MULTI YEAR TARIFF REGULATION

About This Presentation
Title:

MULTI YEAR TARIFF REGULATION

Description:

MULTI YEAR TARIFF REGULATION IN INDIA – PowerPoint PPT presentation

Number of Views:394

less

Transcript and Presenter's Notes

Title: MULTI YEAR TARIFF REGULATION


1
MYT Tariff Regulations
  • Presented By-
  • Navajyoti Martha

2
Why MYT in India
  • Incentivise efficiency improvement
  • Obviate regulatory uncertainty reduce
    regulatory risk
  • Less intrusive and avoids tendency to micro
    manage
  • Assists the utility to plan its business

3
MYT Framework
  • Determine framework for regulating the utilities
    for a period of time,
  • Principles of regulation of returns/profits of
    utilities
  • Principles of regulating individual cost and
    revenue elements
  • Degree of regulation on an on-going basis
  • Incentivise utilities to become more efficient in
    operations
  • Mitigate risks that are external to the utilities
  • Make the sector financially sound
  • Introduce efficient tariff design
  • Separates costs into controllable and
    uncontrollable components and treats them
    separately

4
Multi Year Tariff EA 2003 Tariff Policy
  • Section 61 states that the appropriate
    commissions, for determining the terms and
    conditions for the determination of tariffs shall
    be guided by multi-year tariff principles
  • MYT framework to be adopted for any tariffs from
    1 April 2006
  • The framework should feature a five year control
    period
  • The initial control period can be of 3 years for
    transmission distribution if deemed necessary
    on account of data inadequacies and other
    practical considerations
  • ERC can state assumptions in first control period
    and then as more reliable data becomes available,
    a fresh control period may be started

5
Multi Year Tariff Performance Norms
  • Where operations are below norms for several
    years, improvement trajectories may be recognized
    at relaxed levels and not desired levels
  • Suitable benchmarking studies must be conducted
    to establish desired performance standards
  • Separate studies may be carried out by each
    utility to assess the capital expenditure
    necessary to meet minimum service standards

6
Multi Year Tariff Control Period
  • Once revenue requirements are established at the
    beginning of the control period, the ERC should
    focus on regulation of outputs and not the input
    cost elements
  • Uncontrollable costs should be recovered speedily
    to ensure that future consumers are not burdened
    with past costs
  • Uncontrollable costs would include (but not
    limited to)
  • Fuel costs, cost on account of inflation, taxes
    and cess, variation in power purchase unit costs
    including on account of hydel thermal mix in case
    of adverse natural events

7
Case GERC (MYT Tariff) Regulations 2011
8
Scope of Regulation Extent of Application
  • Supply of electricity by a Generating Co to a
    Discom
  • Intra-state transmission of Electricity
  • Intra-state wheeling of electricity
  • Retail supply of electricity
  • If there are two or more distribution licensees,
    GERC can prescribe a tariff ceiling or cap
  • General framework for tariff determination and
    the Commission reserves a right to vary the
    parameters and procedures when facts and/or
    circumstances so warrant

9
Scope of MYT
  • ARR and expected revenue from tariff and charges
    for Genco, Transmission Licensee, Distribution
    wires and retail supply business
  • All the companies would file the MYT petition/
    applications separately

10
MYT Application/ Petition under MYT Regulations
2011
  • The MYT Petition comprises
  • Truing up for the year for 2009-10 for which
    audited results are available under GERC (Terms
    Conditions) Regulations and GERC (MYT)
    Regulations
  • Annual Performance Review for 2010-11
  • Multi-year ARR for the entire control period
    (2011-12 to 2015-16) with year wise details
  • Revenue from the sale of power at existing
    tariffs and charges projected revenue gap for
    the first year of the control period
  • Application for determination of tariff for the
    first year of the control period

11
MYT Application with Business Plan
  • All MYT Applications would be filed along with a
    Business Plan for the control period
  • Business Plan shall comprise (but not limited to)
    in accordance with the guidelines formats as
    prescribed by the ERC
  • Detailed category wise sales demand projections
  • Power procurement plan
  • Capital investment plan
  • Financing plan
  • Physical targets
  • Capital investment plan shall show on-going
    projects to be completed in the control period
    and new projects that will spill beyond the
    control period
  • ERC will approve the capital investment plan

12
MYT Application with Business Plan (2)
  • Discom will project the power procurement plan
    based on merit order despatch principles, RPPO,
    DSM, Energy Efficiency etc.
  • The Business Plan has to be approved by the ERC

