Title: NIGERIA SAO TOME AND PRINCIPE JOINT DEVELOPMENT AUTHORITY __________________________________________
1NIGERIA SAO TOME AND PRINCIPEJOINT DEVELOPMENT
AUTHORITY________________________________________
____________
- KEY PARAMETERS OF THE FISCAL REGIME
- IN THE NIGERIA SAO TOME AND PRINCIPE
- JOIN DEVELOPMENT ZONE
- CARLOS B. GOMES
- DEPUTY DIRECTOR
- MONITORING AND INSPECTION DEPARTMENT
2INTRODUCTION
- Main purpose of this presentation Give an
insight on the work of the Nigeria São Tomé e
Príncipe Joint Development Authority.
- First Ill briefly give some background
information that led to the signing of the Treaty
between Nigeria and São Tomé e Príncipe on the
Joint Development of all the Resources in the
JDZ - Ill then proceed with more detailed information
on the Applicable Laws in the Zone
- Ill conclude the Presentation with some usefull
information about the current ongoing 2003 JDZ
Licensing Round and information on key elements
of the agreements reached on Third Party Interest.
3BACKGROUND
- The Democratic Republic of Sao Tomé Principe
passed its Official Maritime Claims Law on
March 1998 and deposited same with the United
Nations. - This Law established the limit of STPs maritime
claim at the median line with Nigeria, Equatorial
Guinea and Gabon.
4BACKGROUND
5BACKGROUND
- Based on this Law, there was a considerable
overlap with the maritime boundary as claimed by
the Republic of Nigeria.
- In November 1999, the Heads of State mandated the
Border Commissions of the two countries to meet
and agree on a solution for the Maritime boundary
delimitation. - After several negotiations a Joint Development
Zone was agreed by both States and a Treaty
signed on 21st February 2001.
6THE JOINT DEVELOPMENT ZONE
7KEY PROVISIONS OF THE TREATY
- The Treaty establishes the Joint Development Zone
(JDZ) in a specific area defined by
co-ordinates.
- The two States to share net proceeds from
activities in the Zone on a 60/40 basis.
- The Treaty is valid for 45 years with possible
review after 30 years.
- There is no renunciation of claims to the Zone by
either of the States Parties.
8KEY PROVISIONS OF THE TREATY (continued)
- The resources of the Zone are to be developed
jointly through the Joint Development Authority
(JDA).
- JDA reports to a Joint Ministerial Council (JMC)
which has overall political responsibility over
the JDZ.
- Applicable Laws in the JDZ to be approved by the
JMC.
9KEY PROVISIONS OF THE TREATY (continued)
- THE JOINT MINISTERIAL COUNCIL
- Made up of 2 to 4 Ministers from each country.
- Have overall responsibility for the JDZ.
- Gives directions to the Authority.
- Reviews the operation of the Treaty.
- Reviews Treaty for Amendments.
- Dispute resolution in the Authority.
- Shall meet at least twice a year and as often as
may be required, alternately in Nigeria and in
São Tomé e Príncipe.
- All decisions of the Council shall be adopted by
consensus.
10KEY PROVISIONS OF THE TREATY (continued)
- THE JOINT DEVELOPMENT AUTHORITY
- The Authority shall have juridical personality in
international law and under the law of each of
the States Parties and such legal capacities
under the law of both States Parties as are
necessary for the exercise of its powers and the
performance of its functions. - In particular, the Authority shall have the
capacity to contract, to acquire and dispose of
movable and immovable property and to institute
and be party to legal proceedings. - The Authority, subject to directions from the
Council, shall be responsible for the management
of activities relating to exploration for and
exploitation of the resources in the Zone (in
accordance with the provisions of the Treaty).
11ORGANIZATION CHART OF THE JOINT AUTHORITY
12KEY PARAMETERS OF THE PETROLEUM REGULATIONS 2003
- Petroleum operations in the Joint Development
Zone are guided by the Petroleum Regulations 2003
as approved by the Joint Ministerial Council on
the 4th of April, 2003. - No Petroleum activity may be undertaken in the
JDZ except pursuant to and in accordance with the
Petroleum Regulations 2003.
- All acreage in the JDZ is held on behalf of the
State Parties by the Joint Development
Authority.
- In the JDZ there will be a mixed of licensing and
PSC regimes.
13KEY PARAMETERS OF THE PETROLEUM REGULATIONS 2003
- Participation in petroleum exploration,
development and production operations in the zone
is open to
- Any company registered in any or both of the
States Parties
- Any company incorporated in any or both of the
States Parties
14KEY PARAMETERS OF THE PETROLEUM REGULATIONS 2003
- Termination of the contract can be triggered by
- The contractor upon giving six months written
notice to the Authority.
