Lecture 4 Investment Appraisal III: Risk analysis

1 / 25
About This Presentation
Title:

Lecture 4 Investment Appraisal III: Risk analysis

Description:

Lecture 4 Investment Appraisal III: Risk analysis Objectives: Discuss the relationship between risk and return Evaluate investment projects in the conditions of ... – PowerPoint PPT presentation

Number of Views:26
Avg rating:3.0/5.0
Slides: 26
Provided by: BOA84

less

Transcript and Presenter's Notes

Title: Lecture 4 Investment Appraisal III: Risk analysis


1
Lecture 4 Investment Appraisal III Risk
analysis
  • Objectives
  • Discuss the relationship between risk and return
  • Evaluate investment projects in the conditions of
    uncertainty
  • Discuss the techniques used to evaluate
    investment projects under conditions of
    uncertainty
  • Discuss risk analysis in practice

2
Risk in Investment Appraisal
  • Risk refers to a situation where the future is
    unclear and there is more than one possible
    outcomes.

3
Techniques for dealing with Risk
  • The techniques for dealing with risk include
  • a) the expected NPV rule
  • b) the risk-adjusted discount rate approach
  • c) sensitivity analysis
  • d) Simulation

4
Expected Net Present Value
  • The expected NPV rule (ENPV)
  • EV of a project is the mean value which will be
    obtained if the project was repeated many times
    over
  • EV is not the most likely value of the project.
  • It is only the weighted average of all the
    possible outcomes
  • EV is calculated by multiplying the each possible
    outcome by its probability of occurrence and then
    add them up

5
Example 4.1
  • Shorten Ltd needs to purchase a machine to
    manufacture a new product. The choice lies
    between two machines (A and B). Each machine has
    an estimated life of three years with no scrap
    value.
  • Machine A will cost 30,000 and machine B will
    cost 40,000, payable immediately in each case.
    The total variable cost of manufacture of each
    unit are 2 if made on machine A, but only 1.00
    if made on machine B. This is because machine B
    is more sophisticated and requires less labour to
    operate it.
  • The product will sell for 8 each.
  • The demand for the product is uncertain but is
    estimated at 2,000 units for each year, 3,000
    units for each year or 5,000 units for each year.
    (Note that whatever sales level actually occurs,
    that level will apply to each year.)
  • The sales manager has placed probabilities on the
    level of demand as follows

6
Shorten Ltd Example 4.1
  • Annual demand Probability of occurrence
  • 2000 0.2
  • 3000 0.6
  • 5000 0.2
  • Presume that both taxation and fixed costs will
    be unaffected by any decision made.
  • Shorten Ltds cost of capital is 6 p.a.
  • Calculate the NPV for each of the three activity
    levels for each machine A and B and state your
    conclusion.
  • Calculate the expected NPV for each machine and
    state your conclusion.

7
Shorten Ltd Example 4.1
  • Machine A
  • 2000 3000
    5000
  • Demand Demand
    Demand


  • Year 0 (30,000)
    (30,000) (30,000)
  • 1 (8-2)/unit
    12,000 18,000 30,000
  • 2 12,000
    18,000 30,000
  • 3
    12,000 18,000 30,000
  • Discounted Factor


  • Year0 (1.00) (30,000)
    (30,000) (30,000)
  • 1 (0.94) 11,280
    16,920
    28,200 2
    (0.89)
    10,680 16,020
    26,700
  • 3 (0.84)
    10,080 15,120
    25,200

  • 2,040 18,060
    50,100
  • Expected value
  • (0.2 x 2,040) (0.6 x 18,060) (0.2 x 50,100)
  • 21,264

8
Solution 4.1
  • Different cash flows of Machine B
  • 2000 3000 5000
  • demand demand demand

  • Year 0 40,000 40,000 40,000
  • 1(8-1)/unit 14,000 21,000 35,000
  • 2 14,000 21,000 35,000
  • 3 14,000 21,000 35,000

9
Solution 4.1
  • 2000 3000 5000
  • Discounted Factor  
  • Year0 (1.00) (40,000) (40,000)
    (40,000) 
  • 1 (0.94) 13,160 19,740 32,900 
  • 2 (0.89) 12,460 18,690 31,150 
  • 3 (0.84) 11,760 17,640
    29,400 
  • (2,620) 16,070
    53,450
  • Expected value
  • (0.2 x 2,620) (0.6 x 16,070) (0.2 x
    53,450)
  • 19,808

10
The Risk Adjusted Discount Rate
  • This approach to investment decision making
    process is an attempt to deal with risk in a
    manner that takes account of the attitudes of the
    decision maker.