13
Trajectory for certain variables
  • The MYT Application shall necessarily contain the
    trajectories for the following variables for the
    control period
  • O M expenses
  • Target Plant Load Factor
  • Distribution Losses
  • The companies may seek a mid-term review of the
    trajectory at the time of the mid-term review of
    the Business Plan

14
MYT Petition
  • From the first year of the Control Period and
    onward, the Petition will comprise
  • Truing up for FY 2010-11
  • Revenue from the sale of power at existing
    tariffs and charges for the ensuing year
  • Revenue gap for the ensuing year calculated based
    on ARR approved in the Tariff Order or MYT Order
    and truing up for the previous year
  • Application for determination of tariff for the
    ensuing year

15
MYT Mid Term review Petition
  • Truing up for previous year
  • Modification of the ARR for the remaining years
    of the control period with justification
  • Revenue from the sale of power at existing
    tariffs and the changes for the ensuing year
  • Revenue gap for the ensuring year calculated
    based on the ARR approved in the MYT Order and
    Truing up for the previous year
  • Application for the determination of tariff for
    the ensuing year

16
Truing Up
  • True up is of expenses and revenue during the
    control period
  • The approved forecast of ARR and Expected revenue
    from tariff is compared with the audited
    performance including pass through of
    uncontrollable factors
  • Review of compliance with ERC directives
  • ERC will then pass an order recording the
    approved aggregate gain and loss components of
    costs related to uncontrollable factors will be
    pass through
  • Once ERC notifies the regulations for submission
    of regulatory accounts, the application for
    tariff determination and truing up shall be based
    on the Regulatory Accounts

17
Controllable Uncontrollable Factors
  • Costs are categorised as controllable
    uncontrollable
  • Uncontrollable factors include
  • Force Majeure events
  • Change in law/ judicial pronouncements by govts
    or commission
  • Fuel price variation
  • Power purchase in accordance with FPPPA formula
  • Variation in consumer number or mix or quantities
    of electricity supplied to consumers/ under open
    access
  • Transmission loss
  • Variation in market interest rate
  • Taxes statutory levies
  • Taxes on income

18
Controllable Factors
  • Variation in capitalization on account of time or
    cost overruns or inefficiencies in implementation
  • Variation in interest financial charges on
    account of the above
  • Variation in technical an commercial losses of
    discoms
  • Variations in performance parameters
  • Variations in working capital requirements
  • Failure to meet performance standards
  • Variation in labour productivity
  • Variation in OM expenses
  • Variation in wires availability

19
Mechanisms to deal with gains/ losses
  • Uncontrollable Factors
  • Aggregate gain or loss on account of
    uncontrollable factors is a pass through in the
    next years ARR
  • Controllable Factors
  • In case of gain, one third is passed onto
    consumers and the remaining to be utilised at the
    discretion of the utility
  • In case of loss, one third of the loss may be
    passed on as additional charge over tariffs and
    balance absorbed by the utility

20
Determination of tariffs
  • In accordance with the GERC (Conduct of Business
    Regulations) 2004
  • GERC can suo moto or on basis of a petition
    determine the tariff including terms and
    conditions thereof

21
Determination of Generation Tariffs
  • Existing arrangements would continue but these
    arrangements would be converted to PPAs to be
    approved by ERC
  • PPAs must be signed with new generating stations
  • Where Discom has own generation, transfer price
    shall be determined by ERC

22
Determination of Transmission/ Distribution/
Retail Supply Tariffs
  • Process as specified in the regualtion
  • Filing of tariff
  • Notification in papers
  • Call for objections
  • Public Hearing
  • Tariff Order
  • Process of judicial review APTEL/ Supreme Court

23
Subsidy Mechanism
  • Govt has to pay in advance the amount to
    compensate the DISCOM/ affected party
  • No such direction of state govt would be
    operative if payment is not made in advance

24
Debt Equity Ratio
  • Debt equity ratio is 7030
  • Where equity is more than 30 the amount of equity
    for the purpose of tariff shall be 30 and the
    balance considered a loan
  • When equity is less than 30, actual equity is
    considered
  • In case of retirement or replacement of assets,
    the equity capital approved as mentioned above,
    shall be reduced to the extent of 30 (or actual
    if less than 30) of the original cost of the
    retired or replaced asset

25
Capital Cost Capital Structure
  • Capital cost is expenditure incurred or projected
    to be incurred including
  • Interest during construction and financing
    charges
  • Forex variations on the loan during construction
    upto commercial operation of project
  • Capitalized initial spares subject to ceiling
    rates
  • Capital expenditure will undergo a prudency check
    by ERC
  • Replacement of assets, RM, extension of life
    will be treated as follows
  • Net value of replaced assets OCFA AD CC
    where
  • OCFA Original capital cost of replaced assets
  • AD accumulated depreciation pertaining to
    replaced assets
  • CC Total consumer contribution pertaining to
    the replaced asset

26
Capitalization of Spares
  • The capital cost may include capitalised initial
    spares
  • upto 2.5 of original capital cost in case of
    coal based/lignite fired generating stations
  • upto 4.0 of original capital cost in case of gas
    turbine/combined cycle generating stations
  • upto 1.5 of original capital cost in case of
    hydro-generating stations and
  • upto 1.5 of original capital cost in case of
    Transmission Licensee and Distribution Licensee.

