Bonded Concrete Overlay (BCO) Training Module - PowerPoint PPT Presentation

About This Presentation
Title:

Bonded Concrete Overlay (BCO) Training Module

Description:

... and FWD is normally available for the pavement evaluation. Using FWD testing will provide information on the k-value of the existing pavement, ... – PowerPoint PPT presentation

Number of Views:88
Avg rating:3.0/5.0
Slides: 87
Provided by: mwon
Category:

less

Transcript and Presenter's Notes

Title: Bonded Concrete Overlay (BCO) Training Module


1
Bonded Concrete Overlay (BCO) Training Module
  • TxDOT Research Project 0-4893
  • Performance of Old Concrete Under Thin Overlays
  • Center for Transportation Research
  • The University of Texas at Austin

1
2
Acknowledgement
  • PC Charles Gaskin, P.E. (HOU)
  • PD German Claros, Ph.D., P.E. (RTI)
  • PA Joe Leidy, P.E. (CSTMP)
  • Darlene Goehl, P.E. (BRY)
  • Hua Chen, P.E. (CSTMP)

2
3
Training Module Contents
  • BCO Design Module
  • BCO Construction Module
  • BCO in Texas Lessons Learned

3
4
Scope
  • Primarily, continuously reinforced concrete
    pavement (CRCP) overlay on CRCP
  • CRCP overlay on JCP is not fully covered.

4
5
Bonded Concrete Overlay- Overview -
  • Consists of concrete layer (2 to 8 inches) on top
    of an existing concrete surface.
  • One of the most cost-effective way of enhancing
    structural capacity of under-designed pavements
  • Specific steps are taken to bond the new concrete
    overlay to the existing concrete.
  • Increases structural capacity of the pavement
    system by reducing deflections.

5
6
6
7
7
8
Bonded Concrete Overlay (BCO) Design
  • Currently, the AASHTO 1993 Guide is the most
    widely used design method for bonded overlay.

8
9
AASHTO DESIGNRevisions in the 93 Guide
  • Overlay Design was Completely Revised
  • New Procedure consists of 7 Overlay Design
    Procedures
  • Uses the Concept of Structural Deficiency
  • Used for Structural Overlay Design

9
10
Structural Deficiency Approach to Overlay Design
Original Capacity
Structural Capacity
Loads
10
11
Pavement Evaluation for Overlay Design
  • Functional Evaluation of Existing Pavement
  • Surface Friction Problems/Polishing
  • Use Diamond Grinding or Grooving to Restore Skid
    Resistance
  • Surface Roughness
  • Use CPR and Diamond Grinding.

11
12
Overlay Type Feasibility
  • Availability of Adequate Funds
  • Construction Feasibility
  • Traffic Control
  • Materials and Equipment
  • Climatic Conditions
  • Construction Problems (noise, pollution,
    subsurface utilities, overhead clearance)
  • Traffic Disruptions and User Delay Costs
  • Required Future Design Life of the Overlay

12
13
Important Considerations in Overlay Design
  • Shoulders
  • Existing PCC Slab Durability
  • PCC Overlay Joints
  • PCC Overlay Reinforcement
  • PCC Overlays Bonding
  • Overlay Design Reliability Level Overall
    Standard Deviation
  • Pavement Widening
  • Traffic Disruptions and User Delay Costs

13
14
Important Considerations in Overlay Design
(contd)
  • Existing Pavement Condition Future Traffic
  • Pre-overlay Repair
  • Recycling Existing Pavement (PCC AC)
  • Overlay Materials

14
15
AASHTO Bonded Concrete Overlay Design Procedure
  • 1. Collect Existing Pavement Information.
  • 2. Predict Future ESALs
  • 3. Perform Condition Survey
  • 4. Perform Deflection Testing (Recommended)
  • 5. Perform Coring / Materials Testing
    (Recommended)
  • 6. Determine Future Structural Capacity (TxDOT
    Design Procedures for New PCC Pavement)
  • 7. Determine Existing Structural Capacity
  • 8. Determine Overlay Structural Capacity
    and Thicknesses

