Title: Containment 101
1Presenters Hari Floura Robert Mc Cafferty
December 2009
Solving the Challenges of Containing an Existing
Compression Process using Hard-wall and Flexible
Containment (A Work in Progress!)
2Presentation Plan
- Project History
- Existing Conditions
- Challenges
- Goals and Criteria
- Potential Solutions Issues
- Charging
- Compression
- Product Reconcilliation
- Drawings, Pictures/Video
- Mock Up Testing and Results
- Summary and lessons Learned
- Next Steps
- Questions
3Introduction
- Project Initiated at Barr, Pomona, NY Facility in
May 2008. - Stakeholders Involved To Discuss Need For
Containment Of Compression Processes at the Site.
- The Following Slides Summarize the discussion on
Compression Machine Containment Retrofit Design
Project.
4Existing Process Conditions
- Charging and compression of potent compounds in 4
separate manufacturing suites (Many Legacy
Processes) - Post hoists fitted with drum cones are used to
charge compression machines - Double lined drums are used for product
containers - PAPR/PPE/LEV/Work practice controls and Muller
caps are used to provide operator protection - The maximum concentration of API in the compounds
to be compressed 2.5 - OEL for API 40 Nanograms Per Meter Cubed (Eight
Hour Time Weighted Average) - Similar processes equipment at other sites
5Challenges
- Hand charging of compression machine feed hopper
prior to connection of the drum cone - Connection of product drum to compression machine
feed hopper - Drum changes
- Trouble shooting during the process
- Cleaning of compression machine and integrated
De-duster/product recovery and associated
containment solution - Equipment dimensions/layout varies in each
manufacturing suite
6Project Goal Criteria
- Goal Implement most effective containment
solution with minimal cost and least impact to
production schedules/productivity, and validation
- Criteria
- Reduce operator exposure to lt10 µg/m3
(Potentially lt1 µg/m3) Per Meter Cubed (Eight
Hour Time Weighted Average) - Use existing equipment with minimal modifications
- Able to be reversible for non-potent compounds
- Easily transferable
- all manufacturing suites and other sites
7Project Goals Criteria
- Criteria
- Cost of implementation to be low-moderate
- Operability of solution must allow the operators
to continue utilizing PPE procedures if necessary - Minimal impact to operability and clean-ability
of equipment/process - Applicable in Compounding as well as compression
(drum lift glove box).
8Solutions Discussed - Charging
- Use Split Butterfly Valves with drum liners to
charge press - Issues
- High cost to implement - large number of valves
required - Additional post hoist modifications needed for
charging of drums/containers fitted with split
valves and drum liners - Cleaning and storage of containers (If IBCs Used
instead of lined drums) - Decision Discard
- Buy new contained tablet press
- Issues
- New Contained Press would be as well as
validation costs to transfer to new presses for
existing processes. - Decision Discard
9Solutions Discussed - Charging
- Use flexible split valve to charge compression
machine - Issues
- High operational cost
- Unsatisfactory experience with drum sized
containers - Decision Discard
10Solutions Discussed - Charging
- Use bag over bag grooved contained transfer
system to charge - Issues
- Very high capital operational cost
- Safety concerns of operators working at an
elevated height to make connections - Decision Discard
- Integrate hard or soft wall isolator to feed port
- Issues
- Ergonomics and safety concerns of operators
working at an elevated height to interface drums
and charge machine - Potential requirement for major post hoist
modifications - Decision Discard
11Preferred Solution - Charging
Split Butterfly Valve technology was the
preferred solution. To reduce split valve
numbers, a hard wall isolator system interfaced
with the post hoist, using bag in bag out, to
allow interfacing of a drum. This solution would
require only one active and one passive valve.
(Approximately an 80 reduction in the number and
cost for SBVs total compounding/compression).