27
Additional Capitalisation Allowed
  • Additional capitalisation is allowed on account
    of
  • Un discharged liabilities within the original
    scope of work
  • On works within the original scope of work,
    deferred for execution
  • To meet award of arbitration and compliance of
    final and unappealable order or decree of a court
    arising out of original scope of works
  • On account of change in law
  • On procurement of initial spares included in the
    original project costs subject to the ceiling
    norm laid down in Regulation 35.6
  • Any additional works/services, which have become
    necessary for efficient and successful operation
    of a generating station or a transmission system
    or a distribution system but not included in the
    original capital cost
  • Provided that original scope of work is submitted
    in the Business Line

28
Consumer Contribution, Deposit Grant
  • Works after obtaining a part or all of the funds
    from the users in the context of deposit works
  • Capital works undertaken by utilising grants
    received from the State and Central Governments,
    including funds under RGGVY, APDRP, etc
  • Any other grant of similar nature and such amount
    received without any obligation to return the
    same and with no interest costs attached to such
    subvention

29
Return on Equity
  • Return on equity shall be computed on the paid up
    equity capital - the rate of 14 for Generating
    Companies, including hydro generation stations
    above 25 MW, Transmission Licensee, and
    Distribution Licensee
  • Provided that for Genco, Tranco, and Discoms, ROE
    shall be allowed on the amount of allowed equity
    capital for the assets put to use at the
    commencement of each financial year and on 50 of
    equity capital portion of the allowable capital
    cost for the investments put to use during the
    financial year
  • For the purpose of truing up for the utilites,
    ROE shall be allowed on pro-rata basis based on
    documentary evidence provided for the assets put
    to use during the year.
  • The premium raised by the utilities while issuing
    share capital and investment of internal
    resources created out of free reserve, if any,
    shall also be reckoned as paid up capital for the
    purpose of computing return on equity, provided
    such premium amount and internal resources are
    actually utilised for meeting capital
    expenditure.
  • Equity invested in foreign currency shall be
    converted to rupee currency based on the exchange
    rate prevailing on the date(s) it is subscribed.

30
Interest Finance Charges
  • The loans arrived at shall be considered as gross
    normative loan for calculation of interest on
    loan
  • Provided that interest and finance charges on
    capital works in progress shall be excluded
  • Provided further that in case of retirement or
    replacement of assets, the loan capital approved
    as mentioned above, shall be reduced to the
    extent of outstanding loan component of the
    original cost of the retired or replaced assets,
    based on documentary evidence.
  • The repayment for the year during the tariff
    period from FY 2011-12 to FY 2015-16 shall be
    deemed to be equal to the depreciation allowed
    for that year.

31
Interest Finance Charges (2)
  • The rate of interest shall be the weighted
    average rate of interest calculated on the basis
    of the actual loan portfolio at the beginning of
    each year applicable to the Generating Company or
    the Transmission Licensee or the Distribution
    Licensee
  • Provided that if there is no actual loan for a
    particular year but normative loan is still
    outstanding, the last available weighted average
    rate of interest shall be considered
  • The above interest computation shall exclude
    interest on loan amount, normative or otherwise,
    to the extent of capital cost funded by Consumer
    Contribution, Grants or Deposit Works carried out
    by Transmission Licensee or Distribution Licensee
    or Generating Company, as the case may be.
  • The utilities shall make every effort to
    re-finance the loan as long as it results in net
    savings on interest and in that event the costs
    associated with such re-financing shall be borne
    by the beneficiaries and the net savings shall be
    shared between the beneficiaries and the
    utilities in the ratio of 21.
  • Interest shall be allowed on the amount held as
    security deposit held in cash from Transmission
    System Users, Distribution System Users and
    Retail consumers at the Bank Rate as on 1stApril
    of the financial year in which the Petition is
    filed

