  • MARATHON OIL U.K. LTD.
  • CAMPAIGN MAINTENANCE
  • PRESENTED BY
  • DAVID G. DANIELS

2
OBJECTIVE
  • To Campaign the planned maintenance and
    construction workscopes throughout the Brae field
    using a dedicated squad for planned durations on
    each Platform .
  • Size and make-up of squad to be determined by
    activity.

3
OLD STRUCTURE
  • Three platforms each with its own dedicated
    maintenance squad with supervision, planning and
    services to support it.
  • PLUS
  • A field construction squad spread across the
    three platforms with its own supervision
    utilising platform services to support it.

4
REASONS FOR CHANGE
  • A more efficient and organised system of work
  • Core platform crews able to concentrate solely on
    the safe and efficient operation of the platforms
    without the distraction of a heavy planned
    maintenance workload.
  • Increased efficiency of planned maintenance
  • Maturing Asset determines a requirement to
    reduce OPEX
  • Campaign maintenance a part of an overall project
    to reduce OPEX.
  • Introduction of multi skilling / tasking within
    the platform core team.

5
NEW STRUCTURE
  • Smaller multi skilled / tasked platform core
    teams operating the platform and carrying out
    frontline maintenance and breakdowns.
  • PLUS
  • A Field Campaign Team of maintenance and
    construction technicians supported by their own
    service crew including catering. Moving around
    the field working to a planned scope of work for
    a pre-determined period of time on each platform.

6
FIELD CAMPAIGN TEAM
7
FIELD CAMPAIGN TEAM WORKSCOPE
  • Planned Maintenance Routiness gt 1 year
    frequency including
  • Fire and Gas
  • HVAC
  • Lighting
  • Switchboards
  • Transformers
  • Battery Maintenance
  • Telecom Bulk

8
FIELD CAMPAIGN TEAM WORKSCOPE Cont
  • Construction Work Orders
  • Vessel Inspections
  • Pressure Safety Valves
  • Platform Integrity Management and Corrosion and
    Risk management programmes
  • Technical Modification Requests of a manageable
    size

9
FIELD CAMPAIGN TEAM TRANSITION
  • JUNE - SEPTEMBER 2000. Scope of work defined
  • SEPTEMBER 2000. Offshore construction began
    reporting to the Field Campaign Team
    Superintendent . Offshore Planners on board .
  • SEPTEMBER - NOVEMBER 2000. Yearly Planned work
    for 2001 compiled into Plan alongside Platform
    Plans
  • NOVEMBER - DECEMBER 2000. Personnel transfer into
    the Field Campaign Team from all three Platforms
  • JANUARY 2001 - Field Campaign Team commence first
    Campaign on Brae Alpha .

10
PLANNING
  • The preparation of an appropriate schedule and
    plan for the year 2001 is critical to the Field
    Campaign teams success .
  • The PMR man-hours for each Platform were assessed
    and this along with Platform activity determined
    the size of the team, route and length of time to
    be spent on each Platform during the year 2001.
  • This equated to 23 weeks on the Alpha Platform ,
    17 weeks on Bravo and 12 weeks on East .

11
PLANNING cont
  • All known Construction activities were added to
    the overall plan and the hours plotted against
    the Campaign Team manning.
  • Activities have been planned such that the Field
    Campaign Team will remain together for each
    Platform tour . It is essential to their success
    that they are not fragmented throughout the field

12
PROBLEMS ENCOUNTERED
  • HUMAN FACTORS
  • Repetitive work.
    - Positions
    will be rotated with Platform core team posts
  • Reduced morale.
    - Ensure equality
    of conditions with Platform Core Teams
  • PMR deferment.
    - During the
    first year some PFEER and Cat A PMRs will fall
    into backlog on two of the three platforms. Each
    of these PMRs has been risk assessed by a
    Technician, checked by platform supervision and
    approved by the SHE group.

13
PROBLEMS ENCOUNTERED cont
  • Transfer of manpower to the Field Campaign Team

  • - Platform priorities.
    -
    Platform Supervisors reluctant to release
    personnel to the team leading to delays in
    setting up team.
  • Integration of Construction and Maintenance
    Personnel
  • - New methods of working
  • - All personnel will be Task Supervisors,
    no Chargehands or Foreman.