15
16
AASHTO OVERLAY DESIGN Procedure
  • 1. Collect Existing Pavement Information
  • Existing Slab or Layer Thicknesses
  • Type of Load Transfer Mechanism
  • Type of Shoulder
  • Base/Subbase information
  • Soils Information

16
17
AASHTO OVERLAY DESIGN Procedure
  • 2. Predict Future ESALs
  • Predicted Future 18K ESAL's in the Design Lane
    over the Design Period
  • Past ESAL's if the Remaining Life Method is used
    to determine Structural Capacity of the Existing
    Pavement

17
18
AASHTO OVERLAY DESIGNLoadings
ESAL SELECTION
OVERLAY
EXISTING
TYPE
PAVEMENT
PCC or AC
JPCP or JRCP
Rigid
PCC or AC
CRCP
Rigid
PCC
AC
Rigid
PCC or AC
COMPOSITE
Rigid
Note Flexible ESALs 2/3 Rigid ESALs
18
19
AASHTO OVERLAY DESIGN Procedure
3. Perform Condition Survey
  • Number of punchouts per mile
  • Number of deteriorated transverse cracks per mile
  • Number of existing and new repairs prior to
    overlay per mile
  • Presence and general severity of PCC durability
    problems (D-cracking or ASR)
  • Evidence of pumping of fines or water

20
AASHTO OVERLAY DESIGN Procedure
  • 4. Perform Deflection Testing

20
21
AASHTO OVERLAY DESIGN
  • Nondestructive Deflection Testing (NDT)
  • Estimate Effective k-value
  • Examine Load Transfer Efficiency at Joints and
    Cracks
  • Examine Resilient Modulus of Pavement Layers
  • Quantify Variability Along the Project

21
22
CRCP Deflections for Various Slab Thicknesses
23
AASHTO OVERLAY DESIGN Procedure
  • 5. Perform Coring Materials Testing
  • The surveys and testing are used to estimate the
    in-situ material properties and the condition of
    the pavement and underlying layers.

23
24
AASHTO OVERLAY DESIGN Procedure
  • 6. Determine Future Structural Capacity
  • Df Slab Thickness Required to Carry Future
    Traffic Loadings
  • Use TxDOTs Pavement Design Procedures for New
    PCC Pavements

24
25
Determination of Required Thickness for Future
Traffic
  • Factors Required for Slab Thickness
  • Serviceability (po, pt) Traffic (ESALs,
    E-18s) Load Transfer (J) Concrete Properties
    (Sc, Ec) Subgrade Strength (k, LS) Drainage
    (Cd) Reliability (R, So)

25
26
AASHTO OVERLAY DESIGN Procedure
  • 7. Determine Structural Capacity of Existing
    Pavement
  • Deff Effective Slab Thickness of the Existing
    Pavement

26
27
AASHTO OVERLAY DESIGN Structural Capacity
Determination
  • Proper Evaluation of Existing Pavement is
    Essential to Selecting Appropriate Overlay Designs

27
28
AASHTO OVERLAY DESIGN Structural Capacity
Determination
  • Structural Capacity of Existing Pavement is
    evaluated by two methods
  • 1. Visual Survey
  • 2. Fatigue Damage Due to Traffic (Remaining
    Life Method)

28
29
AASHTO OVERLAY DESIGN Structural Capacity
Determination
  • A. Visual Survey
  • Visual Survey - Deteriorated Transverse and
    Longitudinal Joints and Cracks Localized
    failing Areas Localized Punchouts in CRCP

29
30
AASHTO OVERLAY DESIGN Structural Capacity
Determination
  • B. Fatigue Damage Due to Traffic (Remaining Life)
  • Uses Estimate of Past Traffic to Determine
    Existing Damage
  • Remaining Life Determined from Past Traffic and
    Expected Future Traffic

30
31
Effective Slab Thicknessby Visual Survey Method
  • EFFECTIVE SLAB THICKNESS (Deff)
  • Deff Fjc Fdur Ffat D
  • Where
  • Fjc Joints and Cracks Adjustment Factor Fdur
    Durability Adjustment Factor Ffat Fatigue
    Adjustment Factor D Thickness of Existing
    Slab, in.