12Solutions Discussed Compression
- Hard Wall Containment Enclose machine in an
isolator. - Issues High cost, spatial requirements
ergonomics - Fit glove ports to access doors
- Issues Safety and ergonomics
- Investigate further
13Solutions Discussed Compression Containment
- Roll Up Rigid Isolator with flange connector to
doors - Issues Capital cost, cleaning, storage,
ergonomics - Soft Wall Containment Enclose Machine in an
Isolator or hybrid replace doors with soft wall
containment. - Issues No Major Issues Flexible containment
already successfully used at site. (Operational
costs, disposal)
14Solutions Discussed Product Reconcilliation
- Change vacuum bags in soft wall or rigid
isolators or down flow booths - Issues Capital Cost, space
- Use better collection bags with 0.2 micron
filters as well as police filter in front of HEPA
- Change using glove bag technology
- Use safe change disposable vacuum cartridges
- Issues Consumable costs and capital costs of
the vacuums
15Solutions Discussed Product Reconcilliation
- Connect dust collector pot with Lay Flat Tubing
Using Crimp Cut or SBV for desired containment - Issues Cost, Space, HVAC capacity
- Already in use at some sites
16Conclusion of Discussion
- Based on Stated Goal and Criteria Floura LLC was
tasked with Design and Development of The
Following Solutions Hard wall drum lift isolator
to allow bag in/out connection to split valve - Flexible enclosure interfaced to compression
machine doors - Drum lift isolator to allow bag in/out connection
to split valve.
17Conceptual Drawings
18Conceptual Drawings
19Conceptual Drawings
20Conceptual Drawings
21Mock-ups
Cone with connection for drum liner
Glove Ports
Flow Control Valve
22Mock-ups
23Surrogate Testing of Mockups
24Surrogate Testing Results - 1st Mock Up
25Conclusion of 1st Mock Up Testing
- Update design to incorporate operator comments
- Based on the experience test results, a report
was prepared to document these results and the
next steps - Prepare Manufacturing drawings and specification
drawings and issue for bid
26Sketches for Prototype
27Manufacturing Drawings/Sketches for Prototype
28Manufacturing Drawings for Prototype
29Prototypes
30Prototypes
31Testing
Short Video of Surrogate Testing Played at This
Point
32Surrogate Testing Results 2nd Mock Up
33Surrogate Testing Results - 2nd Mock Up
- Higher concentrations during sampling were caused
by - Holes in inner liner operator tore product bag
with stainless steel scoop when subdividing
lactose drums (prior to test start) - Bungee cord used to secure outer liner on post
hoist isolator failed - Operator removed tablet reject verification bag
(fitted to tablet reject chute) - couldnt see
through it - Leaks in the glazing panels on isolator
34Lessons Learned
- Drum Connecting Isolator
- Elastic cords not an effective solution to hold
liners in position. Band clamp system as
previously used will provide better liner seal - Vision into the enclosure needs to be improved
- Addition/larger vent filter required to prevent
pressurization of isolator - Glazing panels to be caulked gasket installed by
vendor was not effective
35Lessons Learned
- Flexible Enclosures
- Zippers on pass-in port not robust design needs
improvement or substitution - Integrated bungee would reduce setup time/need
for 2 operators. - Replace Allen screws on compression machine with
hand or thumb wheels quick disconnects - Improve reject verification, de-duster and
finished tablet hopper containment/access
36Drum Lift Glove Box with SBV Contained
Kikusui Tablet Press During 3rd Mock Up
373rd Mock Up
- Mock up ran for about 300 minutes
- 2 drum changes were performed as is reasonably
typical for a shift - 1 drum was full (about 80kg) and another nearly
empty (about 14kg) - An upper job was also initiated
- Feed frame was removed as well as several punches
- Most lessons learned from the 2nd mock up were
incorporated into this trial - Some were not due to cost constraints for the
trial but will be incorporated into final design
383rd Mock Up IH Testing Results
Placebo contained 67.4 lactose
39IH Sample Results Discussion
- The bag that was attached to the tablet de-duster
came off and some tablets spilled on the floor - They were vacuumed up immediately
- The operator tore a thumb in the tablet press
glove box while removing a thumb screw - The operator routinely uses latex and nitrile
gloves for the same function and cant remember
tearing those gloves ever before and they are
much thinner gloves - Some visible powder was observed on the SBV
during disconnection - Most likely more than usual as the drum was
removed while full of powder.