11
The Risk Adjusted Discount Rate
  • Example 4.2
  • Before any investments are considered, the
    decision maker should begin by determining an
    appropriate discount rate for risk-free
    investments.
  • Suppose that the rate on such bonds issued by the
    government is currently 7. This figure should be
    used as the base from which discount rates are
    calculated for risky investments.

12
The Risk Adjusted Discount Rate
  • Class of Risk Example of Risk Premium
    Discount rate
  • type of project
  • Very low Buying a bond 1 8
  • Low Improvement in
  • Existing factory 3 10
  • Medium Increased in existing
  • Output 5 12
  • High Launch a new product 8 15
  • Very high Research on areas
  • Related to current activity
    11 18
  • The use of risk-adjusted discount rate approach
    to investment appraisal is indeed, a common sense
    approach. However, it is subjective,
    particularly, the choice of the risk premiums and
    the assignment of projects to particular risk
    classes is based on personal judgement.

13
Sensitivity Analysis
  • Sensitivity analysis
  • is a procedure that calculates the changes in the
    net present value given a change in one of the
    cash flow elements such as product price.
  • With sensitivity analysis each of the figures
    used in the NPV is examined in turn, to determine
    how variations from the estimated figures impact
    on the NPV

14
Sensitivity Analysis
  • Sensitivity analysis helps managers to gain
    better understanding of the nature and degree of
    risk associated with a project
  • because it reveals the margin of safety
    associated with each key variable relating to a
    particular project.
  • It is a form of break even analysis. The point at
    which NPV is equal to zero is the break-even
    point.

15
Sensitivity Analysis
  • Identifying the key or critical variable i.e.
    those
  • with short margin of safety.

16
Sensitivity analysis
  • Example 4.3
  • Swift Ltd, which has a cost of capital of 12 per
    cent, is considering the investment of 7m in an
    improved moulding machine project with a life of
    four years. The garden ornaments produced will
    retail at 9.20 each and cost 6 each to make. It
    is expected that 800,000 ornaments will be sold
    each year. What are the key variables for the
    project?

17
Solution 4.3
  • NPV of the project can be expressed in terms of
    the project variables as follows
  • NPV ( (S -VC) X CPVF??.?) I0
  • Where S Selling price per unit
  • VC Variable cost per unit
  • N No of units sold per year
  • I0 initial investment
  • CPVF??.? Cumulative present value factor for
    four years at 12

18
Sensitivity analysis
  • Inserting the information given in the question
    and finding the cumulative PV factor from annuity
    table, we have
  • (9.20 - 6.00) X800,000X 3.037)-7,000,000 0

19
Sensitivity analysis
  • a) Initial investment. Find the value of I0 that
    makes the NPV zero
  • I0 (9.20 -6.00) x 800,000 x 3.037)
    7,774,720
  • This is an increase of 774,720 or 11.1 per cent
    on the planned initial investment

20
Sensitivity analysis
  • b) Sales price
  • S 6.00 (7,000,000 / (800,000 x 3.037) )
    8.88
  • This is a decrease of 32 pence or 3.5 per cent
    of planned sales price.
  • Variable cost
  • As a decrease of 32 pence in sales price makes
    the NPV zero, an increase of 32 pence or 5.3 per
    cent in variable cost will have the same effect.

21
Exercise 4.1
  1. Try to calculate the 32 pence or 5.3 by using
    the general equation above

22
Sensitivity analysis
  • d). Sales volume
  • N 700,000 / (9.20 - 6.00) x 3.037) 720,283
  • This is a decrease of 79,717 units or 10 per cent
    on the planned sales volume.

23
e) Discount rate
  • CPVF 7,000,000 / (9.20 6.00) X 800,000)
    2.734
  • Using the annuity tables 2.743 corresponds to the
    discount rate of almost exactly 17 per cent. An
    increase of 5 per cent in absolute terms or 42
    per cent on the current project discount rate.

24
Sensitivity analysis- summary
  • Sensitivity analysis of the proposed investment
    by Swift Ltd
  • Variable Original est. B/E point
    Difference Dif. as Sensitivity
  • Sales Volume 800,000 720,283
    (79,717) 10 Low
  • Sales price 9.20 8.88
    (0.32) 3.5 High
  • Variable cost 6.00 6.32
    0.32. 5.3 High
  • Discount rate 12 17 5
    42 Very Low
  • Initial Inv 7,000,000 7,774,720
    774,720 11.1 Low

25
Advantages and Disadvantages
  • Advantages
  • Useful in directing the attention of managers to
    the most sensitive variables of the project
  • Disadvantages
  • Does not formally quantify risk
  • Does not clearly provide any clear-cut decision
    rule
Write a Comment
User Comments (0)