Title: Reservas: Impacto de los
1Reservas Impacto de los últimos cambios en las
definiciones
- Herman G. Acuña
- Managing International V.P.
- Ryder Scott Company
- (Herman_Acuna_at_RyderScott.com)
2Agenda
- Introductory Comments
- 2007 SPE/WPC/AAPG/SPEE PRMS
- 2009 SEC Rules Modernization
- Side-by-Side Comparison of SPE and SEC Definitions
3The Definitions
2009 SECs Modernization Of Oil and Gas
Reporting
2007 SPE PRMS
4WHY IS A RESERVES DEFINITION NEEDED?
- Most of the parameters that define the reserves
of a Reservoir cannot be measured directly, and
must be determined indirectly through geologic
and reservoir engineering analysis and
interpretations. - As a result, the estimates of oil and gas
reserves have an intrinsic uncertainty. - The Definitions of reserves are designed to
promote uniformity and a standard measurement of
the assets, providing a structure to quantify
risk and uncertainty through its categorization.
5Audiences
- Tolerance to Uncertainty
- Access to upside
- Exposure to downside
- Economic indicators
6- The term reserves is generally applied to the
discovered quantities of petroleum anticipated to
be commercially recoverable from known
accumulations from a given date forward under
defined conditions. - The term resources is generally applied to all
quantities of petroleum (recoverable and
unrecoverable) naturally occurring on or within
the Earths crust, discovered and undiscovered,
plus those quantities already produced.
Ref. Sections 2.1.1, 2.1.2 2.1.3 PRMS
7(No Transcript)
8Project Maturity Sub-Classes Play
- Project associated with prospective trend
- Requires additional data acquisition and/or
evaluation - Activities focused on identifying leads or
prospects for more detailed analysis - Chance of discovery, range of potential recovery
under hypothetical development scenarios
Let's keep looking!
9Project Maturity Sub-Classes Lead
- Poorly defined potential accumulation
- Requires more data acquisition or evaluation
- Activities include further analysis to confirm
whether or not the lead can be mature into a
prospect - Chance of discovery, range of potential recovery
under feasible development scenarios
Is that a target?
10Project Maturity Sub-Classes Prospect
- Potential accumulation sufficiently defined as a
viable drilling target - Project focus on assessing chance of discovery
- Evaluating range of potential recoverable
quantities under commercial program
Move the Rig Boys!
11Project Maturity Sub-Classes Development Not
Viable
- Discovery with limited production potential
- No current plans to appraise
- Project not seen as having commercial potential
for eventual development - Keep theoretical recoverable quantities in the
event of major technology or commercial
conditions - Project decision gate not to undertake any
further actions for the foreseeable future
Wish had not spent that money!
12Company Prospector after receiving Development
not Viable status on pet project
At least I kept the dog!
13Project Maturity Sub-Classes Development
Unclarified or on Hold
- Discovery with activities on hold and commercial
development may be significantly delayed - Project seen as having eventual commercial
development potential - Pending removal of significant contingencies
- Substantial further appraisal is necessary to
clarify potential - Project decision gate proceed or suspend
appraisal with temporarily suspension outcome
Tempting, let's wait spend somewhere else.
?
?
14Project Maturity Sub-Classes Development Pending
- Discovery with enough hydrocarbons to justify
ongoing activities to confirm commercial
development in the foreseeable future - Reasonable potential for development subject to
confirmation with ongoing data acquisition and
investigations - Critical contingencies identified and reasonable
expectations to resolve them - Disappointing appraisal may lead to downgrading
to On-hold or Not Viable - Project decision gate is decision to move forward
with appraisal and confirmation
Actively Appraising
15Project Maturity Sub-Classes Justified for
Development
- Projects justified economically based on
reasonable commercial forecast - Reasonable expectation that all approvals will be
obtained - Development plan with sufficient detail to
support claim of commerciality - Reasonable expectations to obtain regulatory
approvals and sales contracts - Project decision gate is notification of project
maturity to proceed with development at that
point in time
Will Spend Money
16- Company prospector after receiving Justified for
Development status on pet project.
I knew it all along, those were reserves not
resources!
