Title: ' ' ' Bryant Cramer
1Section 1 Introduction
. . . Bryant Cramer EO-1 Mission Implementation
Manager
2Purpose of the Meeting
- This is a ? Pre-Ship Review -- the Pre-Ship
Review was held on December 15-17, 1999 - It is a review that combines
- Traditional Pre-Ship Review
- Red Team Review Follow-Up
- Co-chaired by
- Charles Vanek - Director, Office of Systems
Safety Flight Assurance - Ron Thomas - Chairman, EO-1 Red Team
- Objectives of both reviews are combined
- Will not repeat what we have said previously
unless it is necessary to make a point
3Delta Pre-Ship Review Objectives
- A Pre-Ship Review must establish that
- 1) The observatory is finished and all planned
work has been completed - 2) The observatory was properly verified
- 3) It successfully completed an appropriate
environmental test program - 4) Adequate test margins have been demonstrated
- 5) All test anomalies have been fully explored
and explained - 6) All open action items have been closed
- 7) The launch campaign is ready to begin
implementation - 8) All range safety and readiness issues have
been satisfactorily addressed - 9) The ground system will be ready to support the
launch campaign and - 10) A survey of residual risks must be completed
to identify Redbook candidates.
4Office of Systems Safety Flight Assurance
Representatives
- ?PSR Co-Chairman Charles Vanek
- Members
- Tom Cygnarowicz (Flight Assurance)
- Dolf Lekebusch (Flight Assurance)
- Dave Bloom (Engineering)
- John Chitwood (Engineering)
- Chuck Powers (Engineering)
- Louis Fantano (Engineering)
- Eric Holmes (Engineering)
- Robert Vernier (Engineering)
- Vickie Moran (Engineering)
- Oren Sheinman (Engineering)
5Red Team Charter
- Red Team Responsibilities
- Review EO-1 mission in terms of the likelihood of
completing the validation requirements of the
EO-1 Minimal Mission - Comment on the role of single string designs as a
baseline for technology validation missions - Red Teams estimate of the performance level
achieved by the Project in meeting the 13 aspects
of the developmental process - Provide recommendations to improve the status
where the Red Team feels the Projects
performance is inadequate - Ascertain and document all residual risks judged
to be higher than low - Assess all single-point failures and comment as
to their acceptability - Comment on the use of FMEA, FTA, and PRA by the
Project - Provide an overall risk statement
6Red Team Membership
- ?PSR Co-Chairman Ron Thomas
- Members
- Ray Hook
- Ann Merwarth
- Joe Nieberding
- Jean Olivier
- Ken Sizemore
- Ute Ingrid (Judi) vonMehlem
- Ed Goss
- Aldo Domenichini
- Larry Rubert
- Scott Szogas
7AgendaDay 1
TIME SECTION TOPIC PRESENTER 800 1 Introductio
n B. Cramer 820 2 Mission Overview D. Schulz
840 3 Residual Risk B. Cramer 920 4 Systems
Reviews D. Schulz 930 5 Technical Reviews D.
Schulz 940 6 Staffing and Experience D.
Schulz 950 7 Verification Process M. Perry
1030 8 Summary of Recent PRs M.
Perry 1050 9 Flight Software R.
Whitley Lunch Served 1200 10 Advanced Land
Imager C. Digenis 1230 11 Spectral
Registration T. Zukowski 1245 12 Hyperion S.
Carman 130 13 Atmospheric Corrector D.
Reuter 200 14 Spacecraft Systems Management
Approach M. Perry 210 15 Mechanical P.
Alea 300 16 Electrical B. Zink 400 17 Thermal
N. Teti 445 18 Power A. Billings 530 19 Attit
ude Control System P. Sanneman 700 Adjourn
8AgendaDay 2
TIME SECTION TOPIC PRESENTER 800 20 Command
Data Handling P. Luers 845 21 Communications D
. Charlson 915 22 Reaction Control System P.
Sanneman 930 23 WARP T. Smith 1115 24 X-Band
Phased Array Antenna K. Perko
1130 25 Lightweight Flexible Solar Array J.
Lyons 1200 26 Pulse Plasma Thruster C.
Zakrzwski Lunch Served 1215 27 Carbon-Carbon
Radiator G. Hobbs 1230 28 Enhanced Formation
Flying D. Folta 1245 29 GPS J.
Bristow 115 30 Contamination M.
Woronowicz 140 31 Flight Assurance M.
Kelly 220 32 Launch Vehicle D.
Breedlove 300 33 Launch Campaign T.
Gostomski 345 34 Operations / MOC D.
Mandl 515 35 Technology Validations N.
Speciale 530 36 Overall Mission Readiness
Status D. Schulz 600 Adjourn
9EO-1 Remaining Reviews
- Delta Pre-Ship Review 8/9-10/00
- Operational Readiness Review 9/27/00
- Mission Readiness Review 10/5/00
- Launch Readiness Review 11/13/00
- Flight Readiness Review 11/15/00
- Launch Readiness Date 11/16/00