Title: Equipment Efficiency: Availability, Quality and SMED
1Equipment EfficiencyAvailability, Qualityand
SMED
- Operations Analysis and Improvement
- 2009 Spring
- Dr. Tai-Yue Wang
- Industrial and Information Management Department
- National Cheng Kung University
2Presentation
- It has become increasingly important to
economically manufacture products in smaller
product batches. - Product lead times must be kept as small as
possible. - Product customization continues to increase.
- Number of parts produced on manufacturing systems
continues to increase - Batch sizes have been reduced.
3Presentation
- Companies should be as agile and flexible as
possible. - Reduce machine set-up time times to minutes
instead of days or hours. - The Single-Minute Exchange of Dies (SMED) is a
clear easy-to-apply methodology. - Good results in many cases very quickly.
- It was developed by Shigeo Shingo in Japan from
1950-80s. - Achieve good results without costly investments.
4Introduction
- Set-up process.
- Time required to go from the end of the last good
part from one batch to when the first good part
of the following batch is produced. - The trials needed to obtain the first good
product are considered part of the set-up process.
5Introduction
- SMED -gt Single-Minute Exchange of Die.
- Designed so that the set-up process should be
made in less than 10 minutes. - During the 1960s the set-up time for a large
stamping press could take more than a full day. - It is possible to achieve reductions around 60
of the original set-up time. - In reductions of about 90 the project costs
become significant. - It is not always necessary to reduce the machine
set-up process. - Tires on your personal vehicle vs. car racing.
6Introduction
- SMED is contemplated in the Just-in-time and
in the 20 keys methodologies (key number 5). - SMED improves the availability rate as well as
the quality rate. - This set-up time includes the trial phase.
- Startup losses included in the quality rate are
produced in this trial phase
7Basic steps in a set-up process
- Four typical classes of set-up operations
regardless the type of the machine or equipment. - Prepare, adjust and check (new materials and
tools). - Remove old tooling and install new tooling on the
machine. - Measure, set and calibrate (fixtures, tools and
tooling). - Produce initial parts (production trials) and
adjust the machine..
8Basic steps in a set-up process
- Prepare, adjust and check operations focus on
making sure that the tools and materials that
will be used for set-up are available when the
set-up is scheduled. - Produce initial parts and adjust depends on the
set-up specialists know-how.
9Traditional strategies
- For high volume manufacturing applications, the
set-up process duration was not particularly
important. - Manufactures could afford to have customers
waiting. - Production was scheduled based on manufacturing
needs. - These set-ups hardly affected the products
price. - Shutdown production facility to for two weeks
while machines and tools were set-up for new
model year production. - Today, manufacturing lot sizes have decreased.
- Manufacturing flexibility needs to increase.
- Same quantity -gt increased part variety and with
smaller delivery quantities.
10Traditional strategies
- The possible production of defective parts at
set-up coupled with the increased frequency of
set-up has forced manufacturers to make more
products than required. - In order to reduce set-up process affects,
companies usually use two different strategies. - Try to make the set-up as fast as possible.
- Increase the production lot size.
11Skilled based strategies
- Many companies have used set-up specialists to
reduce changeover and set-up times. - Skilled in the operation of specific machines.
- Familiar with the needed tools and methods to
carry out the exchange.
12Skilled based strategies
- Dependence on these specialists can be strong.
- Skill that a set-up specialist needs.
- Set-up process complexity.
- Not all the tasks that set-up specialists carry
out are critical. - The specialist can get help from the machine
operator.
13Large batches based strategies
- The larger the batch size is, the smaller the
impact of the set-up time will be on the
production cost of each part. - Cost per part is based on the company cost
system. - The system shares all company costs to each
product. - There is a section that depends on the time to
manufacture and also on its respective set-up
time. - If the lot size is large, the set-up time effect
is spread out more than if the lot size is small.
14Large batches based strategies
- The higher the set-up time, the bigger the profit
will be. - This reasoning supports the lot size increasing.
- Some companies only accept orders that exceed
certain lot sizes.