32
Depreciation
  • The approved original cost of the project/fixed
    assets shall be the value base for calculation of
    depreciation
  • Depreciation shall be computed annually based on
    the straight line method at the rates specified
    by ERC
  • The remaining depreciable value as on 31st March
    of the year closing after a period of 12 years
    from date of commercial operation shall be spread
    over the balance useful life of the assets
  • Specifies that the utilities formed as part of
    transfer scheme shall be charged as per rates
    specified in these Regulations for a period of 12
    years from the date of the Transfer Scheme, and
    thereafter depreciation will be spread over the
    balance useful life of the assets
  • The salvage value of the asset shall be
    considered at 10 per cent of the allowable
    capital cost and depreciation shall be allowed
    upto a maximum of 90 per cent of the allowable
    capital cost of the asset

33
Depreciation (2)
  • Provided that in the case of hydro generating
    station, the salvage value shall be as provided
    in the agreement, if any, signed by the
    developers with the State Government.
  • Land other than the land held under lease and the
    land for reservoir in case of hydro generating
    station shall not be a depreciable asset and its
    cost shall be excluded from the capital cost
    while computing depreciable value of the asset.
  • In case of the existing projects, the balance
    depreciable value as on April 1, 2011, shall be
    worked out by deducting the cumulative
    depreciation as admitted by the Commission upto
    March 31, 2011, from the gross value of the
    assets.
  • In case of projected commercial operation of the
    asset for part of the year, depreciation shall be
    calculated based on the average of opening and
    closing value of asset, approved by the
    Commission
  • Provided that depreciation will be re-calculated
    during truing-up for assets capitalised at the
    time of Truing Up of each year of the Control
    Period, based on documentary evidence of asset
    capitalised by the applicant, subject to the
    prudence check of the Commission, such that the
    depreciation is calculated proportionately from
    the date of capitalisation.

34
Interest on Working Capital
  • Working capital is defined separately for
  • Generation
  • Coal/ lignite/ oil fired plants
  • Gas Turbine/ combined cycle plants
  • Hydro plants
  • Transmission
  • Distribution Wires Business
  • Retail Supply Business
  • Interest on working capital shall be allowed at a
    rate equal to the State Bank Advance Rate (SBAR)
    as on 1stApril of the financial year in which the
    Petition is filed.

35
Interest on Working Capital Generation for
Coal/ oil/ lignite plants
  • Working capital shall shall cover
  • Cost of coal or lignite for one (1) month for
    pit-head generating stations and one and a half
    (1½) months for non-pit-head generating stations,
    corresponding to target availability plus
  • Cost of oil for one (1) month corresponding to
    target availability plus
  • Cost of secondary fuel oil for two (2) months
    corresponding to target availability plus
  • Operation and Maintenance expenses for one (1)
    month plus
  • Maintenance spares at one (1) per cent of the
    historical cost escalated at 6 from the date of
    commercial operation plus
  • Receivables for sale of electricity equivalent to
    one (1) month of the sum of annual fixed charges
    and energy charges calculated on target
    availability
  • In case of own generating stations, no amount
    shall be allowed towards receivables, to the
    extent of supply of power by the Generation
    Business to the Retail Supply Business

36
Interest on Working Capital Generation gas /
combined cycle plants
  • Fuel cost for one (1) month corresponding to
    target availability factor, duly taking into
    account the mode of operation of the generating
    station on gas fuel and /or liquid fuel plus
  • Liquid fuel stock for fifteen (15) days
    corresponding to target availability plus
  • Operation and maintenance expenses for one (1)
    month plus
  • Maintenance spares at one (1) per cent of the
    historical cost escalated at 6 from the date of
    commercial operation plus
  • Receivables equivalent to one (1) month of
    capacity charge and energy charge for sale of
    electricity equivalent calculated on normative
    plant availability factor, duly taking into
    account mode of operation of the generating
    station on gas fuel and liquid fuel
  • In case of own generating stations, no amount
    shall be allowed towards receivables, to the
    extent of supply of power by the Generation
    Business to the Retail Supply Business

37
Interest on Working Capital Hydro Plants
  • Operation and maintenance expenses for one (1)
    month
  • Maintenance spares at one (1) per cent of the
    historical cost escalated at 6 from the date of
    commercial operation and
  • Receivables equivalent to one (1) month of fixed
    cost
  • Provided that in case of own generating stations,
    no amount shall be allowed towards receivables,
    to the extent of supply of power by the
    Generation Business to the Retail Supply
    Business, in the computation of working capital
    in accordance with these Regulations.