17Project Maturity Sub-Classes Approved for
Development
- All approvals obtained, capital funds committed
project is underway - Certainty that project is going forward
- No outstanding approvals or sales contracts
- Committed budget should be part of the approved
budget - Project decision gate is to start investments and
construction
Spending Money
18Project Maturity Sub-Classes On Production
- Project is on production and selling hydrocarbons
- Receiving income versus simply a completed
project - Project chance of commerciality is 100
- Project decision gate is the decision to initiate
commercial production
Making Money
19Securities and Exchange Commission (SEC)Reserves
Definitions
20SEC Mission and Objectives
- SEC administers federal securities laws and issue
rules and regulations to provide protection for
investors and ensure the securities markets are
fair and honest. - Its main objective is to protect shareholders by
providing a homogeneous base for comparison among
the various Companies. - SEC promotes the full and effective disclosure to
the investing public. - SEC does not conduct merit review does not
guarantee the value or merit of an investment. - SEC cannot prohibit the sale of securities of
questionable value. The investor must make the
ultimate judgment of the worth of any securities
offered for sale.
212009 SEC Reserves Definitions Modernization
- Now covers Proved, Probable and Possible
Reserves, previously only Proved Reserves - Use of 12 month average price for the first day
of each month versus fiscal year end price - Allows booking of non-conventional hydrocarbons
- Ability to use new technology if reliable and
repeatable. - Certainty criteria for PUDs now use reasonable
certainty criteria. - Analogous reservoir properties must be in the
aggregate be no more favorable than the reservoir
of interest. - Allows for Deterministic and Probabilistic
methods - It does not reflect the global position of the
Company in the area of Resources
22- Side By Side Comparison of
- U.S. SEC vs. SPE-PRMS
- Reserves Definitions
23Classify by Chance of Commerciality
Categorize estimates based on Uncertainty of
sales volumes
24Definition of Reserves
- SEC 210.4-10(a)(26)
- Reserves are estimated remaining quantities of
oil and gas and related substances anticipated to
be economically producible, as of a given date,
by application of development projects to known
accumulations. In addition, there must exist, or
there must be a reasonable expectation that there
will exist, the legal right to produce or a
revenue interest in the production, installed
means of delivering oil and gas or related
substances to market, and all permits and
financing required to implement the project.
SPE-PRMS Appendix A Reserves are those
quantities of petroleum anticipated to be
commercially recoverable by application of
development projects to known accumulations from
a given date forward under defined conditions.
Reserves must further satisfy four criteria They
must be discovered, recoverable, commercial, and
remaining (as of a given date) based on the
development project(s) applied.
25Economically Producible vs. Commercially
Recoverable
SPE-PRMS 3.1, 3.1.1 Commercial Evaluations Resou
rces evaluations are based on estimates of future
production and the associated cash flow schedules
for each development project. While each
organization may define specific investment
criteria, a project is generally considered to be
economic if its best estimate case has a
positive net present value under the
organizations standard discount rate, or if at
least has a positive undiscounted cash flow.
- SEC 210.4-10(a)(10)
- The term economically producible, as it relates
to a resource, means a resource which generates
revenue that exceeds, or is reasonably expected
to exceed, the costs of the operation. The value
of the products that generate revenue shall be
determined at the terminal point of oil and gas
producing activities as defined in paragraph
(a)(16) of this section.
26Existing Economic Conditions vs. Defined Economic
Conditions
- SEC 210.4-10(a)(22)(v)
- Existing economic conditions include prices and
costs at which economic producibility from a
reservoir is to be determined. The price shall be
the average price during the 12-month period
prior to the ending date of the period covered by
the report, determined as an unweighted
arithmetic average of the first-day-of-the-month
price for each month within such period, unless
prices are defined by contractual arrangements,
excluding escalations based upon future
conditions.
SPE-PRMS 3.1.2 The economic evaluation
underlying the investment decision is based on
the entitys reasonable forecast of future
conditions, including costs and prices, which
will exist during the life of the project
(forecast case). Such forecasts are based on
projected changes to current conditions SPE
defines current conditions as the average of
those existing during the previous 12 months.
Alternative economic scenarios are considered in
the decision process and, in some cases, to
supplement reporting requirements. Evaluators may
examine a case in which current conditions are
held constant (no inflation or deflation)
throughout the project life (constant case).