40Lessons Learned from the 3rd Mock Up
- Drum Lift Glove Box Isolator
- Handling small quantities could be done in small
drums or full drums with boxes in the bottom - Not likely to happen but this will make it easier
to reach - Sealing the inner and outer bag is a 2 person job
- Clamps for both could make it a one person job
- The inner bag can be difficult to seal to the
drum cone with a full drum of powder - Use clamps to hold the bag out of the way on the
bottom of the glove box instead of on the drum
cone
41Lessons Learned from the 3rd Mock Up
- Tablet Press Isolator
- 2 glove ports are needed on the left side for
cleaning - Better access is needed for lower punch access
- May be a perfect place for a glove bag
- Design so feed frame slides instead of lifting
out of the way - Better ergonomically and reduces the front
isolator door profile by 5 from over 13 ¾ to
about 8 ¾ - Seal the upper glove box chamber to the die table
so that both areas are separated - Need to see where and how large the pass through
needs to be based on the punch holder cases
42Current Status/Next Steps
- Drum lift Isolator and Compression Machine feed
funnel design with lessons learned modifications
has been sent out to bid - Modify the tablet press door Isolator/glove ports
design with lessons learned and perform ergonomic
testing before finalizing the design and sending
to bid. - Make final decision regarding soft wall around
existing doors or hybrid (some flexible with some
rigid containment) - Make improvements for containment/access for
de-duster, rejects and finished tablets hopper - Make business decision regarding product recovery
solution - Use cyclone with bag out collection or SBV
- Use contained HEPA vacuum (contained weighing/
disposal)
43Compression Containment Cost Considerations
- Assuming each is just as effective from a
containment and operational perspective a
business decision needs to be made between the 2
approaches - Each tablet press produces about 200-250 batches
per year - Soft wall containment tablet press isolator is
1300-1500 ea - A batch campaign averages 5 batches per campaign
so the average batch cost is 260-300 - Therefore the cost of consumables for the soft
wall will run 52,000-75,000 per press per year - Flanges and supports for the soft wall isolator
can also be estimated at 5,000 per press - Assuming a rigid isolator (glove box doors
interlock upgrades) costs between 50,000-75,000
per press - 50k DPP 1.1-1.6 years, ROI 80-106, IRR 64-97
- 75k DPP 1.7-2.4 years, ROI 50-78, IRR 37-61
- Assuming 5,000 in consumables for rigid isolator
hybrid - 50k DPP 1.2-1.9 years, ROI 57-84, IRR 51-82
- 75k DPP 1.9-2.8 years, ROI 34-61, IRR 29-52
44Status on Goals/Objectives/Criteria
- We believe we have developed a concept for the
most effective, least cost, least impact to
manufacturing and validation solution for our
processes (Met our target criteria) - Need to implement lessons learned with tablet
press isolator before finalizing design - Finalize designs receive bids present to
management for implementation - Mock up testing shows IH target of lt10µ/m3 with
the potential for 1 µg/m3 should be readily
achieved for final product
45Any Questions?
Contact Details
Robert Mc Cafferty North American IH Manager
Teva Pharmaceuticals, Inc. Tel 201 930
3411Fax 201-930-3316Mobile 201-312-7522 E-mail
rmccafferty_at_barrlabs.com
Hari Floura President Floura LLC. Tel
609-259-7136Fax 609-249-5541Mobile
908-896-1698 E-mail hari_at_flourallc.com