31
32
Bonded Concrete Overlay Joints Cracks
Adjustment Factor, (Fjc)
  • Adjusts for PSI loss due to unrepaired joints,
    cracks, and other discontinuities
  • Pavements with no D cracking or reactive
    aggregates
  • Number of deteriorated transverse joints per mile
  • Number of deteriorated transverse cracks per mile
  • Number of existing expansion joints,
    exceptionally wide joints (gt1 in.), or AC
    full-depth patches
  • Do not include joints or cracks with D cracking
    or reactive aggregate deterioration

32
33
Bonded Concrete Overlay Joints Cracks
Adjustment Factor, (Fjc)
33
34
34
35
35
36
Bonded Concrete Overlay
  • THICKNESS DESIGN Dol Df - Deff
  • Where
  • Dol Required Slab Thickness of Overlay,
    in. Df Slab Thickness to Carry Future
    Traffic, in. Deff Thickness of Existing Slab,
    in.

36
37
BCO Design Procedures
Thickness Needed for Future Traffic
(13-in)
Effective Thickness of Existing Pavement
(10-in 8-in)
Determine Overlay Thickness
(13 8 5 in for BCO)
37
38
38
39
39
40
(No Transcript)
41
(No Transcript)
42
(No Transcript)
43
Bonded Concrete Overlay Joints Cracks
Adjustment Factor, (Fjc)
Fjc 1.0
44
Bonded Concrete Overlay Durability Adjustment
Factor, (Fdur)
  • Adjusts for PSI loss due to durability problems,
    such as D cracking and reactive aggregates
  • 1.00 No durability problems
  • 0.96-0.99 Durability cracking exists, no spalling
  • 0.88-0.95 Substantial cracking, some spalling
  • 0.80-0.87 Substantial cracking, Severe spalling

Fdur 1.0 (no durability problems)
45
Bonded Concrete Overlay Fatigue Adjustment
Factor, (Ffat)
  • Adjusts for PSI loss due to fatigue damage in the
    slab
  • 0.97-1.00 Few Cracks / punchouts JPCP lt5
    Slabs cracked JRCP lt25 working
    cracks/mile CRCP lt 4 punchouts/mile
  • 0.94-0.96 Significant cracking /
    punchouts JPCP 5-15 Slabs cracked JRCP
    26-75 working cracks/mile CRCP 4-12
    punchouts/mile
  • 0.90-0.94 Extensive cracking /
    punchouts JPCP gt15 Slabs cracked JRCP
    gt75 working cracks/mile CRCP gt12 punchouts/mile

Ffat 0.97
46
DETERMINATION OF EFFECTIVE SLAB THICKNESS
(Deff) Deff Fjc Fdur Ffat
D Where Fjc Joints and Cracks Adjustment
Factor Fdur Durability Adjustment Factor Ffat
Fatigue Adjustment Factor D Effective
Thickness of Existing Slab, in.
Deff 1.0 1.0 0.97 8 7.75-in
47
Bonded Concrete Overlay
THICKNESS DESIGN Dol Df - Deff Where Dol
Required Slab Thickness of Overlay, in. Df
Slab Thickness to Carry Future Traffic, in. Deff
Thickness of Existing Slab, in.
Dol 12.5 7.75 4.75 in Use 5-in for BCO.
48
Reinforcement
  • The amount of longitudinal reinforcement about
    0.6 of concrete cross-sectional area.

48
49
49
50
End of Design Module
50
51
BCO Construction Module
  • Material Selection
  • Pre-overlay repair
  • Surface Preparation
  • Reinforcement
  • Concrete Placement
  • Finishing
  • Curing

51
52
Material Selection
  • Concrete material properties in new layer are
    critical for the good performance of BCO.
  • More specifically, coarse aggregate type is of
    utmost importance.
  • Coarse aggregate with low CTE and modulus of
    elasticity is most desirable.

52
53
Material Selection
  • Fiber or no fiber?
  • For thin BCO, up to 3-in., fibers appear to
    improve performance.
  • For thicker BCO, fibers do not seem to help.