27Definition of Proved Reserves
- SEC 210.4-10(a)(22)
- Proved oil and gas reserves are those quantities
of oil and gas, which, by analysis of geoscience
and engineering data, can be estimated with
reasonable certainty to be economically
produciblefrom a given date forward, from known
reservoirs, and under existing economic
conditions, operating methods, and government
regulationsprior to the time at which contracts
providing the right to operate expire, unless
evidence indicates that renewal is reasonably
certain, regardless of whether deterministic or
probabilistic methods are used for the
estimation. The project to extract the
hydrocarbons must have commenced or the operator
must be reasonably certain that it will commence
the project within a reasonable time.
SPE-PRMS Appendix A Proved Reserves are those
quantities of petroleum, which by analysis of
geoscience and engineering data, can be estimated
with reasonable certainty to be commercially
recoverable, from a given date forward, from
known reservoirs and under defined economic
conditions, operating methods, and government
regulations.
28Reasonable Certainty For Proved Reserves
- SEC 210.4-10(a)(22)
- If deterministic methods are used, reasonable
certainty means a high degree of confidence that
the quantities will be recovered. If
probabilistic methods are used, there should be
at least a 90 probability that the quantities
actually recovered will equal or exceed the
estimate. A high degree of confidence exists if
the quantity is much more likely to be achieved
than not, and, as changes due to increased
availability of geoscience (geological,
geophysical, and geochemical), engineering, and
economic data are made to estimated ultimate
recovery (EUR) with time, reasonably certain EUR
is much more likely to increase or remain
constant than to decrease.
SPE-PRMS Appendix A If deterministic methods are
used, the term reasonable certainty is intended
to express a high degree of confidence that the
quantities will be recovered. If probabilistic
methods are used, there should be at least a 90
probability that the quantities actually
recovered will equal or exceed the
estimate.
29Discounted Future Net Revenue or Net Present Value
- FASB Topic 932
- This amount shall be derived from using a
discount rate of 10 percent a year to reflect the
timing of the future net cash flows relating to
proved oil and gas reserves.
SPE-PRMS 3.1.1 When the cash flows are
discounted according to a defined discount rate
and time period, the summation of the discounted
cash flows is termed net present value (NPV) of
the project. The calculation shall reflect The
application of an appropriate discount rate that
reasonably reflects the weighted average cost of
capital or the minimum acceptable rate of return
applicable to the entity at the time of the
evaluation.
30Proved Reserves and Expiration of Existing
Contracts
- SEC 210.4-10(a)(22)
- prior to the time at which contracts providing
the right to operate expire, unless evidence
indicates that renewal is reasonably certain
SPE-PRMS 3.1.1 3.3.3 The calculation shall
reflect A project life that is limited to the
period of entitlement or reasonable expectation
thereof. Reserves should not be claimed for
those volumes that will be produced beyond the
ending date of the current agreement unless there
is reasonable expectation that an extension, a
renewal, or a new contract will be granted. Such
reasonable expectation may be based on the
historical treatment of similar agreements by the
license-issuing jurisdiction. Otherwise, forecast
production beyond the contract term should be
classified as Contingent Resources with an
associated reduced chance of commercialization.
31Reserves and Constraints for Project Financing
- SEC 210.4-10(a)(26)
- Reserves are estimated remaining quantities of
oil and gas and related substances anticipated to
be economically producible, as of a given date,
by application of development projects to known
accumulations. In addition, there must exist, or
there must be a reasonable expectation that there
will exist, the legal right to produce or a
revenue interest in the production, installed
means of delivering oil and gas or related
substances to market, and all permits and
financing required to implement the project. - Authors Note This applies to SEC Reserves of
any category.
SPE-PRMS 3.1.2 While SPE guidelines do not
require that project financing be confirmed prior
to classifying projects as Reserves, this may be
another external requirement. In many cases,
loans are conditional upon the same criteria as
above that is, the project must be economic
based on Proved Reserves only. In general, if
there is not a reasonable expectation that loans
or other forms of financing (e.g., farm-outs) can
be arranged such that the development will be
initiated within a reasonable timeframe, then the
project should be classified as Contingent
Resources. If financing is reasonably expected
but not yet confirmed, the project may be
classified as Reserves, but no Proved Reserves
may be reported as above. SPE-PRMS 3.1.2
Reasonable Expectation Indicates a high degree
of confidence (low risk of failure) that the
project will proceed with commercial development
or the referenced event will occur.
