Title: Claudia Womble
1COMPILING A COMPLETE PROCUREMENT REQUEST PACKAGE
- Claudia Womble
- GSFC Procurement Operations Division
- Updated March 3, 2005
2Contents
- PR Package (Competitive Procurement)
- PR Package (Non-Competitive Procurement)
- Simplified Acquisition PR Package (Competitive
Procurement) - Simplified Acquisition PR Package
(Non-Competitive Procurement) - Details for Each Checklist Item
3Procurement Request
- SAP Purchase Requisition Form used for purchases
over 2500 and administrative actions such as
funding, option exercise, task orders, and change
orders - Commitment of PR Funds by Resources Analyst
- Obligation of Funds by Contracting Officer
- Planning Purpose Procurement Requests
- The funding document provides written assurance
from a responsible fiscal authority that adequate
funds are available for the proposed contract or
action.
4PR Package (Competitive Procurement)
- SAP Only
- Planning Purpose PR at a minimum (w/o estimated
value in NASA Data TabCompetition Sensitive) - Hard Copy Only
- Government Cost Estimate
- Funding Profile
- Government Estimate
- Evaluation Criteria
- Market Research
- Performance Work Statement/specifications
- Source List (GSA Only)
- SAP or Hard Copy
- Contract Type Recommendation
- NF 1707 Certificate
- Deliverables List
- GSFC Form 23-59 (Initiators Acquisition
Checklist) - When Applicable
- Security Requirements
- Government Furnished Property
- Procurement Library Info
5PR Package (Non-Competitive)
- SAP Only
- Planning Purpose PR (when funding is unavailable
at outset) - Hard Copy Only
- Government Cost Estimate
- Funding Profile
- SAP or Hard Copy
- Market Research
- Performance Work Statement/specifications
- Contract Type Recommendation
- NF 1707 Certificate
- Deliverables List
- GSFC Form 23-59 (Initiators Acquisition
Checklist) - When Applicable
- Security Requirements
- Government Furnished Property
- Procurement Library Info
- SUNS Certificate
- Risk Management Planning
- Sole Source Justification (draft JOFOC)
6Simplified Acquisition PR Package (Competitive
Procurement)
- SAP Only
- Purchase Requisition (w/o estimated value in NASA
Data TabCompetition Sensitive) - Hard Copy Only
- Government Cost Estimate
- Evaluation Criteria
- SAP or Hard Copy
- Performance Work Statement/specifications
- NF 1707 Certificate
- Deliverables List
- Market Research
- When Applicable
- Security Requirements
- Government Furnished Property
- GSFC Form 23-59 (Initiators Acquisition
Checklist) - SUNS Certificate
- Packaging, Marking Consignment Instructions
7Simplified Acquisition PR Package
(Non-Competitive)
- SAP Only
- Purchase Requisition
- Hard Copy Only
- Government Cost Estimate
- SAP or Hard Copy
- Performance Work Statement/specifications
- NF 1707 Certificate
- Deliverables List
- Market Research
- When Applicable
- Security Requirements
- Government Furnished Property
- GSFC Form 23-59 (Initiators Acquisition
Checklist) - SUNS Certificate
- Packaging, Marking Consignment Instructions
- Sole Source Justification
8Planning Purpose PR
- Required to Initiate PR Processing
- Used When Funding Unavailable at Initiation
- For Competitive Packages, the Planning PR should
cite - Estimated Value Is Competition SensitivePlease
call RA to Review Package in the text tab at the
Header Level in SAP - Include No Estimated Value in the NASA Data Tab
9Government Cost Estimate
- Required by FAR 7.304(b)
- Releasable to Public with Sealed Bidding (FAR
7.306(b)(2) - Used with Government Evaluation Presentation with
Negotiated Procurements (NFS 1815.370)
10Funding Profile
- Shows Estimated Phasing of Funds Availability
- Used By Offerors for Planning Schedules of Work
to be Performed - Usually Included in Competitive Solicitations
- Not Required When All Funds Are Available at Time
of Award
11Evaluation Criteria
- Used to Draft Sections L M of Solicitation
- Ensures Technical Personnel Participate in
Determining These Parts of Solicitation - With GSA requirements, the evaluation criteria is
delineated in the RFO letter
12Source List
- NASA Uses NAIS/FedBizOpps (web-based posting of
solicitation) for Most Mailings - Required for GSA Competitive Orders
- Used for Acquisition Planning Market Research
- May Be Used for Mailing of Construction Drawings
13Market Research
- Required by Part 10 of FAR
- Jointly Performed by Technical Procurement
- Necessary to Understand the Capabilities of the
Marketplace of Potential Vendors - Increased Emphasis due to NFS Change re Options
(1817.207-70) (document justifying the option
exercise at least to include the "technique" used
