Ontario Wind Energy Storage Case Study

1 / 21
About This Presentation
Title:

Ontario Wind Energy Storage Case Study

Description:

NPV evaluated by Navigant Consulting Inc. with operation data from Huron Wind ... Credit: Navigant Consulting Inc. Huron Wind. Cost-Benefit Case Study $0 ($2, ... – PowerPoint PPT presentation

Number of Views:127
Avg rating:3.0/5.0
Slides: 22
Provided by: oceon

less

Transcript and Presenter's Notes

Title: Ontario Wind Energy Storage Case Study


1
Ontario Wind Energy Storage Case Study
  • Melanie Chamberland
  • 15 June 2008

2
Navigant Distributed Generation Cost-Benefit
Study
  • 6 DG case studies in Ontario with costing data
    and operating history
  • 3 CHP projects, 1 landfill gas project, 2 wind
    farm projects
  • Study conducted by Navigant Consulting Inc.
  • Asses 20 year NPV costs and benefits for DG
    owner, LDC/ratepayers, and society

3
Why Ontario case studies?
  • Competitive electricity market
  • Nuclear, coal, hydro, gas electricity mix
  • Planned coal fired generation shut-downs
  • New generation and peak shaving needed
  • Standard Offer Program tariff structures in
    place
  • Clean Energy Standard Offer Program (CESOP)
    Wholesale Hourly Ontario Energy Price (HOEP)
    price plus on-peak and off-peak premiums
  • Renewable Energy Standard Offer Program (RESOP)
    Flat kWh rate plus a premium for on-peak
    generation

4
Presentation Objective
Hypothetical 900 kW Energy Storage system
Navigant Cost-Benefit Case Study for the 8.9 MW
Huron Wind project
Hypothetical Cost-Benefit analysis of the Huron
Wind farm with Energy Storage on the Ontario
market
5
Huron Wind
  • First commercial wind farm in Ontario, developed
    in partnership between OPG and Canadian
    consortium
  • 5 x 1.8 MW (V80) turbines installed in Bruce
    County, Ontario in 2003
  • 44 kV, 35 km distribution feeder
  • All power locally consumed

Photo courtesy of Huron Wind
6
Huron Wind
  • Located in a capacity constrained area
  • Hydro One open issues
  • Is wind a solution or issue for voltage
    management?
  • Does project backfeed through TS and how does
    this affect loss savings?
  • Negative NPV for DG owner

Photo courtesy of Huron Wind
7
Huron WindCost-Benefit Case Study
  • NPV evaluated by Navigant Consulting Inc. with
    operation data from Huron Wind
  • Energy generation 25,215 MWh/yr
  • Major Costs
  • Equipment installation
  • Operation and Maintenance
  • LDC connection costs
  • Major Benefits
  • Wholesale Ontario electricity revenue ( 1.2
    million/yr at average HOEP of 4.8 /kWh)
  • WPPI (1.2 /kWh)

8
Huron Wind Cost-Benefit Case Study
  • 6.0 discount rate, 5.0 Interest rate, 2.0
    Inflation rate
  • 20 yr project life
  • Average HOEP 4.8 /kWh for 2007
  • 20 capacity factor for wind
  • 81.9/kW generation capacity value
  • 5.46/kW-yr voided transmission investment cost
  • 7 average transmission losses
  • 2500/ton NOX, 1300/ton SOX, 20/ton CO2
    (hypothetical)

As per Exhibit D of the OPAs IPSP Taken from
NCIs Avoided Cost Analysis for the Evaluation of
CDM Measures, prepared for Hydro One
9
Huron WindCost-Benefit Case Study
Cost/Benefit values shown in (000s)
Credit Navigant Consulting Inc.
10
Huron WindCost-Benefit Case Study
  • Negative NPV for DG owner
  • Overall positive net NPV for all stakeholders
  • Can adding energy storage improve the NPV for the
    DG owner?
  • Use the case study results as baseline for
    comparison against two hypothetical scenarios
    with energy storage
  • Evaluate NPV for scenarios with and without
    incentives on the Ontario market
  • Yield rough estimate of the potential value of
    adding storage

