Title: ISPE Central Canada Chapter BAS Lifecycle Overview using GaMP
1ISPE Central Canada Chapter BAS Lifecycle
Overview using GaMP
- January 24, 2006 Toronto
- January 25, 2006 Montreal
- Irene Miess Sr Manager Regulated Industries
- Siemens Building Technologies
2BAS Lifecycle Overview using GaMP
- GaMP Model
- System Impact Assessment
- Direct Impact Systems
- Indirect Impact Systems
- Good Engineering Practice
- Commissioning
- Qualification Practices
- Installation and Operational Qualification
- Documentation Requirements
- Ongoing Operation
3Good Automated Manufacturing Practice (GaMP)
As a regulated site supplier, what guidance do we
have in delivering a validated and compliant
system?
Good Automated Manufacturing Practice (GaMP)
GaMP provides a method to relate development
activities to validation activities on automated
systems using a life cycle approach
4Good Automated Manufacturing Practice (GaMP)
- GaMP was created due to
- the increased use and complexity of automated
systems in FDA regulated manufacturing areas - the less mature interpretation of regulations in
automated applications than in more conventional,
non-automated areas
- A GaMP Industry Board establishes GaMP principles
and recommendations
5Project Lifecycle (GaMP)
Planning
Design Development
Ongoing Operation
Installation
Commissioning Qualification
FAT Required?
NO
YES
Factory Acceptance Testing
6Planning and Design/Development Phases
Master Validation Plan (MVP)
Planning Phase
User Requirement Specification (URS)
Impact Assessment
Quality System Program and Implementation Plan
Functional Specification
Hardware
Software
Engineering Submittal
Design Development Phase
Hardware
Software
Customer Approval of Functional and Design
Factory Acceptance Test (FAT) Phase
7Master Validation Plan
The Validation Master Plan (VMP) is the key
document in the overall validation process, and
is critical to the success of the project. It is
an important project document and a living
document that must be maintained throughout the
project life cycle. The validation master plan
typically defines
- Validation Strategy
- Validation Deliverables
- Acceptance Criteria
- Change Control Management
- Standard Operating Procedures
- Training
- Documentation Management
- Maintaining a Validated State
8Master Validation Plan
- BAS needs to be addressed
- Monitor Alarm only
- Direct Impact only
- If you want tomatoes, dont plant turnips!
9Planning and Design/Development Phases
Master Validation Plan (MVP)
Planning Phase
User Requirement Specification (URS)
Impact Assessment
Quality System Program and Implementation Plan
Functional Specification
Hardware
Software
Engineering Submittal
Design Development Phase
Hardware
Software
Customer Approval of Functional and Design
Factory Acceptance Test (FAT) Phase
10User Requirements
- The User Requirement Specification (URS)
specifies the requirements of the user for
individual aspects of the facility, equipment,
and systems in terms of function, throughput,
operability, and applicable standards - Defines what the user wants the system to do.
What functions will be carried out, the data on
which the system will operate, and the operating
environment. Non-functional requirements, such as
constraints (that is, time) and what deliverables
will be provided by the system (that is,
Training, Testing, Tools), are also documented - The User Requirement Specification (URS) and
Performance Testing are linked. The URS provides
the performance benchmark criteria upon which the
performance qualification (PQ) is based
11BAS User Requirement Spec
- Do you want
- to follow GaMP
- traceability matrix
- functional specs
- testing
- calibratable sensors
- commissioning documents
- remote notification
- horn/bell
- paging
12Planning and Design/Development Phases
Master Validation Plan (MVP)
Planning Phase
User Requirement Specification (URS)
Impact Assessment
Quality System Program and Implementation Plan
Functional Specification
Hardware
Software
Engineering Submittal
Design Development Phase
Hardware
Software
Customer Approval of Functional Design
Factory Acceptance Test (FAT) Phase
13Impact Assessment
- A process which allows a complex situation of
interdependent engineering systems and components
to be reviewed, understood and systematically
evaluated for their effect on product quality
(Commissioning vs. Qualification).
14Relationship Between Systems and Components
Components
Critical
Non-Critical
Direct Impact
Good Engineering Practices Qualification
Practices
Systems
?
Indirect/ No Impact
Good Engineering Practices Commissioning
15System Level Assessment
- System An organization of engineering
components which have defined operational
function (e.g., piping, instrumentation,
equipment, facilities, computer hardware,
computer software, etc.) - System Boundary A limit drawn around a system
to logically define what is and is not included
in the system.
