Title: Electricity Deregulation Next Stop, Transmission
1 Electricity Deregulation Next Stop,
Transmission
- Cheryl L. Runge
- Director, Market Development
- Economics Society of Calgary
- October 24, 2003
2Market Evolution Timeline
3NOT just different shades of grey!
4Why Restructure?
- One small step for man,
- one giant leap for mankind.
markets
the economy.
5Industry Model Post-Restructuring
Vertically Integrated Utility
Functional Separation
competitive forces
Generation
natural monopoly
Transmission
natural monopoly
Distribution
competitive forces
Retail
6Benefits
7Competitive Generation
- Incentive to build more efficient generation
costs lower than marginal unit - Options to build will weigh political risk (e.g.
Kyoto) - Options to build will consider consumer
wants/needs (e.g. consumer reliability
requirements, increasing demand for wind power) - Encourages innovation
8Generation Additions in 2003
- 570 MW of gas and 32 MW of Hydro were added go
the grid in the first half of 2003 - An additional 184 MW of gas and 76 MW of other
are expected by year end - 174 MWs are expected to be decommissioned by year
end - Net to grid total generation is expected to
increase to 11,202 MWs by end of year
9Alberta Generation Capacity
10Increase in AESO Participants
Groups
Aug 2003
Jan 2000
A (under 1MW) B (1-10 MW) C (over 10 MW and
Marketers) D (Retailer/ Self-Retailer)
38 21 62 110
9 12 21 6
Total
Date August 2003
11Load Response
- Consumers have demonstrated a response to prices
- Will choose to reduce consumption during tight
supply situations
12(No Transcript)
13Wholesale Market Prices
14Ancillary Services
- Compete to provide reserves to the AESO for
system reliability - Additional management schemes added to promote
efficiency while ensuring system security - AESO accountability to reduce costs
15Other Markets
- Forward Trading (Watt-ex)
- Bilaterals
- Net Settlement Instructions through AESO
- Contracts for Differences
- NGX swap
16Next Stop Transmission
17Albertas Electric Industry
- 20,000 km transmission
- Single control area of 660,000 km²
- B.C. Sask. Connections
- (785MW)
- over 130 generating units
- 8,570 MW system peak
- Over 200 market participants
- 10,515 MW internal capacity net to grid
- 600 MW added 1st half 2003
BC
Alta
Sask
18Transmission
- Backdrop
- New Transmission Policy
- Transmission infrastructure within Alberta to
support expanding economy - Stronger backbone grid
- Managed Congestion
- Transmission aligns to and supports inter
regional trade
19Transmission
- Design Considerations
- Sufficient to meet Alberta needs
- Sufficient to support new generation
- Supports imports and exports
20Transmission Planning Process
- Previous Planning Process
- 10 year transmission development plan
- Projects pursued once firm contracts are signed
with generators - Current Planning Process
- 20 Year conceptual transmission plan
- Navigant is assisting in the development of the
plan - paints the long term outlook for system
development - 10 Year transmission development plan
- refinement of the 20 year plan
- identifies projects that we will move towards
commitment for - Projects implemented in anticipation of
generation development
21Study Objectives
- 20 year outlook for system development
- primary focus on 500 kV development
- Better understanding the implications of
alternative generation and export scenarios on
the development of the transmission system - Preliminary evaluation of the impact on the
overall costs of generation and transmission
costs of the alternative generation and export
scenarios
22Generation Scenario Definition
- Scenario 1
- Heavy Fort McMurray development
- Scenario 2
- Heavy Edmonton area coal development
- Scenario 3
- Heavy southern Alberta area generation
- Brooks
- Combined-cycle near Calgary
- Wind
23Export/Load ForecastScenario Definition
- Exports
- Low -- opportunity service
- Medium -- 1,000 MW export to the Pacific
Northwest - High -- 2,000 MW export to the Pacific Northwest
- Load Forecasts
- Expected
- High
24(No Transcript)
25Navigant Conceptual Planning Study Preliminary
Conclusions
- Building transmission to facilitate the
competitive market for electricity is in the
long-term interest of consumers as it is expected
to lower the overall delivered cost of energy
within Alberta - Fort McMurray cogeneration and/or Edmonton Area
coal development is expected to result in lower
long term generation and transmission costs - The export of 1,000 MW, when combined with Fort
McMurray co-generation and/or Edmonton coal
generation development, results in lower long
term generation and transmission costs compared
to southern generation development without
exports -
26Navigant Conceptual Planning Study Preliminary
Conclusions (Contd.)
- Market simulations of the western interconnection
indicates that there is the potential for about
1,000 MW export from Alberta to the Pacific
North West and California - Alberta exports are more economical than gas
fired generation in the Pacific Northwest - Export of 2,000 MW would require further detailed
technical and market analysis within Alberta and
in the Western Interconnection
27Transmission
- Seams Considerations
- Inter-Regional Co-ordination
- FERC 888 Tariff terms are different than
Albertas injection - withdrawal model - Business Practices at the border could be better
aligned - Releasing on unused transmission
28In Summary
- Not just another shade of grey
- Competition in Generation
- Planning in Transmission
- Integrated Markets
- You can get there from here
29Contact Us
Current Prices and Market Statistics Historical
Reports News, Announcements Market and
Transmission Access www.aeso.ca
30(No Transcript)