15Large batches based strategies
- If set-up time and production time were about the
same magnitude - it would not make sense to search for large
lots size.
16Economic Lot Size strategy
- Large set-up times -gt large batch size.
- Increase in inventory cost and potential loss for
products becoming obsolete. - The economic lot size is a direct relationship
between the inventory cost and the set-up cost. - The effect of the set-up cost decreases
exponentially according to the increase of the
batch size. - This hypothesis is based on a constant set-up
time.
17Economic Lot Size strategy
- As set-up cost decreases, the economic lot size
would also decrease until reaching the unit
product lot size. - It would be profitable to only accept orders made
up of one article a batch size of one!
18SMED methodology
- 1950 in Toyo Kogyo factory.
- Shingo discovered that the exchange of an 800 ton
press was delayed because of a missing screw. - Two types of operations in the process of change.
- Those that should be carried out with the machine
running producing parts from the previous lot. - Shingo called these activities External set-up.
- Those that required the machine and for it to be
idle while they were performed. - Shingo denoted as Internal set-up.
19SMED methodology
- In 1957 Shingo improved the SMED methodology.
- Placing an extra table in a Mitsubishi Company
machine. - Convert some of the internal set-up tasks to
external set-up operations. - Shingo reduced the set-up time for a screw
machine manufacturer from 8 hours to 58 seconds. - At the Mitsubishi Company from 24 hours to 2
minutes and 40 seconds.
20SMED. 4 conceptual stages
21Preliminary stage
- Studying the current set-up process because
simply put what is unknown cannot be improved. - Know the process, the variability and the
cause(s) that produce this variability. - Collect values for the set-up times.
- set-ups can be frequent or sporadic.
- By means of the time study process.
22Preliminary stage
- the SMEDs goal is not to eliminate specialists
job. - set-up specialist opposition can lead to project
failure.
23Separating internal and external set-up
- Classify set-up operations according to the given
definition of external and internal set-up. - It takes into account the same operations and
duration included in the current method. - Without improving any particular operation.
24Separating internal and external set-up
- Assure that the operations defined as external
set-up can all be carried out with the machine
running. - Time to get the necessary tools and materials is
not allocated to the operators. - It is possible to reduce the exchange time by as
much as 60 without any capital investments.
25Converting internal set-up to external set-up
- The set-up process time reduction from the first
stage can be very significant but is not where
SMED ends.
26Converting internal set-up to external set-up
- This stage examines two important aspects.
- Re-evaluate the internal set-up.
- Check or see if some of them were considered
erroneously as internal. - Look for alternatives that allow internal set-up
to be carried out in whole or in part as external
operations. - For example, is it possible to screw a die to a
press before placing it inside the press chamber?
27Converting internal set-up to external set-up
- This stage will require an economic investment.
- Carry out a cost justification.
- Sometimes the investment will be necessary in
spite of the economics.
28Converting internal set-up to external set-up
- Other important aspect to consider.
- New process or system reliability.
- The possible appearance of new operations.
- The benefits and possible risks of the new
process. - It is possible to achieve set-up process time
nearing ingle minutes (lt 10 minutes)
29Streamlining all aspects of the set-up process
- This stage tries to improve all the set-up
operations. - Both internal and external.
- Trying to eliminate some operations.
- SMED methodology recommends that one follows
systematically these four stages. - Common sense -gt not be invested in operations
that previously have not been optimized.
30Streamlining all aspects of the set-up process
- stage 3.
- Improvement of the external set-up operations.
- Revisit of the internal activities that have not
been possible to convert into external.
31First stage tools
- Numerous time wastes take place in many set-up
processes. - Materials are moved to the warehouse with the
machine stopped. - Tools and dies are supplied late, or incorrectly.
- Tools and dies that are not needed, are taken
back to the supply room before starting the
machine.
32First stage tools
- Some required screws and tools were not collected
during the set-up process. - Some nuts are just too tight when trying to
remove them. - It is necessary to eliminate all these wastes.
