NIGERIA SAO TOME AND PRINCIPE JOINT DEVELOPMENT AUTHORITY __________________________________________ - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

NIGERIA SAO TOME AND PRINCIPE JOINT DEVELOPMENT AUTHORITY __________________________________________

Description:

Luanda Angola, May 20 23rd. 2003. NIGERIA SAO TOME AND PRINCIPE ... Luanda Angola, May 20 23rd. 2003. KEY PARAMETERS OF THE PRODUCTION SHARING ... – PowerPoint PPT presentation

Number of Views:470
Avg rating:3.0/5.0
Slides: 26
Provided by: carlos109
Category:

less

Transcript and Presenter's Notes

Title: NIGERIA SAO TOME AND PRINCIPE JOINT DEVELOPMENT AUTHORITY __________________________________________


1
NIGERIA SAO TOME AND PRINCIPEJOINT DEVELOPMENT
AUTHORITY________________________________________
____________
  • KEY PARAMETERS OF THE FISCAL REGIME
  • IN THE NIGERIA SAO TOME AND PRINCIPE
  • JOIN DEVELOPMENT ZONE
  • CARLOS B. GOMES
  • DEPUTY DIRECTOR
  • MONITORING AND INSPECTION DEPARTMENT

2
INTRODUCTION
  • Main purpose of this presentation Give an
    insight on the work of the Nigeria São Tomé e
    Príncipe Joint Development Authority.
  • First Ill briefly give some background
    information that led to the signing of the Treaty
    between Nigeria and São Tomé e Príncipe on the
    Joint Development of all the Resources in the
    JDZ
  • Ill then proceed with more detailed information
    on the Applicable Laws in the Zone
  • Ill conclude the Presentation with some usefull
    information about the current ongoing 2003 JDZ
    Licensing Round and information on key elements
    of the agreements reached on Third Party Interest.

3
BACKGROUND
  • The Democratic Republic of Sao Tomé Principe
    passed its Official Maritime Claims Law on
    March 1998 and deposited same with the United
    Nations.
  • This Law established the limit of STPs maritime
    claim at the median line with Nigeria, Equatorial
    Guinea and Gabon.

4
BACKGROUND
5
BACKGROUND
  • Based on this Law, there was a considerable
    overlap with the maritime boundary as claimed by
    the Republic of Nigeria.
  • In November 1999, the Heads of State mandated the
    Border Commissions of the two countries to meet
    and agree on a solution for the Maritime boundary
    delimitation.
  • After several negotiations a Joint Development
    Zone was agreed by both States and a Treaty
    signed on 21st February 2001.

6
THE JOINT DEVELOPMENT ZONE
7
KEY PROVISIONS OF THE TREATY
  • The Treaty establishes the Joint Development Zone
    (JDZ) in a specific area defined by
    co-ordinates.
  • The two States to share net proceeds from
    activities in the Zone on a 60/40 basis.
  • The Treaty is valid for 45 years with possible
    review after 30 years.
  • There is no renunciation of claims to the Zone by
    either of the States Parties.

8
KEY PROVISIONS OF THE TREATY (continued)
  • The resources of the Zone are to be developed
    jointly through the Joint Development Authority
    (JDA).
  • JDA reports to a Joint Ministerial Council (JMC)
    which has overall political responsibility over
    the JDZ.
  • Applicable Laws in the JDZ to be approved by the
    JMC.

9
KEY PROVISIONS OF THE TREATY (continued)
  • THE JOINT MINISTERIAL COUNCIL
  • Made up of 2 to 4 Ministers from each country.
  • Have overall responsibility for the JDZ.
  • Gives directions to the Authority.
  • Reviews the operation of the Treaty.
  • Reviews Treaty for Amendments.
  • Dispute resolution in the Authority.
  • Shall meet at least twice a year and as often as
    may be required, alternately in Nigeria and in
    São Tomé e Príncipe.
  • All decisions of the Council shall be adopted by
    consensus.

10
KEY PROVISIONS OF THE TREATY (continued)
  • THE JOINT DEVELOPMENT AUTHORITY
  • The Authority shall have juridical personality in
    international law and under the law of each of
    the States Parties and such legal capacities
    under the law of both States Parties as are
    necessary for the exercise of its powers and the
    performance of its functions.
  • In particular, the Authority shall have the
    capacity to contract, to acquire and dispose of
    movable and immovable property and to institute
    and be party to legal proceedings.
  • The Authority, subject to directions from the
    Council, shall be responsible for the management
    of activities relating to exploration for and
    exploitation of the resources in the Zone (in
    accordance with the provisions of the Treaty).

11
ORGANIZATION CHART OF THE JOINT AUTHORITY
12
KEY PARAMETERS OF THE PETROLEUM REGULATIONS 2003
  • Petroleum operations in the Joint Development
    Zone are guided by the Petroleum Regulations 2003
    as approved by the Joint Ministerial Council on
    the 4th of April, 2003.
  • No Petroleum activity may be undertaken in the
    JDZ except pursuant to and in accordance with the
    Petroleum Regulations 2003.
  • All acreage in the JDZ is held on behalf of the
    State Parties by the Joint Development
    Authority.
  • In the JDZ there will be a mixed of licensing and
    PSC regimes.