16System Level Assessment
- Direct Impact System An engineering system that
is expected to have a direct impact on product
quality. - Indirect Impact System An engineering system
that is not expected to have a direct impact on
product quality, but is linked to a direct impact
system. - No Impact System An engineering system that is
not expected to have an impact on product quality.
17System Level Assessment
- System Impact Assessment The process of
evaluating the impact of the operating,
controlling, alarming and failure conditions of a
system on the quality of a product. - The quality of the product can be impacted by a
system or systems which meets any of the
following criteria - In contact with the product
- Used as an excipient
- Controls the process or
- Provides information relative to product
acceptance or rejection
18Component Level Assessment
- Critical Component A component within a system
where the operation, contact, data, control,
alarm or failure will have a direct impact on the
quality of the product. - Non-Critical Component A component within a
system where the operation, contact, data
control, alarm or failure will have an indirect
or no impact on the quality of the product.
19Relationship Between Systems and Components
Components
Critical
Non-Critical
Direct Impact
Good Engineering Practices Qualification
Practices
Systems
?
Indirect/ No Impact
Good Engineering Practices Commissioning
20BAS Draw Boundaries
- HVAC
- BAS only
- AHU controls
- zone controls
- monitor alarm
- Design system accordingly
- Separation by panels
- Separate GMP from non GMP
21Where are YOUR Boundaries
Sample PID of HVAC and BAS Equipment
22Planning and Design/Development Phases
Master Validation Plan (MVP)
Planning Phase
User Requirement Specification (URS)
Impact Assessment
Quality System Program and Implementation Plan
Functional Specification
Hardware
Software
Engineering Submittal
Design Development Phase
Hardware
Software
Customer Approval of Functional and Design
Factory Acceptance Test (FAT) Phase
23Quality System Program and Implementation Plan
- The Quality System Program and Implementation
Plan is a contractual document between the Client
and BAS supplier. - Defines actions, deliverables, responsibilities,
and procedures satisfying the user quality and
validation requirements.
24Planning and Design/Development Phases
Master Validation Plan (MVP)
Planning Phase
User Requirement Specification (URS)
Impact Assessment
Quality System Program and Implementation Plan
Functional Specification
Hardware
Software
Engineering Submittal
Design Development Phase
Hardware
Software
Customer Approval of Functional and Design
Factory Acceptance Test (FAT) Phase
25Functional Requirements Specification
- The Functional Requirements Specification (FRS)
describes the detailed functions of the facility,
equipment, and system (i.e., what the system will
do). - The Functional Specification is normally written
by the Supplier and then reviewed and approved
by the Customer. - The FRS is used to develop the Acceptance Test
Specification that outlines those items to be
tested as part of the Factory Acceptance Test
(FAT) and/or Site Assessment Test (SAT).
26Planning and Design/Development Phases
Master Validation Plan (MVP)
Planning Phase
User Requirement Specification (URS)
Impact Assessment
Quality System Program and Implementation Plan
Functional Specification
Hardware
Software
Engineering Submittal
Design Development Phase
Hardware
Software
Customer Approval of Functional and Design
Factory Acceptance Test (FAT) Phase
27Design Specification
- The Design Specification (DS) document developed
by Supplier describes how to build the facility,
equipment, and system (that is, how to design or
construct the system). - It is recommended that the Design Specification
is illustrated by the use of diagrams wherever
possible. - The Design Specification is normally written by
the Supplier and then reviewed and approved by
the Customer. - In most cases the DS may be included in the FS
28Planning and Design/Development Phases
Master Validation Plan (MVP)
Planning Phase
User Requirement Specification (URS)
Impact Assessment
Quality System Program and Implementation Plan
Functional Specification
Hardware
Software
Engineering Submittal
Design Development Phase
Hardware
Software
Customer Approval of Functional and Design
Factory Acceptance Test (FAT) Phase
29Project Lifecycle (GaMP)
Planning
Design Development
Ongoing Operation
Installation
Commissioning Qualification
FAT Required?
NO
YES
Factory Acceptance Testing
30Project Lifecycle (GaMP)
Planning
Design Development
Ongoing Operation
Installation
Commissioning Qualification
FAT Required?
NO
YES
Factory Acceptance Testing
31FAT and Installation Phases
Factory Acceptance Test (FAT) Required?