38
Interest on Working Capital Transmission
  • Operation and maintenance expenses for one month
    plus
  • Maintenance spares at one (1) per cent of the
    historical cost escalated at 6 from the date of
    commercial operation plus
  • Receivables equivalent to one (1) month of
    transmission charges calculated on target
    availability level
  • minus
  • Amount, if any, held as security deposits except
    the security deposits held in the form of Bank
    Guarantee from Transmission System Users.

39
Interest on Working Capital Distribution Wires
Business
  • Operation and maintenance expenses for one month
    plus
  • Maintenance spares at one (1) per cent of the
    historical cost escalated at 6 from the date of
    commercial operation plus
  • Receivables equivalent to one (1) month of the
    expected revenue from charges for use of
    Distribution Wires at the prevailing tariffs
  • minus
  • Amount, if any, held as security deposits under
    clause (b) of sub-section (1) of Section 47 of
    the Act from Distribution System Users except the
    security deposits held in the form of Bank
    Guarantees.

40
Interest on Working Capital Retail Supply of
Electricity
  • Operation and maintenance expenses for one month
    plus
  • Maintenance spares at one (1) per cent of the
    historical cost escalated at 6 from the date of
    commercial operation plus
  • Receivables equivalent to one (1) month of the
    expected revenue from sale of electricity at the
    prevailing tariffs
  • minus
  • Amount held as security deposits under clause (a)
    and clause (b) of sub-section (1) of Section 47
    of the Act from consumers except the security
    deposits held in the form of Bank Guarantees

41
Details about how other parameters are treated
  • Tax on income provisionally allow for the
    control period and then actuals after audited
    results are available
  • Rebate
  • Delayed Payment surcharge
  • Forex Rate Variation Utilities will be
    encouraged to hedge cost of hedging will be
    allowed

42
Applicability
43
  • Tariffs for Generation, Transmission and
    Distribution dealt with in separate session
  • Certain specific norms etc as spelt out in GERC
    MYT regulations follows

44
Generation Components of Tariff
  • Annual Fixed Charge
  • Energy (variable charges) for recovery of primary
    and secondary fuel cost

45
Generation Annual fixed charge
  • Depreciation
  • Operation Maintenance Expenses
  • Return on Equity
  • Interest and Finance Charges on Loan Capital
  • Interest on Working Capital
  • minus
  • Non-Tariff Income
  • Capital costs as specified in the MYT regulations

46
Generation Non-Tariff Income
  • Indicative list of various heads to be considered
    for Non-Tariff Income shall be as under
  • Income from rent of land or buildings
  • Income from sale of scrap
  • Income from statutory investments
  • Income from sale of Ash/rejected coal
  • Interest on delayed or deferred payment on
    bills
  • Interest on advances to suppliers/contractors
  • Rental from staff quarters
  • Rental from contractors
  • Income from hire charges from contactors and
    others
  • Income from advertisements, etc.
  • Provided that the interest earned from
    investments made out of Return on Equity
    corresponding to the regulated business of the
    Generating Company shall not be included in
    Non-Tariff Income.

47
Norms of Operations
  • Norms are specified for
  • Plant Availability 85 for full fixed cost
    recovery
  • Gross station Heat rate Existing and new
    stations
  • Secondary Fuel oil consumption - Existing and new
    stations
  • Coal-based generating stations 1.00 ml/kWh
  • Lignite-Fired generating stations except stations
    based on CFBC technology 2.00 ml/kWh
  • Lignite-Fired generating stations based on CFBC
    technology 1.25 ml/kWh
  • Trajectory determined separately for GSECL
    stations
  • Auxiliary Energy consumption - Existing and new
    stations
  • Transit and Handling losses
  • OM expenses
  • Norms for Hydro stations
  • Norms specified are ceiling norms

48
Distribution Norms for Wires Availability
  • The target Wires Network Availability for full
    recovery of Return on Equity for Wires Business
    shall be as under
  • Rural Areas 90 percent
  • Towns and cities 95 percent
  • Provided that the Commission may stipulate a
    trajectory for achieving the target Availability
    for Wires Business of the Distribution licensee
    as part of the Order on the Business Plan filed
    by the Distribution Licensee
  • Provided further that for every 1 percent
    under-achievement in Wires Availability vis-a-vis
    target availability, Rate of Return on Equity
    shall be reduced by 0.1
  • Provided further that for every 1 percent
    over-achievement in Wires Availability vis-a-vis
    target availability, Rate of Return on Equity
    shall be increased by 0.1.

49
Retail Supply Business
  • Components of Tariffs (will be dealt with in ARR
    session)
  • Amount received as cross subsidy surcharge will
    be deducted from ARR

50
  • Thank you
Write a Comment
User Comments (0)