13
KEY PARAMETERS OF THE PETROLEUM REGULATIONS 2003
  • Participation in petroleum exploration,
    development and production operations in the zone
    is open to
  • Any company registered in any or both of the
    States Parties
  • Any company incorporated in any or both of the
    States Parties

14
KEY PARAMETERS OF THE PETROLEUM REGULATIONS 2003
  • Termination of the contract can be triggered by
  • The contractor upon giving six months written
    notice to the Authority.
  • The Authority if the contractor does not carry
    out operations as specified by the Regulations
    and does not explain or remedy the grounds of
    revocation upon written notice by the Authority.
  • The Authority may revoke or terminate the
    Contract if within 4 years the company fails to
    show verifiable evidence of efforts made to meet
    the required minimum work programme, and/or is
    not conducting operations in a vigorous and
    businesslike manner in accordance with good
    oilfield practice, or has failed to comply either
    with the terms of its license, lease or PSC.

15
KEY PARAMETERS OF THE FISCAL REGIME
  • A uniform Tax rate of 50 shall be charged
    throughout the JDZ.
  • A sliding scale royalty rate based on daily
    production will apply.

16
KEY PARAMETERS OF THE FISCAL REGIME
  • Area Rentals shall be charged as follows
  • OPL for each sq. km. or part thereof 200
  • OML for each sq. km or part thereof
  • During the first 10 years of term 50
  • Thereafter 200

17
KEY PARAMETERS OF THE FISCAL REGIME
  • The following fees and charges shall apply
  • Application for an OPL (bid package)
    15,000
  • Processing fee for an OPL application
    10,000
  • Application for an OML
    1,000,000
  • Application to assign a stake in an OPL or PSC
    500,000
  • Application to assign a stake in an OML or PSC
    1,000,000
  • Application to terminate an OPL , OML or PSC
    100,000
  • Application for a license to operate a drilling
    rig 100,000
  • License to operate a drilling rig (annually)
    50,000
  • Permit to export samples for analysis (per
    well) 10,000

18
KEY PARAMETERS OF THE PRODUCTION SHARING CONTRACT
  • The term of a PSC shall be for twenty eight (28)
    years from the Effective Date, inclusive of eight
    (8) years Exploration period under an OPL and
    twenty (20) years of Development and Production
    Period under an OML.
  • CONTRACTOR is authorized to conduct Exploration
    Operations for a period of eight (8) years from
    the Effective Date (Exploration Period) as
    follows
  • CONTRACTOR shall commence Operations not later
    than thirty (30) days after the Effective Date.
  • The eight (8) years Exploration Period shall be
    divided into three separate phases as follows
  • Phase I -four (4) years from the Effective
    Date.
  • Phase II -From the end of Phase I until two (2)
    years after the end of Phase I.
  • Phase III -From the end of Phase II until two
    (2) years after the end of Phase II.

19
KEY PARAMETERS OF THE PRODUCTION SHARING CONTRACT
  • A Signature Bonus shall be payable in one tranche
    and shall be non cost recoverable and non tax
    deductible.
  • The Production Bonus shall be paid within one
    month upon reaching the stated production
    threshold.
  • A Minimum Work Obligation of two wells or the
    equivalent of one well worth of 3D seismic data
    and one well. This minimum work obligation may be
    increased for blocks with a significant number of
    prospects.
  • Ring Fencing of individual developments for cost
    recovery and profit share and on a PSC basis for
    taxation.
  • There shall be a Cost Recovery Ceiling of 80.

20
KEY PARAMETERS OF THE PRODUCTION SHARING
CONTRACT(cont.)
  • Contractors Profit Share, P() will be based on
    an R factor.
  • R factor will be a function of Investors
    cumulative cost recovery and profit share over
    cumulative capital and operating costs.

21
KEY PARAMETERS OF THE PRODUCTION SHARING
CONTRACT(cont)
  • The following relinquishment provisions shall
    apply
  • 25 of the contract area shall be relinquished at
    the end of phase I of the Exploration Period.
  • A further 25 of the Contract Area shall be
    relinquished at the end of phase III of the
    Exploration Period.
  • Any excluded area shall revert to the JDA.
  • The retained 50 area has to be a single
    continuous unit

22
JDZ 2003 LICENSING ROUND
  • The opening of the JDZ 2003 Licensing Round has
    been announced by JDA on April 22nd , 2003
  • The Round will remain open for a period of six
    months and will be closed on Friday 18th, October
    2003 at 0500 Oclock pm
  • All Bids to be delivered to the Head Office of
    the JDA in Abuja or to the Liaison Office in S.
    Tomé e Príncipe
  • A total of nine (9) Blocks in the Northern part
    of the JDZ, covering a total area of over eight
    thousand (8,000) sq. Km, have been offered for
    tender
  • Guidelines containing key directives for
    potential Investors have been published by JDA.

23
BLOCKS FOR TENDER IN JDZ 2003 LICENSING ROUND
24
RESOLUTION OF THIRD PARTY INTERESTS
  • All issues pertaining to Third Party Interest
    (ExxonMobil, PGS and ERHC) have been amicably
    resolved
  • On the nine Blocks offered for tender in the JDZ,
    only a cumulative of 22 have been commited
  • There is only a maximum of 40 pre-commitment on
    any of the nine (9) Blocks on offer
  • There is no prior commitment for operatorship in
    any of the Blocks
  • All remaining interest in the nine (9) Blocks are
    open to the ongoing competitive bidding round.

25
JDA ROAD SHOW
  • JDA will hold Road Shows as follows
  • In London June 19 and 20
  • In Houston, June 23 and 24.
  • All relevant legislation (Petroleum Regulations,
    Tax Regulations and model PSC) will be available,
    as part of the Bid Package, before the Road
    Show
  • Data Package can be purchased through appropriate
    seismic company.
Write a Comment
User Comments (0)
About PowerShow.com