NO
Factory Acceptance Test (FAT) Phase
YES
BUILD SYSTEM
Factory Acceptance Test (FAT)
BUILD SYSTEM
Installation at Job Site
Develop IQ/OQ/PQ Tests
Installation Phase
Develop Commissioning Plan
Commissioning Qualification Phase
32FAT and Installation Phases
Factory Acceptance Test (FAT) Required?
NO
Factory Acceptance Test (FAT) Phase
YES
BUILD SYSTEM
Factory Acceptance Test (FAT)
BUILD SYSTEM
Installation at Job Site
Develop IQ/OQ/PQ Tests
Installation Phase
Develop Commissioning Plan
Commissioning Qualification Phase
33Factory Acceptance Test (FAT)
- A FAT is recommended when the project deadline is
critical and construction schedule does not allow
enough time for commissioning and validation
after installation. - Combining the commissioning findings with the FAT
as part of the validation process helps avoid
collecting data twice, making better use of time
and project resources. - Other tests used during the FAT and SAT may be
used to support the validation effort. - The request for the FAT occurs during the
planning stage of a project and usually is
included in the Validation Master Plan and the
Request for Quote (RFQ).
34Project Lifecycle (GaMP)
Planning
Design Development
Ongoing Operation
Installation
Commissioning Qualification
FAT Required?
NO
YES
Factory Acceptance Testing
35Commissioning/Qualification Phase Ongoing Ops
Start-up Commissioning
Site Acceptance Test (SAT)
Commissioning Qualification Phase
INDIRECT NO IMPACT SYSTEMS
DIRECT IMPACT SYSTEMS
Installation Qualification (IQ)
Trending to verify operational changes
Operational Qualification (OQ)
Performance Qualification (PQ)
Document Control
Change Control
Ongoing Operations
Training
Standard Operations (SOPs)
Business Continuity
Maintenance Operations
36Impact Assessment
GEP Only
No Impact
Parking Facilities
Office Terminal Devices
Office HVAC Systems
Chilled Water Systems
Indirect Impact?
cGMP HVAC Systems
Building Management System
cGMP Terminal Devices
Direct Impact
GEP and Qualification
37Commissioning Plan
38Commissioning
A well planned, documented and managed
engineering approach to the start-up and turnover
of facilities, systems and equipment to the
end-user that results in a safe and functional
environment that meets established design
requirements and stakeholders expectations.
39Commissioning
- Concepts
- Requires close cooperation of a multi-disciplined
team - Builds on concepts and activities such as Impact
Assessment and Good Engineering Practices - Execution typically occurs after the installation
of equipment, piping and instrumentation is
complete and operational - Systems, equipment and instrumentation need to be
physically complete and operational
40Commissioning Plan
- Agree on the Commissioning Plan early in the
project - Plan should identify systems to be commissioned,
activities and sequences, deliverables, personnel
and organizations involved and their
roles/responsibilities - Provide list of facilities, utilities and
equipment to be commissioned - Approvers should include Design, Construction and
the End-User representatives include Validation
and QA for direct impact systems - Commissioning should be integrated with
qualification activities for direct impact
systems - Commissioning may be the final activity prior to
use/operation by the end-user - Plan for either phased or one-time turnover
41Commissioning Process
- Levels of commissioning for building automation
systems - Standard Commissioning
- Enhanced Commissioning
- The level of commissioning is defined in the VMP
and Quality Plan. - Direct Impact systems require enhanced
documentation, which may involve additional
tests, documentation, QA change control, and QA
review/approval. Enhance documentation should
complement (not repeat) the documentation that is
created through GEP.
42Commissioning/Qualification Phase Ongoing Ops
Start-up Commissioning
Site Acceptance Test (SAT)
Commissioning Qualification Phase
INDIRECT NO IMPACT SYSTEMS
DIRECT IMPACT SYSTEMS
Installation Qualification (IQ)
Trending to verify operational changes
Operational Qualification (OQ)
Performance Qualification (PQ)
Document Control
Change Control
Ongoing Operations
Training
Standard Operations (SOPs)
Business Continuity
Maintenance Operations
43Site Acceptance Test
- Tests that are completed On-site with installed
equipment to prove the correct operation of the
software, hardware, and instrumentation as
defined by the URS
44Site Acceptance Test
- The Site Acceptance Test (SAT) is performed to
determine that the system and any associated
equipment has not been damaged and functions
correctly in its operating environment. - The SAT normally constitutes a repeat of the FAT
(or portions of the FAT) in the users
environment plus those test made possible with
all process, field instrumentation, interfaces,
and service connections established. - The SAT may be combined with equipment and plant
commissioning, and this will provide a basis for
the IQ and OQ. - The incorporation of SAT into qualification
testing is acceptable where the level of detail
and documentation of the tests meet the
requirement of user company policies and
procedures, and are acceptable to user company QA.