53
54
54
55
Pre-Overlay Repair
  • Severe distresses need to be repaired.
  • Repair punchouts, wide open transverse
    construction joints, working cracks
  • Do not repair shallow and medium spalling,
    non-working transverse and longitudinal cracks

55
56
Surface Preparation
  • Needed for good bond of new concrete to old
    concrete
  • Good bond is essential to good long-term
    performance of BCO.
  • Making surface texture rough enough to provide
    enhanced physical bonding
  • However, loose materials need to be removed.

56
57
Bonding
  • One of the most critical element in BCO
    construction
  • Poor construction practices might result in poor
    bonding and premature pavement distresses (PPD).

57
58
Bonding- Factors -
  • Soundness/texture and cleanliness of the existing
    pavement surface
  • Concrete materials low coefficient of thermal
    expansion and modulus of elasticity
  • Curing
  • Location of steel reinforcement

58
59
Surface Preparation
  • Shotblasting
  • Milling

59
60
Shotblasting

60
61
Shotblasting
62
Milling
62
63
63
64
64
65
Surface Cleaning
65
66
Bonding- Factors -
  • Bonding grout? - Do not use.
  • Existing surface dry or wet? Keep it wet before
    the concrete placement.

66
67
Reinforcement
  • If thickness is more than 3 inches, provide
    longitudinal reinforcement.
  • Vertical location of reinforcement
  • - D lt 6-in near the bottom of overlay slab
  • - D gt 5-in middle of the overlay slab

67
68
68
69
Reinforcement
  • The amount of longitudinal reinforcement about
    0.6 of concrete cross-sectional area
  • Follow Item 360 requirements for splicing and
    staggering.

69
70
70
71
Concrete Placement
  • Follow Item 360 requirements for the following
    items
  • - temperature restrictions
  • - sawing timing requirements
  • Requirements might be different from Item 360
  • - strength
  • - slump
  • - sawing depth

71
72
Concrete Placement
72
73
73
74
74
75
75
76
Finishing
  • Follow Item 360 requirements.
  • Do not over-finish as it increases potential for
    segregation.
  • Surface will be made rough later by carpet drag
    and tining. Therefore, the surface doesnt have
    to be slick.

76
77
Curing
  • Follow Item 360 requirements.
  • Uniformity of curing is quite important.
  • Poor curing will result in plastic shrinkage
    cracks and de-bonding, as well as poor durability
    of concrete.

77
78
78
79
Non-uniform curing
79
80
plastic shrinkage crack after 6 hours of concrete
placement
80
81
Curing
  • Curing is critical to the performance of BCO.
  • Good curing keeps moisture and reduces volume
    changes in concrete due to drying shrinkage and
    temperature variations.
  • Reduced volume changes at early ages provide
    concrete to develop bond strength prior to the
    development of bond stress.

81
82
CTE and Drying Shrinkage Measurements
Vibrating Wire Gage
Insert VWG in conc. specimen
Small size specimen
Spray curing compound
83
(No Transcript)
84
BCO in Texas- Lessons Learned -
  • A number of BCO projects have been placed in
    Texas.
  • Most of them have provided good performance.
  • However, problems were experienced in one project.

84
85
(No Transcript)
86
One BCO Project with Premature Distress
  • Too high strength was required.
  • Contractor used concrete with low water-cement
    ratio, resulting in rather dry concrete produced.
  • Dry concrete did not have enough moisture to
    develop bond.

86
87
One BCO Project with Premature Distress
  • As long as concrete meets durability and strength
    requirements, it doesnt have to be super strong.
  • Currently, there is no minimum requirement for
    water cement ratio. However, pay attention to
    water cement ratio.

87
88
CRCP BCO on JCP
  • Georgia DOT placed CRCP BCO on JCP in 1971 on IH
    75 southbound between Atlanta and Macon.
  • It has provided excellent performance over 30
    years.

88
89
89
90
Concluding Remarks
  • BCO is one of the most cost-effective options to
    extend the life of structurally deficient
    pavement.
  • Proper design, materials selection, pre-overlay
    repairs, and proper construction will result in
    good long-term pavement system.

90
Write a Comment
User Comments (0)
About PowerShow.com