11
Huron WindEnergy Storage Scenarios
  • Scenario 1 Wholesale market plus premium
  • Generation sold on wholesale market
  • Add electricity storage to arbitrage energy to
    peak hours with higher wholesale market price
  • Include CESOP peak premium (8.10 /kWh) for
    generating at peak hours, in addition to
    wholesale price
  • Scenario 2 Flat rate plus premium
  • Wind generation sold at 11 /kWh RESOP rate
  • Add electricity storage to arbitrage energy to
    peak hours to receive 3.52 /kWh peak premium

12
Huron WindEnergy Storage Scenario 1
  • Storage sized to 10 of wind farm 900 kW
  • Storage increases Capacity factor to 30 from 20
  • In base case all energy sales (25,215 MWh/yr)
    sold at 4.80 /kWh average HOEP
  • With storage arbitrage 3 hours/day to peak hours
    sold at 9.60 /kWh HOEP
  • 30 capacity factor yields 2.7 MW firm capacity
  • 2.7 MW 3 hours/day 365 days 2,957 MWh/yr
  • Assume 500/kWh cost for 2.7 MWh electricity
    storage system (1,350,000 total)
  • Evaluate NPV with different energy storage costs
    and CESOP peak premium 8.10 /kWh

Calculated from OPA 2007 data
13
Huron WindEnergy Storage Scenario 1
  • Improved NPV for DG owner, storage provides
    positive benefit on the wholesale market without
    incentives or premiums!
  • LDC/Ratepayer benefits increase from avoided
    losses, generation capacity and transmission
    capacity due to 30 capacity factor (up from 20)
    from electricity storage
  • Shift some of the LDC/Ratepayer value to the DG
    owner through on-peak premium

14
Huron WindEnergy Storage Scenario 1
  • Assume a 8.10 /kWh peak premium (as per CESOP)
    in addition to peak wholesale price of 9.60 /kWh
  • Total price paid to DG owner is 17.70 /kWh
    during peak hours vs. 4.80 /kWh during off-peak
    hours leads to positive net NPV
  • Perform sensitivity analysis for different
    parameters in reference to the last analysis

15
Huron Wind Energy Storage Scenario 1
Sensitivity Analysis
16
Huron WindEnergy Storage Scenario 2
  • Storage size 900 kW, 8 hours, 7.2 MWh
  • Assume 500/kWh cost for 7.2 MWh electricity
    storage system (3,600,000 total)
  • RESOP incentive for wind generation
  • 11 /kWh, cannot be combined with HOEP
  • Peak premium of 3.52 /kWh for 8 hours/day (11 am
    to 7pm) in addition to 11 /kWh
  • Evaluate NPV with different energy storage costs
    and the RESOP incentive and premium

17
Huron Wind Energy Storage Scenario 2
  • First consider RESOP 11 /kWh flat rate without
    peak premium
  • RESOP incentive huge impact on DG owner and
    LDC/Ratepayer
  • LDC/Ratepayer bears the cost of the RESOP
    incentive, DG owner reaps the benefits

18
Huron Wind Energy Storage Scenario 2
  • Adding energy storage with a 3.52 cents/kWh peak
    premium does not show an overall benefit
  • 3.52 cents/kWh is not enough of a price
    difference between off-peak and on-peak to make
    economic case for storage
  • In addition, increased benefits to LDC/Ratepayers
    from improved capacity factor overridden by cost
    of peak premium

19
Huron Wind Energy Storage Scenario 2
  • Only a small increase in the peak premium needed
    to meet the same gains without storage (or slight
    decrease on storage cost)
  • Are the benefits of firming wind and the storage
    accruing to the LDC/Ratepayer and society well
    accounted for?
  • Perform sensitivity analysis for different
    parameters in reference to the analysis with 3.52
    cents/kWh incentive

20
Huron Wind Energy Storage Scenario 2
Sensitivity Analysis
DG owner loses significant RESOP rate revenue
from efficiency losses
21
Conclusion
  • Speculative analysis using existing project and
    incentive programs
  • Storage on the wholesale market does improve NPV
  • Need a large enough price difference between
    off-peak and on-peak electricity sale price to
    make storage valuable
  • With the right incentive tariff similar to those
    already in place energy storage can be cost
    effective
  • There is value for firm wind generation to
    society and the LDC/ratepayer in the long-term
    not captured
  • Need electricity storage cost figures to
    determine tariff for stand-alone electricity
    storage projects
Write a Comment
User Comments (0)