45Commissioning/Qualification Phase Ongoing Ops
Start-up Commissioning
Site Acceptance Test (SAT)
Commissioning Qualification Phase
INDIRECT NO IMPACT SYSTEMS
DIRECT IMPACT SYSTEMS
Installation Qualification (IQ)
Trending to verify operational changes
Operational Qualification (OQ)
Performance Qualification (PQ)
Document Control
Change Control
Ongoing Operations
Training
Standard Operations (SOPs)
Business Continuity
Maintenance Operations
46BAS Installation Qualification Table of Contents
- Documentation Verification
- SOP Verification
- Hardware and Software Verification
- Field Panel
- Hardware and Firmware Verification
- Utility Verification
- Application Code Version Verification
47Installation Qualification Table of Contents
- Database Configuration Verification
- Trend Configuration Verification
- Trend Collection Schedule Verification
- Alarm Configuration Verification
- Point Configuration Verification
- Alarm Management Configuration Verification
- Remote Notification Configuration Verification
- Alarm Paging Notification Verification
- Point List Verification
48Installation Qualification Table of Contents
- Archive Database Configuration Verification
- Data Base Verification
- Data Server Configuration Verification
- Archive Schedule Verification
- Data Purge Configuration Verification
- Summary Point Configuration Verification
- Uninterruptible Power Supply Installation
Verification - Field Device Calibration Verification
- Field Equipment Installation Verification
49Commissioning/Qualification Phase Ongoing Ops
Start-up Commissioning
Site Acceptance Test (SAT)
Commissioning Qualification Phase
INDIRECT NO IMPACT SYSTEMS
DIRECT IMPACT SYSTEMS
Installation Qualification (IQ)
Trending to verify operational changes
Operational Qualification (OQ)
Performance Qualification (PQ)
Document Control
Change Control
Ongoing Operations
Training
Standard Operations (SOPs)
Business Continuity
Maintenance Operations
50Operational Qualification Table of Contents
- System Security Qualification Test Cases
- User Account Security
- Access Groups
- Audit Trail Qualification Test Cases
- Audit Trail Verification
- Long Term Storage of Audit Trails
- Field Panel Qualification Test Cases
- Field Panel Loss of Communication
- Field Panel Battery Check
- Field Panel Power Failure Alarming and Recovery
- Electric Field Instrument (EFI) Interference
51Operational Qualification Table of Contents
- Uninterrupted Power Supply
- Custom Code Testing
- Scheduled Functions Qualification Test Cases
- Trend Collection Report Verification
- Data Server Verification
- Archive Schedule Verification
- System Alarms Qualification Test Cases
- Standard Alarm Notification Test
- Enhanced Alarms Notification Test
52Operational Qualification Table of Contents
- Remote Notification Qualification Test Cases
- Building Level Network Event
- Escalation Test
- Alarm Management Qualification Test Cases
- Alarm Management Operational Test Case
- Alarm Management Archival Test Case
- Data Integrity Qualification Test Cases
- Transmitter Failure Test
- 72 Hour Trend Analysis
53Commissioning/Qualification Phase Ongoing Ops
Start-up Commissioning
Site Acceptance Test (SAT)
Commissioning Qualification Phase
INDIRECT NO IMPACT SYSTEMS
DIRECT IMPACT SYSTEMS
Installation Qualification (IQ)
Trending to verify operational changes
Operational Qualification (OQ)
Performance Qualification (PQ)
Document Control
Change Control
Ongoing Operations
Training
Standard Operations (SOPs)
Business Continuity
Maintenance Operations
54Standard Operating Procedures (SOPs)
- System Operation
- Change Control/ Upgrade Procedures
- Hardware Maintenance Procedures
- Software Maintenance Procedures
- Electronic Records/Data Management Procedures
- Incident Management Procedures
- System Security Procedures
- Training Procedures
- Disaster Recovery Procedures
- Source Code Handling
55The V-ModelA Basic Framework for Specification,
Design and Testing
User Requirements Specification
56IQ/OQ
57Questions??
- If you want tomatoes
-
- Dont plant turnips!
58(No Transcript)