33First stage tools
- Try to answer certain questions before starting
the set-up. - What has to be done before starting the change?
- How many screws are necessary in order to fix the
die? Of what type? - What tools are necessary? Are they prepared for
proper conditions? - Where should the tools be placed after using them?
34First stage tools
- A group of visual controls have been developed.
- Checklist.
- Questionnaire that should be checked before each
set-up process. - Verify in advance that all elements that should
be prepared are in fact ready and available. - Can be universal for all products changeover or
specific for each product.
35First stage tools
- Check panel placed next to the machine.
- Small number of tools or exclusive tools.
- The worker can visually check if all the
necessary tools are located. - In some check panels the tools are silhouetted.
- Another strategy is to code the tools with two
stickers. - A sticker is placed in the machine and another is
placed on the tool.
36First stage tools
- Function checks.
- The checklist or the check panel do not show the
die and tools status. - Material inlays.
- Special devices for checking the molds before
placing them in the machine. - If the company does not own one -gtsecond stage.
37First stage tools
- Parts and tools transportation improvements.
- Transportation from the warehouse to the work
area should be carried out before the exchange
begins. - traditional press exchange process
- Removes the used mold -gt loads it in a crane -gt
takes it to the warehouse -gt loads the new mold
-gt place it. - new changeover process
- Load the new mold -gt leave it next to the
machine -gt take out the mold -gt leave it next to
the machine -gt loads up the new mold -gt set the
machine into operation -gt carry the used mold to
take it to the warehouse.
38First stage tools
- This new changeover looks like it takes longer
than the traditional method. - According to Shingos definition of set-up time,
the time with the machine stopped is drastically
reduced.
39Second stage tools
- The second stage usually runs parallel with the
third stage. - SMED methodology offers some recommendations that
facilitate complex cases studies. - Movements around the machine should not be
questioned. - Will be analyzed in the third stage.
- It is not that some operations will be
eliminated. - There are several methods broadly intended to
enhance the set-up process.
40Endless material method
- When a reel is empty, it should be removed and
replaced with a full one. - Rolling mill or on packing machines.
- The changeover time of reels could potentially be
eliminated if the end of a reel is welded or tied
to the beginning of the following one. - The product made with the welding seem would be
scrape.
41Endless material method
- Temporary containers.
- If it is not possible to weld or tie the reels to
carry out the changeover operation. - Save set-up time considerably because they
eliminate the movements to locate and bring in
the new reel. - If the reels allow it, it might be possible to
tie the previous reel with the following reel and
with a simple turn, carry out the exchange.
42Second stage tools
- Press die preheat.
- There are devices that heat the molds up before
being placed in the machine. - The main concern in this case is labor safety.
- Function standardization.
- Standardize some measures (height and depth).
- The set-up process should be as safe as before.
- The quality of the manufactured pieces should not
be adversely affected. - Add new functionalities or features to the mold.
43Second stage tools
- Tools duplication.
- Have two or more identical elements (cranes,
tools, pallets,) to reduce the set-up time. - A single six pack is as easy to handle as a
single can of soda. - With a double crane it is possible to prepare the
next mold and to extract the previous one without
the need of removing and placing the molds again.
44Third stage tools
- The improvement or elimination of an operation
requires reengineering some aspect of the product
or process. - it is possible to make the operation in a
different way? - Is this operation necessary?
- Is this procedure the most appropriate?
45Third stage tools
- Up to this stage, external operations have not
been analyzed. - Will the set-up specialist have enough time?
- Schedule the changeovers so that the specialists
are not needed at the same time in two machines. - Internal operations can be improved.
- Analyze in detail the movements around the
machine. - Determine the optimal number of workers that
should take part in the set-up process.
46Improving tool storage. Indicators strategy
- Begin with the 5Ss.
- Organize tool storage in an efficient way.
- Keeping high use items close for easy access.
- Organizing the tooling so that it is easily
located and identified. - The 5S methodology offers a common orientation
when choosing the coding standards.
