Transcript and Presenter's Notes

Title: Texas Tech University Bikeway Plan


1
Texas Tech UniversityBikeway Plan
  • August 12, 2005

2
Committee
  • Walker Parking Consultants
  • Michael Shonrock, Student Affairs
  • Mike Ellicott, Facilities Planning Const.
  • Ryan Worley, Student Government Assoc.
  • Nathan Nash, Student Government Assoc.
  • Eric Crouch, Traffic and Parking Oper.
  • Buddy Knox, Traffic and Parking Operations
  • Art Glick, Site Development
  • Charles Leathorwood, Grounds Maintenance
  • Jimmy Tillinghast, Police Department

3
Purpose
  • Provide a comprehensive bike system that enhances
    and encourages safe bicycle traveling on campus
  • Ensure the safety of our students who do choose
    to ride their bikes on campus
  • Alleviate the current stress that is being placed
    on our parking system

4
Current Conditions
  • The first bike lane was recently completed,
    extending down 18th street from Indiana to Boston
  • No other bike lanes on the interior of campus
  • Shared use paths have been constructed at the new
    park and ride facility as well as on 4th street
    in front of the TTPD that need to be striped

5
Current Conditions (cont.)
  • Bike Racks
  • 233 existing bike racks
  • All existing racks are mobile
  • Bike Traffic
  • Estimated 2,500 bikes on campus

6
Construction options
  • Bike Lane
  • 4 striped roadway that is shared by the vehicles
    and the bicyclists (road must be at least 34
    wide)
  • Shared Roadway
  • Roadway less than 34 wide that is shared by the
    vehicles and the bicyclists
  • Shared Use Paths
  • 10 path that is striped and shared by
    pedestrians and bicyclists

7
Cost Breakdown
Shared Paths 40 Ln. Ft.
Shared Roadway 4,500 Per mile/ c
Bike Lanes on Roadway 8,000 Per mile
Bike Racks 100 Per bike space
Bike Lockers 1,500 Per bike space
8
Future Plans
  • Phase 1
  • Implemented by Spring 2006
  • To include
  • Shared paths
  • Bike lanes
  • Route signs
  • Additional bike racks
  • Cost
  • 58,900

9
Phase 1
10
Future Plans (cont.)
  • Phase 2
  • Set to begin as soon as funding is secured
  • To include
  • An established path from the park and ride to
    the interior of campus
  • Access over the Marsha Sharp Freeway
    (ie. Pedestrian overpass)
  • Cost
  • 142,200

11
Phase 2
12
Marketing
  • Program name (Bike Tech)
  • Bicycle registration drives
  • Bicycle signs (including the pavement)
  • Education
  • On-campus facilities
  • (Maintenance, supplies, etc.)
  • If you build it, they will come. -Field of
    Dreams