32Proved Reserves and Constraints for Project Timing
- SEC 210.4-10(a)(22) Proved Reserves
- The project to extract the hydrocarbons must
have commenced or the operator must be reasonably
certain that it will commence the project within
a reasonable time. - SEC 210.4-10(a)(31)(ii) Undeveloped Reserves
- Undrilled locations can be classified as having
undeveloped reserves only if a development plan
has been adopted indicating that they are
scheduled to be drilled within five years, unless
the specific circumstances, justify a longer
time. - Authors Note The SEC regulations do not define
what constitutes acceptable instances of
specific circumstances that justify a longer
time. Guidance, however, is provided in the SEC
26 October 2009 Website Release Compliance and
Disclosure Interpretations Oil and Gas Rules.
SPE-PRMS Table 1 Appendix A Commercial There
must be a reasonable expectation that all
required internal and external approvals will be
forthcoming, and there is evidence of firm
intention to proceed with development within a
reasonable time frame. In addition, a project is
commercial if the degree of commitment is such
that the accumulation is expected to be developed
and placed on production within a reasonable time
frame. While 5 years is recommended as a
benchmark, a longer time frame could be applied
where, for example, development of economic
projects are deferred at the option of the
producer for, among other things, market-related
reasons, or to meet contractual or strategic
objectives. In all cases, the justification for
classification as Reserves should be clearly
documented.
33Proved Reserves and Constraints for Project Timing
- SEC 210.4-10(a)(22) Proved Reserves
- The project to extract the hydrocarbons must
have commenced or the operator must be reasonably
certain that it will commence the project within
a reasonable time. - SEC 210.4-10(a)(31)(ii) Undeveloped Reserves
- Undrilled locations can be classified as having
undeveloped reserves only if a development plan
has been adopted indicating that they are
scheduled to be drilled within five years, unless
the specific circumstances, justify a longer
time. - Authors Note The SEC regulations do not define
what constitutes acceptable instances of
specific circumstances that justify a longer
time. Guidance, however, is provided in the SEC
26 October 2009 Website Release Compliance and
Disclosure Interpretations Oil and Gas Rules.
SPE-PRMS Table 1 Appendix A Commercial There
must be a reasonable expectation that all
required internal and external approvals will be
forthcoming, and there is evidence of firm
intention to proceed with development within a
reasonable time frame. In addition, a project is
commercial if the degree of commitment is such
that the accumulation is expected to be developed
and placed on production within a reasonable time
frame. While 5 years is recommended as a
benchmark, a longer time frame could be applied
where, for example, development of economic
projects are deferred at the option of the
producer for, among other things, market-related
reasons, or to meet contractual or strategic
objectives. In all cases, the justification for
classification as Reserves should be clearly
documented.
Oh, my! 5 years nobody told me.
34Definition of Proved Area
- SEC 210.4-10(a)(22)(i)Proved Reserves
- The area of the reservoir considered as proved
includes - (A) The area identified by drilling and limited
by fluid contacts, if any, and - (B) Adjacent undrilled portions of the reservoir
that can, with reasonable certainty, be judged to
be continuous with it and to contain economically
producible oil or gas on the basis of available
geoscience and engineering data.
- SPE-PRMS Table 3 Proved Reserves
- The area of the reservoir considered as Proved
includes - the area delineated by drilling and defined by
fluid contacts, if any, and - (2) adjacent undrilled portions of the reservoir
that can reasonably be judged as continuous with
it and commercially productive on the basis of
available geoscience and engineering data.
35Proved Area In the Absence of Established Fluid
Contacts
- SEC 210.4-10(a)(22) Proved Reserves
- (ii) In the absence of data on fluid contacts,
proved quantities in a reservoir are limited by
the lowest known hydrocarbons (LKH) as seen in a
well penetration unless geoscience, engineering,
or performance data and reliable technology
establishes a lower contact with reasonable
certainty. - (iii) Where direct observation from well
penetrations has defined a highest known oil
(HKO) elevation and the potential exists for an
associated gas cap, proved oil reserves may be
assigned in the structurally higher portions of
the reservoir only if geoscience, engineering, or
performance data and reliable technology
establish the higher contact with reasonable
certainty.