47Parallel operations
- For large machines, it is necessary to carry out
operations at the front of the machine as well as
at the back of it. - The worker can waste important set-up time when
walking around the machine. - The set-up time and complexity can be reduced
with the help of a second worker.
48Parallel operations
- Utilize a task map to indicate what operations
will be carried out by each worker - Starting with the initial situation.
49Parallel operations
- Two workers executing the exchange in a parallel
way. - Table shows task sharing and those tasks that can
be carried out simultaneously as well as the
times where the workers should be waiting.
50Parallel operations
- Allows the Lean thinker to discover which are the
most important tasks that should be improved. - Labor safety, once again, is a priority in this
type of synchronized work. - Safety mats that stop the machine when they are
activated. - Confirmation buttons.
51Third stage tools
- One-Motion Method.
- Perform more than one task simultaneously.
- Electric and hydraulic connections.
52Third stage tools
- Functional clamps.
- Devices that are used to passively hold an object
in a fixed position with the minimum effort. - The SMED methodology seeks to eliminate the use
of screws and nuts as fixing elements. - Pear-shaped holes.
- U-shaped washers rings.
53Third stage tools
- Functional clamps.
- C-shaped washers.
- Guttered thread.
- Single-movement method.
- Reduce the tools variety.
54Eliminating trials and adjustments
- Can represent 50 of the total changeover time.
- They are not only decreased but eliminated.
- A set-point should be used instead of an
adjustment. - Without applying the trial and error method.
- The adjusting procedures must be written
- The machine parameters value should be specified.
- OTED (One Touch Exchange of Die).
55Process Automation
- The last resource after the successful
implementation of the previous methods. - Process automation supposes high investments
costs. - Regardless of its expensive implementation, in
some cases it is the best alternative.
56Zero changeover
- When Shingo died in 1990, Sekine and Arai
continued his work. - They tried to achieve set-up times of less than a
minute. - They create a strategy called Zero changeover.
57Zero changeover
- The only way to achieve set-up times near to
seconds was to automate the exchange process. - Represents large investments.
- Many of the achieved improvements, came from
ideas developed by Shingo.
58SMED effects and benefits
- Easier set-up process.
- New changeover procedures.
- Set-up process is simplified and easier to carry
out. - Many of the operations can be carried out by the
majority of the employees. - Increased safety also results from the improved
changeover simplicity. - Eliminate defective parts.
59SMED effects and benefits
- On-hand stock production.
- Manufacturing batch size can be decreased as
well. - Work-in-process will decrease.
- Mean time of material flow will decrease.
- Lead time will decrease too because it is
directly related with the time of material flow. - Workplace tasks simplification.
- Tool coding, a clean and upstanding machine
environment. - Easier to locate tools.
60SMED effects. Productivity and flexibility
- The main benefits.
- Productivity.
- Flexibility.
- Productivity.
- Decrease the machines load in order to increase
the productive period. - SMEDs principal benefit is to increase
flexibility as it will be show next.
61SMED effects. Productivity and flexibility
- Productivity increase.
- SMED is an alternative among other methods
- Increase in flexibility.
- SMED is the only solution
- Buying a new machine does not provide an increase
on the flexibility.
62SMED effects. Productivity and flexibility
63Economic benefits
- Economic benefits depend on the machine situation
in which the SMED is applied. - Saturated machine.
- Liberate the machine from its load time to
increase the machine availability - The benefit takes place due to the economic
margin in the sales increment.
64Economic benefits
- Not saturated machine.
- The necessary time to carry out a production
order will decrease. - Saved cost in the workforce.
- If the goal is to increase flexibility can be
impossible. - Qualitative benefits derived from SMED.
65Summary
- This chapter has presented a basic but helpful
methodology to reduce the set-up time in a
machine. - SMEDs methodology proposes the arrangement of
the needed tools used in the set-up process
before the machine finishes the previous lot.
66Summary
- The main benefit of the set-up time reduction is
the increase in the flexibility of the
production. - Nevertheless, the economic justification of a
SMED project, focus on flexibility increment, is
quite difficult.