Title: Bonded Concrete Overlay (BCO) Training Module
1Bonded Concrete Overlay (BCO) Training Module
- TxDOT Research Project 0-4893
- Performance of Old Concrete Under Thin Overlays
-
- Center for Transportation Research
- The University of Texas at Austin
1
2Acknowledgement
- PC Charles Gaskin, P.E. (HOU)
- PD German Claros, Ph.D., P.E. (RTI)
- PA Joe Leidy, P.E. (CSTMP)
- Darlene Goehl, P.E. (BRY)
- Hua Chen, P.E. (CSTMP)
-
2
3Training Module Contents
- BCO Design Module
- BCO Construction Module
- BCO in Texas Lessons Learned
3
4Scope
- Primarily, continuously reinforced concrete
pavement (CRCP) overlay on CRCP - CRCP overlay on JCP is not fully covered.
4
5Bonded Concrete Overlay- Overview -
- Consists of concrete layer (2 to 8 inches) on top
of an existing concrete surface. - One of the most cost-effective way of enhancing
structural capacity of under-designed pavements - Specific steps are taken to bond the new concrete
overlay to the existing concrete. - Increases structural capacity of the pavement
system by reducing deflections.
5
66
77
8Bonded Concrete Overlay (BCO) Design
- Currently, the AASHTO 1993 Guide is the most
widely used design method for bonded overlay.
8
9AASHTO DESIGNRevisions in the 93 Guide
- Overlay Design was Completely Revised
- New Procedure consists of 7 Overlay Design
Procedures - Uses the Concept of Structural Deficiency
- Used for Structural Overlay Design
9
10Structural Deficiency Approach to Overlay Design
Original Capacity
Structural Capacity
Loads
10
11Pavement Evaluation for Overlay Design
- Functional Evaluation of Existing Pavement
- Surface Friction Problems/Polishing
- Use Diamond Grinding or Grooving to Restore Skid
Resistance - Surface Roughness
- Use CPR and Diamond Grinding.
11
12Overlay Type Feasibility
- Availability of Adequate Funds
- Construction Feasibility
- Traffic Control
- Materials and Equipment
- Climatic Conditions
- Construction Problems (noise, pollution,
subsurface utilities, overhead clearance) - Traffic Disruptions and User Delay Costs
- Required Future Design Life of the Overlay
12
13Important Considerations in Overlay Design
- Shoulders
- Existing PCC Slab Durability
- PCC Overlay Joints
- PCC Overlay Reinforcement
- PCC Overlays Bonding
- Overlay Design Reliability Level Overall
Standard Deviation - Pavement Widening
- Traffic Disruptions and User Delay Costs
13
14Important Considerations in Overlay Design
(contd)
- Existing Pavement Condition Future Traffic
- Pre-overlay Repair
- Recycling Existing Pavement (PCC AC)
- Overlay Materials
14
15AASHTO Bonded Concrete Overlay Design Procedure
- 1. Collect Existing Pavement Information.
- 2. Predict Future ESALs
- 3. Perform Condition Survey
- 4. Perform Deflection Testing (Recommended)
- 5. Perform Coring / Materials Testing
(Recommended) - 6. Determine Future Structural Capacity (TxDOT
Design Procedures for New PCC Pavement) - 7. Determine Existing Structural Capacity
- 8. Determine Overlay Structural Capacity
and Thicknesses
15
16AASHTO OVERLAY DESIGN Procedure
- 1. Collect Existing Pavement Information
- Existing Slab or Layer Thicknesses
- Type of Load Transfer Mechanism
- Type of Shoulder
- Base/Subbase information
- Soils Information
16
17AASHTO OVERLAY DESIGN Procedure
- 2. Predict Future ESALs
- Predicted Future 18K ESAL's in the Design Lane
over the Design Period - Past ESAL's if the Remaining Life Method is used
to determine Structural Capacity of the Existing
Pavement
17
18AASHTO OVERLAY DESIGNLoadings
ESAL SELECTION
OVERLAY
EXISTING
TYPE
PAVEMENT
PCC or AC
JPCP or JRCP
Rigid
PCC or AC
CRCP
Rigid
PCC
AC
Rigid
PCC or AC
COMPOSITE
Rigid
Note Flexible ESALs 2/3 Rigid ESALs
18
19AASHTO OVERLAY DESIGN Procedure
3. Perform Condition Survey
- Number of punchouts per mile
- Number of deteriorated transverse cracks per mile
- Number of existing and new repairs prior to
overlay per mile - Presence and general severity of PCC durability
problems (D-cracking or ASR) - Evidence of pumping of fines or water
20AASHTO OVERLAY DESIGN Procedure
- 4. Perform Deflection Testing
20
21AASHTO OVERLAY DESIGN
- Nondestructive Deflection Testing (NDT)
- Estimate Effective k-value
- Examine Load Transfer Efficiency at Joints and
Cracks - Examine Resilient Modulus of Pavement Layers
- Quantify Variability Along the Project
21
22CRCP Deflections for Various Slab Thicknesses
23AASHTO OVERLAY DESIGN Procedure
- 5. Perform Coring Materials Testing
- The surveys and testing are used to estimate the
in-situ material properties and the condition of
the pavement and underlying layers.