SPE-PRMS Table 3 Proved Reserves In the absence
of data on fluid contacts, Proved quantities in a
reservoir are limited by the lowest known
hydrocarbon (LKH) as seen in a well penetration
unless otherwise indicated by definitive
geoscience, engineering, or performance
data.
36Proved Area In the Absence of Established Fluid
Contacts
- SEC 210.4-10(a)(25) Reliable Technology
- Reliable technology is a grouping of one or more
technologies (including computational methods)
that has been field tested and has been
demonstrated to provide reasonably certain
results with consistency and repeatability in the
formation being evaluated or in an analogous
formation.
SPE-PRMS Table 3 Proved Reserves In the absence
of data on fluid contacts, Proved quantities in a
reservoir are limited by the lowest known
hydrocarbon (LKH) as seen in a well penetration
unless otherwise indicated by definitive
geoscience, engineering, or performance data.
Such definitive information may include pressure
gradient analysis and seismic indicators.
Seismic data alone may not be sufficient to
define fluid contacts for Proved reserves (see
2001 Supplemental Guidelines, Chapter 8).
37Definition of Undeveloped Reserves
- SEC 210.4-10(a)(31)
- Undeveloped oil and gas reserves are reserves of
any category that are expected to be recovered
from new wells on undrilled acreage, or from
existing wells where a relatively major
expenditure is required for recompletion. - (i) Reserves on undrilled acreage shall be
limited to those directly offsetting development
spacing areas that are reasonably certain of
production when drilled, unless evidence using
reliable technology exists that establishes
reasonable certainty of economic producibility at
greater distances. - (ii) Undrilled locations can be classified as
having undeveloped reserves only if a development
plan has been adopted indicating that they are
scheduled to be drilled within five years, unless
the specific circumstances, justify a longer
time. - (iii) Under no circumstances shall estimates for
undeveloped reserves be attributable to any
acreage for which an application of fluid
injection or other improved recovery technique is
contemplated, unless such techniques have been
proved effective by actual projects in the same
reservoir or an analogous reservoir, as defined
in paragraph (a)(2) of this section, or by other
evidence using reliable technology establishing
reasonable certainty.
SPE-PRMS Table 2 Appendix A Undeveloped
Reserves are quantities expected to be recovered
through future investments (1) from new wells on
undrilled acreage in known accumulations, (2)
from deepening existing wells to a different (but
known) reservoir, (3) from infill wells that will
increase recovery, or (4) where a relatively
large expenditure (e.g., when compared to the
cost of drilling a new well) is required to (a)
recomplete an existing well or (b) install
production or transportation facilities for
primary or improved recovery projects. SPE-PRMS
Table 3 Proved Reserves Reserves in undeveloped
locations may be classified as Proved provided
that The locations are in undrilled areas of
the reservoir that can be judged with reasonable
certainty to be commercially productive. Interpre
tations of available geoscience and engineering
data indicate with reasonable certainty that the
objective formation is laterally continuous with
drilled Proved locations.
38Definition of Proved Reserves for Improved
Recovery
SPE-PRMS 2.3.4 Improved Recovery The judgment
on commerciality is based on pilot testing within
the subject reservoir or by comparison to a
reservoir with analogous rock and fluid
properties and where a similar established
improved recovery project has been successfully
applied. Incremental recoveries through improved
recovery methods that have yet to be established
through routine, commercially successful
applications are included as Reserves only after
a favorable production response from the subject
reservoir from either (a) a representative pilot
or (b) an installed program, where the response
provides support for the analysis on which the
project is based.
- SEC 210.4-10(a)(25) Proved Reserves
- (A) Successful testing by a pilot project in an
area of the reservoir with properties no more
favorable than in the reservoir as a whole, the
operation of an installed program in the
reservoir or an analogous reservoir, or other
evidence using reliable technology establishes
the reasonable certainty of the engineering
analysis on which the project or program was
based and - (B) The project has been approved for development
by all necessary parties and entities, including
governmental entities.
39Conclusions
- Reserves definition provide a framework to
classify reserves according to the uncertainty
level in the evaluation. - The SPE and SEC definitions are more similar than
you think. - The SPE and SEC definitions are more different
than you think. - The perception of the consequences of
non-compliance may affect how we perceive the
different guidelines.
40Questions?
Herman G. Acuña Managing International V.P. Ryder
Scott Company (Herman_Acuna_at_RyderScott.com)