Title: Creating Value Through Investment
1Creating Value Through Investment
- Indigenous Fuel is the Key to Energy Security of
Pakistan
2Pakistans Development Challenge
Population Below Poverty Line (income less than
USD 2 / day) _____________________ 60
Population Growth Rate _______________________ 2
GDP per Capita _____________ 980 USD
.and needs energy to meet this challenge
Source World Bank
3Pakistans Power Demand-Supply Forecast
Peak Demand
Average 3 Growth rate based on GDP Population
Growth
Supply
Average 2 Growth rate assumed
Daimer Basha Dam (4500 MW)
Thar Coal (1200 MW)
Only plants that have achieved or are likely to
achieve financial close included in the supply
forecast
4Impact of Energy Crisis
- Electricity shortage of more than 4500 MW and
frequent power cuts translate to
- Increasing dependence on expensive imported
energy puts a severe constraint on ability to pay - Import bill expected to increase to above USD 8
billion by 2020
Source State of the Economy Emerging from
Crisis 2008, Beacon House National University
publication, Pakistan Economic Survey 2009
5Wrong Fuel Choice
- Due to lack of indigenous natural gas shortages,
reliance on expensive imported RFO has increased
and exacerbated Circular Debt problem - If Coal had been used instead of RFO to make up
for indigenous natural gas shortage, it would
have reduced energy import bill by USD 600 M and
direct saving of USD 280 M to electricity
consumers - 50 reduction in use of RFO for power generation
would reduce Pakistans energy import bill by USD
900 M and benefit electricity consumers by USD
400 M
Source 1) State of Industries Report 2010,
NEPRA 2) Integrated Energy Plan
6Thar Coal Potential
- Thar Desert contains the worlds 7th largest coal
reserves -
175 Billion Ton 50 Billion TOE
2000 TCF Total Thar Coal Reserve
More than Saudi Arabia 68 times higher
than Iranian Oil Reserves
Pakistans total gas reserves
1 25 Thar Coal Reserve
Pakistans Power Generation Capacity in 2010
- Development of Block II alone would bring in
investment of USD 12 Billion - Entire Thar Coal Reserves can be used to generate
100,000 MW of electricity for over 200 years -
Location of Thar Coal Field
Source GSP data/report Energy equivalent is
based on Shenhua report/RWE
7(No Transcript)
8Public Private Partnership Alignment of
Incentives
- Sindh Engro Coal Mining Companys Vision
- To develop and execute technically and
commercially viable Coal Mining Project in Thar
Block II to generate electric power and bring
energy security to Pakistan based on indigenous
resource - Joint Venture (JV) Company Structure
- 40 Shares owned by the Government of Sindh (GoS)
- 60 Shares owned by Engro PowerGen Limited (EPL)
- Core expertise and responsibilities of each JV
Partner include - GoS would assist in timely availability of all
relevant data (previous and currently ongoing
studies), requisite approvals from Federal and
Provincial Governments and timely delivery of
infrastructure requirement for the Project
including roads and transmission line - Engro PowerGen will lead development, financing,
management and execution of the Project in a
professional and fast track manner - This Public Private Partnership reflects new
strategic focus of Government Engro to develop
Thar Coal reserves, raising the bar on how mega
project investment is planned, prioritized,
financed and delivered
Sindh Engro Coal Mining Company
9Bankable Feasibility Study Consultants
SECMC
RWE-Germany
SINOCOAL Intl. China
Bankable Feasibility Study Consultant
Hydrological Model GW Abstraction Consultant
-
- Environment and Social Impact Assessment
10Key Highlights Thar Coal Mining Feasibility
Study
- Bankable Feasibility Study (BFS) for Thar Block
II Coal Mining Project has been completed by
internationally renowned Consultants within
budget on August 31, 2010 as per target date - Technical, environmental and social viability of
the Project has been confirmed meeting all
international lenders standards (IFC/World Bank,
ADB etc.) - Salient features of the study for 6.5 Mt/a Mine
are as follows - Total Lignite reserve in Block II - 2 Billion
tons Exploitable Reserve - 1.57 Billion tons
which can support 5,000 MW for 50 years average
striping ratio is 6.21 - Required Overburden removal 140 Mm3 for initial