to satisfy the results of market research (FAR
10.001 (a)(3))
14Stating Requirements
- Statement of Work (SOW)/Specifications
- Functiondescribes a broad need
- Performancehow the item must work
- Essential physical characteristicsstates
required attributes - Defines Requirements to enable and encourage
vendors to supply commercial items or
nondevelopmental items - Largest Area of Post-Award Problems
15SOW/Specifications
- Do
- Write functional or performance specifications
- Use active verbs and clear, concise sentences
- Spell out acronyms or abbreviations the first
time used - Keep technical jargon to a minimum
- Use shall and will appropriately
- Have COTR/PR Initiator provide a SUNS certificate
prior to award - Do Not
- Use design or level-of-effort specifications
inappropriately - Include proprietary or restrictive information
- Gold plate your requirement
- Create or continue personal services arrangements
16Contract Type Recommendation
- Used for FAR 16.103(d) Determination Findings
- Ensures Technical Procurement Make Joint
Decision - Can Be Used w/ Options Determination (NFS
1817.207-70)
17NF 1707 Certificate
- Safety Health Checklist (formerly GSFC 23-59)
- Section 508/EIT Certificate
- Affirmative Procurement Certificate (Recovered
MaterialEPA Designated Products List) - 7120.5 Certificate No Longer Required
18Deliverables List
- Often Included in Statement of Work
- Used as Basis for Clause B.1 Deliverables List
- Can Be Used for Milestone Payment Determination
- Each Deliverable Must Be Described Elsewhere in
the Contract - For Major Efforts, Data Item Descriptions (DIDs)
Often Accompany
19GSFC Form 23-59 (Initiators Acquisition
Checklist)
- Contains Occupational Safety Health Checklist
- Used by Code 250 (Safety Environmental) to
Determine Clauses for Health Safety Plans, etc. - Form Available at http//gsfc-artemis.gsfc.nasa.
gov/210/procform.htm
20Security Requirements
- Used When National Security Considerations (e.g.
Classified Information) Used on the Contract - DD254 Form is the Designated Contract Attachment
- GSFC Security to Review Draft DD254
21Government Furnished Property
- Specific List of GFP Should be Included as
Solicitation/Contract Attachment - DF May Be Required Under FAR 45.302-1(a)(4)
- Potential Competitive Advantage and Cost and
Savings Issues to Address (FAR 45.201)
22Procurement Library Information
- Most Competitions Use Only QA Approach
- Where there is historical information, reference
documents, etc.provide these to all potential
offerors - Documents Can Be Uploaded Via NAIS/FedBizOpps
- Temporary Website Can Be Established for this
Purpose
23SUNS Certificate
- Standards Update Notification System
- Maintained by MSFC at http//standards.msfc.nasa.
gov/ - No Prescribed Format for Certificate
- Addresses Whether Specs, etc. are Latest Most
Current - Effective 2004
24Risk Management Planning
- Separate Risk Based Acquisition Management (RBAM)
Analysis Required When NPD 7120.5 Not Used - Required in Acquisition Plans/ASMs per FAR/NFS
7.105
25Justification for On-Site Performance (JOP)
- No Longer Used at GSFC
- Used for Space Planning Document at HQ
- Used When Performance is On-Site
26Packaging, Marking Consignment Instructions
- Used For Technical Deliverables
- Inspection and Acceptance Instructions specify
inspection, testing and other quality
requirements essential to ensure the integrity of
the supplies/services for all proposed contracts - Request package shall include
- Individual responsible for inspecting and
accepting deliverables (supplies/services) - Individual who will monitor the quality
assurance requirements - Place of acceptance
27Liquidated Damages Analysis
- Standard for Construction Contracts (FAR 36.206)
- May Be Used for supplies, services and research
and development as well - (FAR 11.5)
28Draft Sole Source Justification
- Technical Personnel Draft the JOFOC (FAR 6.302)
Required Above SAT - To Be Compliant with GSFC Procurement Circular
97-4 (and Attachments) - Now Required for GSA Sole Source Orders
- Simpler Format for Simplified Acquisitions (same
authorities apply)
29Preaward Acquisition Process
- Acquisition Planning
- Preparation of procurement request and package
- Submission of the Record of Procurement Request
Review to Industry Assistance - Synopsize (advertise) the requirement, when
applicable - Develop issue draft solicitation, address
comments, and finalize solicitation - Issue Solicitation (IFB, RFP, RFQ)
- Bid/Proposal/Quote Receipt
- Technical/cost/business evaluation
- Negotiations/discussions, if applicable
- Contract Award