing failure-prone equipment on a system
wide basis is rarely cost-effective. You have to
target the highest failure rate (worst first) - Information is usually lacking to discriminate
more finely among classes of equipment to find
the one that is most likely to fail next
10One solution is to recognize the business value
of reliability At a value to the utility of
about 25 per customer interruption per year
Reactive Response Cost 2.5 Mil./yr.
PQ Rel. Cust. Sat. 2.8
Customer Interruptions -100,000
Overall Cust. Sat. .64
SAIFI -.14
-100,000 CI / 700,000 Cust. -.14 SAIFI
PQ Rel. Cust. Sat. 23 of Overall Cust. Sat.
Reactive Response 4 Mil./yr. per Cust. Sat. Pt.
10 Points PQ Rel. Cust. Sat. per .5
SAIFI
I.e., a 10-point drop in utilitys customer
satisfaction would require a 40 million response
by utility
Source JD Power Associates, with Navigant
Consulting
11Many utilities are already seeing such reactive
response costsPenalties/refunds of 25 to 100
per customer interruption are appearing
- Customer refund programs (In addition to
reliability improvement programs) - ComEd Commitment 60-100 per customer
interruption over 8 hours - IPL refund 100 per customer interrupted over
24 hours - PacifiCorp guarantee Up to 100 per customer for
missed service levels - Entergy-TX refund 33 per customer per year (for
120,000 customers) - PBR Programs (Each of these companies agreed to
penalties for SAIDI/SAIFI) - All NY State Utilities (ConEd, National Grid,
Central Hudson, Energy East, etc.) - All MA Utilities (NSTAR, National Grid, NU
(WMECO) - All CA Utilities (PGE, SCE, SDGE)
- Xcel (in NSP/New Century merger agreement)
- Western Resources (in WR/KCPL proposed merger
agreement)
12With such costs included, PM can be
cost-effectiveAnd utilities can go where a
dollar of PM can save a dollar of cost
illustrative
Note At 25 per customer interruption, the value
per outage would be 2,500 - 25,000 per outage,
depending on whether the outages were on
100-customer taps or 1000-customer feeder
backbones. And the PV of all future avoided
outages would be ten times that.
13Such values can be built into a funding curve
methodologyNavigant Consultings methodology
incorporates this concept
Vertical axis shows cumulative value of projects
to company
Each project is shown adding to totals, ranked by
value/cost ratio
- Option Development
-
- Developing
- cost-effective alternatives for possible funding
- Additions
- Upgrades
- Replacement
- Maintenance
- Standards
- Systems
- Results Monitoring
- Measuring managing the drivers of the funded
projects and processes - Benchmarking
- Unit costs
- Failure rates
- Event impacts
- Value added
Horizontal axis shows cumulative project cost
Exempt
14Any questions?