23
24AASHTO OVERLAY DESIGN Procedure
- 6. Determine Future Structural Capacity
- Df Slab Thickness Required to Carry Future
Traffic Loadings - Use TxDOTs Pavement Design Procedures for New
PCC Pavements
24
25Determination of Required Thickness for Future
Traffic
- Factors Required for Slab Thickness
-
- Serviceability (po, pt) Traffic (ESALs,
E-18s) Load Transfer (J) Concrete Properties
(Sc, Ec) Subgrade Strength (k, LS) Drainage
(Cd) Reliability (R, So)
25
26AASHTO OVERLAY DESIGN Procedure
- 7. Determine Structural Capacity of Existing
Pavement - Deff Effective Slab Thickness of the Existing
Pavement
26
27AASHTO OVERLAY DESIGN Structural Capacity
Determination
- Proper Evaluation of Existing Pavement is
Essential to Selecting Appropriate Overlay Designs
27
28AASHTO OVERLAY DESIGN Structural Capacity
Determination
- Structural Capacity of Existing Pavement is
evaluated by two methods - 1. Visual Survey
- 2. Fatigue Damage Due to Traffic (Remaining
Life Method)
28
29AASHTO OVERLAY DESIGN Structural Capacity
Determination
- A. Visual Survey
- Visual Survey - Deteriorated Transverse and
Longitudinal Joints and Cracks Localized
failing Areas Localized Punchouts in CRCP
29
30AASHTO OVERLAY DESIGN Structural Capacity
Determination
- B. Fatigue Damage Due to Traffic (Remaining Life)
- Uses Estimate of Past Traffic to Determine
Existing Damage - Remaining Life Determined from Past Traffic and
Expected Future Traffic
30
31Effective Slab Thicknessby Visual Survey Method
- EFFECTIVE SLAB THICKNESS (Deff)
- Deff Fjc Fdur Ffat D
- Where
- Fjc Joints and Cracks Adjustment Factor Fdur
Durability Adjustment Factor Ffat Fatigue
Adjustment Factor D Thickness of Existing
Slab, in.
31
32Bonded Concrete Overlay Joints Cracks
Adjustment Factor, (Fjc)
- Adjusts for PSI loss due to unrepaired joints,
cracks, and other discontinuities - Pavements with no D cracking or reactive
aggregates - Number of deteriorated transverse joints per mile
- Number of deteriorated transverse cracks per mile
- Number of existing expansion joints,
exceptionally wide joints (gt1 in.), or AC
full-depth patches - Do not include joints or cracks with D cracking
or reactive aggregate deterioration
32
33Bonded Concrete Overlay Joints Cracks
Adjustment Factor, (Fjc)
33
3434
3535
36Bonded Concrete Overlay
- THICKNESS DESIGN Dol Df - Deff
- Where
- Dol Required Slab Thickness of Overlay,
in. Df Slab Thickness to Carry Future
Traffic, in. Deff Thickness of Existing Slab,
in.
36
37BCO Design Procedures
Thickness Needed for Future Traffic
(13-in)
Effective Thickness of Existing Pavement
(10-in 8-in)
Determine Overlay Thickness
(13 8 5 in for BCO)
37
3838
3939
40(No Transcript)
41(No Transcript)
42(No Transcript)
43Bonded Concrete Overlay Joints Cracks
Adjustment Factor, (Fjc)
Fjc 1.0
44Bonded Concrete Overlay Durability Adjustment
Factor, (Fdur)
- Adjusts for PSI loss due to durability problems,
such as D cracking and reactive aggregates - 1.00 No durability problems
- 0.96-0.99 Durability cracking exists, no spalling
- 0.88-0.95 Substantial cracking, some spalling
- 0.80-0.87 Substantial cracking, Severe spalling
Fdur 1.0 (no durability problems)
45Bonded Concrete Overlay Fatigue Adjustment
Factor, (Ffat)
- Adjusts for PSI loss due to fatigue damage in the
slab - 0.97-1.00 Few Cracks / punchouts JPCP lt5
Slabs cracked JRCP lt25 working
cracks/mile CRCP lt 4 punchouts/mile - 0.94-0.96 Significant cracking /
punchouts JPCP 5-15 Slabs cracked JRCP
26-75 working cracks/mile CRCP 4-12
punchouts/mile - 0.90-0.94 Extensive cracking /
punchouts JPCP gt15 Slabs cracked JRCP
gt75 working cracks/mile CRCP gt12 punchouts/mile
Ffat 0.97
46DETERMINATION OF EFFECTIVE SLAB THICKNESS
(Deff) Deff Fjc Fdur Ffat
D Where Fjc Joints and Cracks Adjustment
Factor Fdur Durability Adjustment Factor Ffat
Fatigue Adjustment Factor D Effective
Thickness of Existing Slab, in.
