Title: Material Handling
1Material Handling
2Materials Handling
- Materials handling is a non-value activity that
your customer is unwilling to pay for. - Constantly question material handling methods
and manufacturing methods. . . your competitors
do! - Just because you have always done it that way
does not make it right.
3Materials Handling Mistakes
A Local Companys Materials Handling Process-
Step 2- Move to WIP Warehouse
Step 1-Begin Assemblies
Step 3- Store in WIP Warehouse
Step 4- Move back to Manufacturing
4Materials Handling Mistakes
Local Companys Materials Handling Process-
Step 6- Back to the Warehouse
Continue Until Complete 36 Trailers / Day
Step 5- Begin Assembly
5Materials Handling Mistakes
Company Results
- Material was handled so much that damage was
inevitable. - Their customer began penalizing them 100 per
damaged part received due to the poor finished
goods quality. - The materials handling inefficiencies manifested
themselves in higher product costs, larger
amounts of WIP, poor product quality and longer
lead times. - The parts were inspected eight (8) times on
average, product yield was a dismal 60. - A reduction in two (2) inspections steps
generated over 1M in annual savings. . .the
right question should have been Why are we
moving these parts so much?
6Materials Handling Example
7Cycle Times and Materials Handling
Old Adage the smaller the lot size, the higher
the materials handling and setup costs the
faster the assembly line conveyor speed, the
higher the production output Response Ask the
right answer and get the right question . .
. Focus on the true problems that prevent
smaller lot sizes and faster production speeds.
8Cycle Times and Materials Handling
Units / shift 60 sec / cycle time per unit 60
/ 18 3.33 units per minute 3.33 units per
minute X 60 minutes X 7 hours 1400 units / shift
9Cycle Times and Materials Handling
Units / shift 60 sec / cycle time per unit 60
/ 15 4 units per minute 4 units per minute X 60
minutes X 7 hours 1680 units / shift
10Cycle Times and Materials Handling
The right question was how to increasing
production while reducing cycle time. . .the
wrong answer was speeding up the line!
Results 1,680 / 1,400 1.2 20 Production
Increase
11Key Manufacturing Fundamentals
- Four Fundamental Customer Expectations
- Product Quality
- Delivery as scheduled / requested
- Flexibility to handle change and service
- Low
One method to achieve this is by implementing
Lean Manufacturing principles
12Benefits of Lean
Percentage of Benefits Achieved
0 25 50 75 100
Lead Time Reduction
Productivity Increase
WIP Reduction
Quality Improvement
Space Utilization
13Conclusion
Two Major Elements of the Direct and Indirect
Factory Labor Costs Equation are Effected by 1.
The way we handle materials 2. The way our
facilities are laid out This will be our focus
this semester