Title: Treatment of Slaughterhouse Wastewater
1Treatment of Slaughterhouse Wastewater
- Mike Lawrence
- NDSU
- Fall 2006
2Overview
- Challenges
- Wastewater Parameters
- Treatment Options
- Process Modifications
- Typical On-site Treatment Options
- Design Problem
3Challenges of Slaughterhouse Wastewater
- Wastewater contains large amounts of blood, fat,
and hair - Wastewater is above municipal standards which
leaves two options on site treatment or pay to
be treated elsewhere - On site treatment with low capital and
maintenance costs is desirable
4Wastewater Parameters
- BOD approx. 1,000 to 4,000 mg/L
- COD approx. 2,000 to 10,000 mg/L
- SS approx. 200 to 1,500 mg/L
- High Oil and Grease content
- Possible high chloride content from salting skins
5Treatment Options
- Discharge to sewer to be treated by municipal
treatment plant - Land application of wastewater for irrigation
- Reduce amount of wastewater and/or concentrations
with the wastewater by changing the processes - On site Treatment
- Flow Equalization, Screening, Dissolved Air
Flotation, Primary Sedimentation - Aerobic Treatment
- Anaerobic Treatment
6In-Plant Modifications to Reduce Pollution
- Main goal should be to prevent product from
entering the waste stream and using the least
amount of water possible - Reduce the amount of water used, saves money in
two ways - Use high pressure and just enough
- Proper detergents
- Lower volume of water helps equipment
- Reuse as much water as possible
7Line Separation
- Separating the various waste streams as much as
possible - Sanitary lines should be discharged directly to
the city sewer - Grease waste streams and non grease waste streams
can help reduce treatment costs - Separate Blood line
8Blood Recovery
- Blood has ultimate BOD of 405,000 mg/L
- One head of cattle contains 49 lbs. of blood
which equals 10 lbs. BOD, compared to 0.2 lbs.
discharged per person per day - All blood should be recovered in a separate line
draining to a tank - Blood is then dried, commonly a continuous drier
is used - Profitable end product
9Stockpen Area
- Stockpen waste and other manure should be hauled
away as a solid - Cleaned periodically with as little water as
possible - Ideally this water would go to a separate tank
- From the tank it would be emptied into a truck
and land applied
10On-Site Treatment
- Costs of treating on site or letting the
municipality treat the waste should calculated - Maintenance and operation should be also put into
cost analysis - Flow equalization is usually a very good first
step in on-site treatment
11Hydrasieve
- BOD Removal 5-20
- TSS Removal 5-30
12Hydrasieve
Width (ft) Height (ft) Capacity (gpm) Estimated Price
2 5 75 5,200
3.5 5 150 6,400
4.5 7 300 8,000
5.5 7 400 10,000
6.5 7 500 12,000
7 7.3 1000 20,000
14 7.3 2000 40,000
21 7.3 3000 60,000
28 7.3 4000 80,000
35 7.3 5000 100,000
13SS and Grease Removal
- Grease removal could be very profitable
- Skimming operations
- 20 to 30 BOD removal
- 40 to 50 SS removal
- 50 to 60 grease removal
- Dissolved Air Flotation, DAF
- 30 to 35 BOD removal
- 60 SS removal
- 80 grease removal
14Skimming Operation (Primary Sedimentation)
- Detention time 1.5 to 2.5 hr
- Overflow Rate 800 to 1200 gal/ft2d
15Dissolved Air Flotation (DAF)
- Hydraulic Loading Rate
- 1.5 to 5.0 gpm/ sq. ft.
- Solids Removal Rate
- 1.0 to 2.0 lbs/hr/sq. ft.
16Anaerobic Lagoons
- Ideally the lagoon would be covered, odor gas
production contained, heat retention - Not well suited for colder climates
- Detention time 20 to 50 days
- BOD5 loading 200 to 500 lb/ac.-d
17Anaerobic Contact Reactor (ACR)
- Hydraulic Retention time 0.5-5 days
- Organic Loading rate of 1.0-8.0 kg COD/m3-d
Flocculator or
18Anaerobic Sequencing Batch Reactor (ASBR)
- HRT 6 to 24 hours
- SRT 50 to 200 days
- 98 removal with 1.2kgCOD/m3-d
- 92 removal with 2.4kgCOD/m3-d
- Possibly rates to 5 kgCOD/m3-d
- Effluent SS range between 50 100mg/L depending
on HRT
19Upflow Anaerobic Sludge Blanket (UASB)
- Proteins and fats may cause problems in formation
of granules. - Loading rates of 4-12 kg sCOD/m3-d
- Retention times of 7-14 hours
20Design Problem
- Flowrate120,000 gpd, 83 gpm, Max 300 gpm
- TSS1500 mg/L
- COD5000 mg/L
- sCOD3000 mg/L
- BOD52,000 mg/L
- Reduce levels to municipal levels and discharge
into sewer
21Screening
- Hydrasieve
- Use prior to flow equalization to save on pumps
and buildup in the tanks - Design for max flow of 300 gpm
- 4.5 by 7 foot model will handle flow
- Approximate cost of 8,000
22Primary
- Loading Rate of 600 gal/ft2-d
- Final Design
- 8 ft. wide, 25 ft. long, 10 ft. deep
- 8 ft. of weir w/ loading rate of 15,000 gpd/ft
- HRT 3 hours
10 ft
8 ft
25 ft
23Anaerobic Lagoon
- Covered for heat retention
- Side depth 8 feet
- Final Design 540 lb BOD5/ac-d
- HRT80 days
Plan View
400 ft
400 ft
24Anaerobic Contact Reactor
- Final Design HRT5 days
- Loading Rate 1.0 kg COD/m3-d
- Clarifier design based on 24m/d settling velocity
56 ft
16ft
10 ft
Anaerobic Contact Reactor, Completely Mixed
Clarifier
30 ft
Flocculator, Deglassifier
25Aerated Sequencing Batch Reactor
- Two reactors of same size
- Feed 8 hr, react 37.5 hr, settle 2 hr, drain .5
hr - Feed 8 hr, react 13.5 hr, settle 2 hr, drain .5
hr
24 ft
46 ft
Supernatant Drain 11.5 ft above bottom
Sludge waste at bottom
26Upflow Aerated Sludge Blanket Reactor
- Loading Rate of 10 kg sCOD/m3-d
- Two tanks, operated in parallel
- Diameter 4.5 m, Height 7 m,
2.5 m for gas storage
4.5 m
7 m
27Final Design
- Include Hydrasieve effectiveness and low
capital, O M costs - Upflow Anaerobic Sludge Blanket Reactor
- Tank is smaller than most of the others due to
high organic loading rate - Provides constant source of methane gas