4 years 1277 Mm3 over 30 years - Total mine depth is 195 m (640 ft) cumulative
lignite seam thickness is 32 m - Average lignite quality calculated from 1618
samples is (Heating Value 11.6 MJ/kg ( 5000
Btu/lb) , Ash 7.3 , Moisture 47.48 , Sulphur
1.1 ) better than lignite being used in Greece
Germany for power generation - To keep the mine dry for operations, 37 Mm3/a
( 41 cusecs) of GW1 will have to be pumped out
in the initial years, which will reduce to 25
Mm3/a ( 28 cusecs) in later years - Shovel Truck (S/T) has been selected for
Lignite Mining due to its flexibility to achieve
mine scalability to 13 Mt/a 22.8 Mt/a in a cost
effective manner. Bucket Wheel Excavator (BWE)
Spreader system will be utilized for mine
expansion to 13 Mt/a 22.8Mt/a
11Key Highlights Thar Coal Mining Feasibility
Study
- Environment Social Viability Assessment
- No significant or unmanageable environmental
threats and social implications indicated - GW impact assessment and mitigation measures
finalized drawdown in 1st aquifer will be
monitored, re-infiltration may be done after 20
years if required - Only 2 villages will need to be relocated 1st
in 2025 and 2nd in 2035 - Mine power plant to be developed in parallel
- Phase 1 of the project will be development of a
6.5 million tons/annum coal mine in parallel with
development of 1200 MW Coal fired Power Plant.
Total Mining and Power Generation Projects Cost
is estimated to be 3 4 Billion USD - Subsequently, the coal mine will be scaled up to
22.5 Mt/a capacity and power plant capacity will
be increased to 4000 MW expeditiously. This will
require investment of over USD 12 Billion - 1st Phase of Coal Mine Power Plant construction
is targeted to start in 2012 and both Coal Mine
Power Plant will start operations by 2016 - GoS GoP to ensure timely provision of
infrastructure requirements including roads
network and transmission line
12Project Financing from Chinese Financial
Institutions
- Subsequent to Chinese Prime Ministers visit to
Pakistan in Dec, 2010, a Joint Energy Working
Group (JEWG) between Government of Pakistan
(GoP) Govt. of China has been formed to
shortlist the energy projects for technical and
financial assistance from Govt. of China - SECMC team presented details of Thar Block II
Coal Mining, Power Plant Infrasturucture
Projects to Sub-Energy Working Group (SEWG)
comprising Joint Secretary MoPNR1, Secretary
CEDD and DG Mines on 7-8 Jan, 2011. SEWG
unanimously agreed to forward the comprehensive
proposal for the Projects with their
recommendations to Energy Working Group (EWG) of
GoP - EWG has included these Projects in the list of
energy projects to be presented in JEWG meeting
scheduled to be held in March, 2011 in Beijing to
seek Govt. of China support for financing - SECMC has communicated to GoS / GoP financing
requirement and proposed structure for discussion
and approval at JEWG meeting - GoS to pursue EWG to ensure JEWG recommends to
Govt. of China to instruct Chinese Financial
Institutions for financing of Thar Projects as
per structure proposed by SECMC
13Benefits of Thar Coal Development
- To overcome the current energy crisis, Pakistan
has no other alternative except development of
indigenous energy resources - Thar investment will provide the following
benefits - Strategic energy resource that will guarantee
energy security to Pakistan in the decades to
come - Import substitution of expensive RFO or Natural
Gas Due to import substitution benefits, Thar
mining will act as a direct foreign exchange
earning sector and help lower the adverse impact
of imported fuel on Pakistans Trade Balance - Lower power tariff for Coal fired Power Plants as
compared to RFO based power tariff - Socio-Economic Development of Thar region
- Presently Thar District ranks lowest on all
socio-economic development indicators in Sindh - Development of indigenous coal mining industry
will lead to skilled job creation and transfer of
technology - Potential for future downstream industries in
Petro-chemical and Fertilizer products
Thar Coal is a fortune turning opportunity for
Pakistan
14Thank YOu
15Mine Equipment Shovel Truck
Dump Truck
Shovel
16Bucket Wheel Excavator Spreader
17Mine Power Plant Layout
Township
Power Plant
Stock Yard
MSF
Layout - 6.5 Mt/a Mine with Expansion to 22.8
Mt/a Mine
18Location of Aquifers in Block II