- The Authority if the contractor does not carry
out operations as specified by the Regulations
and does not explain or remedy the grounds of
revocation upon written notice by the Authority. - The Authority may revoke or terminate the
Contract if within 4 years the company fails to
show verifiable evidence of efforts made to meet
the required minimum work programme, and/or is
not conducting operations in a vigorous and
businesslike manner in accordance with good
oilfield practice, or has failed to comply either
with the terms of its license, lease or PSC.
15KEY PARAMETERS OF THE FISCAL REGIME
- A uniform Tax rate of 50 shall be charged
throughout the JDZ.
- A sliding scale royalty rate based on daily
production will apply.
-
16KEY PARAMETERS OF THE FISCAL REGIME
- Area Rentals shall be charged as follows
- OPL for each sq. km. or part thereof 200
- OML for each sq. km or part thereof
- During the first 10 years of term 50
- Thereafter 200
17KEY PARAMETERS OF THE FISCAL REGIME
- The following fees and charges shall apply
- Application for an OPL (bid package)
15,000
- Processing fee for an OPL application
10,000
- Application for an OML
1,000,000
- Application to assign a stake in an OPL or PSC
500,000
- Application to assign a stake in an OML or PSC
1,000,000
- Application to terminate an OPL , OML or PSC
100,000
- Application for a license to operate a drilling
rig 100,000
- License to operate a drilling rig (annually)
50,000
- Permit to export samples for analysis (per
well) 10,000
18KEY PARAMETERS OF THE PRODUCTION SHARING CONTRACT
- The term of a PSC shall be for twenty eight (28)
years from the Effective Date, inclusive of eight
(8) years Exploration period under an OPL and
twenty (20) years of Development and Production
Period under an OML. - CONTRACTOR is authorized to conduct Exploration
Operations for a period of eight (8) years from
the Effective Date (Exploration Period) as
follows - CONTRACTOR shall commence Operations not later
than thirty (30) days after the Effective Date.
- The eight (8) years Exploration Period shall be
divided into three separate phases as follows
- Phase I -four (4) years from the Effective
Date.
- Phase II -From the end of Phase I until two (2)
years after the end of Phase I.
- Phase III -From the end of Phase II until two
(2) years after the end of Phase II.
19KEY PARAMETERS OF THE PRODUCTION SHARING CONTRACT
- A Signature Bonus shall be payable in one tranche
and shall be non cost recoverable and non tax
deductible.
- The Production Bonus shall be paid within one
month upon reaching the stated production
threshold.
- A Minimum Work Obligation of two wells or the
equivalent of one well worth of 3D seismic data
and one well. This minimum work obligation may be
increased for blocks with a significant number of
prospects. - Ring Fencing of individual developments for cost
recovery and profit share and on a PSC basis for
taxation.
- There shall be a Cost Recovery Ceiling of 80.
20KEY PARAMETERS OF THE PRODUCTION SHARING
CONTRACT(cont.)
- Contractors Profit Share, P() will be based on
an R factor.
- R factor will be a function of Investors
cumulative cost recovery and profit share over
cumulative capital and operating costs.
21KEY PARAMETERS OF THE PRODUCTION SHARING
CONTRACT(cont)
- The following relinquishment provisions shall
apply
- 25 of the contract area shall be relinquished at
the end of phase I of the Exploration Period.
- A further 25 of the Contract Area shall be
relinquished at the end of phase III of the
Exploration Period.
- Any excluded area shall revert to the JDA.
- The retained 50 area has to be a single
continuous unit
22JDZ 2003 LICENSING ROUND
- The opening of the JDZ 2003 Licensing Round has
been announced by JDA on April 22nd , 2003
- The Round will remain open for a period of six
months and will be closed on Friday 18th, October
2003 at 0500 Oclock pm
- All Bids to be delivered to the Head Office of
the JDA in Abuja or to the Liaison Office in S.
Tomé e Príncipe
- A total of nine (9) Blocks in the Northern part
of the JDZ, covering a total area of over eight
thousand (8,000) sq. Km, have been offered for
tender - Guidelines containing key directives for
potential Investors have been published by JDA.
23BLOCKS FOR TENDER IN JDZ 2003 LICENSING ROUND
24RESOLUTION OF THIRD PARTY INTERESTS
- All issues pertaining to Third Party Interest
(ExxonMobil, PGS and ERHC) have been amicably
resolved
- On the nine Blocks offered for tender in the JDZ,
only a cumulative of 22 have been commited
- There is only a maximum of 40 pre-commitment on
any of the nine (9) Blocks on offer
- There is no prior commitment for operatorship in
any of the Blocks
- All remaining interest in the nine (9) Blocks are
open to the ongoing competitive bidding round.
25JDA ROAD SHOW
- JDA will hold Road Shows as follows
- In London June 19 and 20
- In Houston, June 23 and 24.
- All relevant legislation (Petroleum Regulations,
Tax Regulations and model PSC) will be available,
as part of the Bid Package, before the Road
Show - Data Package can be purchased through appropriate
seismic company.