Deff 1.0 1.0 0.97 8 7.75-in
47Bonded Concrete Overlay
THICKNESS DESIGN Dol Df - Deff Where Dol
Required Slab Thickness of Overlay, in. Df
Slab Thickness to Carry Future Traffic, in. Deff
Thickness of Existing Slab, in.
Dol 12.5 7.75 4.75 in Use 5-in for BCO.
48Reinforcement
- The amount of longitudinal reinforcement about
0.6 of concrete cross-sectional area.
48
4949
50End of Design Module
50
51BCO Construction Module
- Material Selection
- Pre-overlay repair
- Surface Preparation
- Reinforcement
- Concrete Placement
- Finishing
- Curing
51
52Material Selection
- Concrete material properties in new layer are
critical for the good performance of BCO. - More specifically, coarse aggregate type is of
utmost importance. - Coarse aggregate with low CTE and modulus of
elasticity is most desirable.
52
53Material Selection
- Fiber or no fiber?
- For thin BCO, up to 3-in., fibers appear to
improve performance. - For thicker BCO, fibers do not seem to help.
53
5454
55Pre-Overlay Repair
- Severe distresses need to be repaired.
- Repair punchouts, wide open transverse
construction joints, working cracks - Do not repair shallow and medium spalling,
non-working transverse and longitudinal cracks
55
56Surface Preparation
- Needed for good bond of new concrete to old
concrete - Good bond is essential to good long-term
performance of BCO. - Making surface texture rough enough to provide
enhanced physical bonding - However, loose materials need to be removed.
56
57Bonding
- One of the most critical element in BCO
construction - Poor construction practices might result in poor
bonding and premature pavement distresses (PPD).
57
58Bonding- Factors -
- Soundness/texture and cleanliness of the existing
pavement surface - Concrete materials low coefficient of thermal
expansion and modulus of elasticity - Curing
- Location of steel reinforcement
58
59Surface Preparation
59
60Shotblasting
60
61Shotblasting
62Milling
62
6363
6464
65Surface Cleaning
65
66Bonding- Factors -
- Bonding grout? - Do not use.
- Existing surface dry or wet? Keep it wet before
the concrete placement.
66
67Reinforcement
- If thickness is more than 3 inches, provide
longitudinal reinforcement. - Vertical location of reinforcement
- - D lt 6-in near the bottom of overlay slab
- - D gt 5-in middle of the overlay slab
67
6868
69Reinforcement
- The amount of longitudinal reinforcement about
0.6 of concrete cross-sectional area - Follow Item 360 requirements for splicing and
staggering.
69
7070
71Concrete Placement
- Follow Item 360 requirements for the following
items - - temperature restrictions
- - sawing timing requirements
- Requirements might be different from Item 360
- - strength
- - slump
- - sawing depth
71
72Concrete Placement
72
7373
7474
7575
76Finishing
- Follow Item 360 requirements.
- Do not over-finish as it increases potential for
segregation. - Surface will be made rough later by carpet drag
and tining. Therefore, the surface doesnt have
to be slick.
76
77Curing
- Follow Item 360 requirements.
- Uniformity of curing is quite important.
- Poor curing will result in plastic shrinkage
cracks and de-bonding, as well as poor durability
of concrete.
77
7878
79Non-uniform curing
79
80plastic shrinkage crack after 6 hours of concrete
placement
80
81Curing
- Curing is critical to the performance of BCO.
- Good curing keeps moisture and reduces volume
changes in concrete due to drying shrinkage and
temperature variations. - Reduced volume changes at early ages provide
concrete to develop bond strength prior to the
development of bond stress.
81
82CTE and Drying Shrinkage Measurements
Vibrating Wire Gage
Insert VWG in conc. specimen
Small size specimen
Spray curing compound
83(No Transcript)
84BCO in Texas- Lessons Learned -
- A number of BCO projects have been placed in
Texas. - Most of them have provided good performance.
- However, problems were experienced in one project.
84
85(No Transcript)
86One BCO Project with Premature Distress
- Too high strength was required.
- Contractor used concrete with low water-cement
ratio, resulting in rather dry concrete produced. - Dry concrete did not have enough moisture to
develop bond.
86
87One BCO Project with Premature Distress
- As long as concrete meets durability and strength
requirements, it doesnt have to be super strong. - Currently, there is no minimum requirement for
water cement ratio. However, pay attention to
water cement ratio.
87
88CRCP BCO on JCP
- Georgia DOT placed CRCP BCO on JCP in 1971 on IH
75 southbound between Atlanta and Macon. - It has provided excellent performance over 30
years.
88
8989
90Concluding Remarks
- BCO is one of the most cost-effective options to
extend the life of structurally deficient
pavement. - Proper design, materials selection, pre-overlay
repairs, and proper construction will result in
good long-term pavement system. -
90