Containment 101 - PowerPoint PPT Presentation

1 / 45
About This Presentation
Title:

Containment 101

Description:

Solving the Challenges of Containing an Existing Compression Process using Hard-wall and Flexible Containment (A Work in Progress!) Compression Containment Cost ... – PowerPoint PPT presentation

Number of Views:128
Avg rating:3.0/5.0
Slides: 46
Provided by: njaihaOrg
Category:

less

Transcript and Presenter's Notes

Title: Containment 101


1
Presenters Hari Floura Robert Mc Cafferty
December 2009
Solving the Challenges of Containing an Existing
Compression Process using Hard-wall and Flexible
Containment (A Work in Progress!)
2
Presentation Plan
  • Project History
  • Existing Conditions
  • Challenges
  • Goals and Criteria
  • Potential Solutions Issues
  • Charging
  • Compression
  • Product Reconcilliation
  • Drawings, Pictures/Video
  • Mock Up Testing and Results
  • Summary and lessons Learned
  • Next Steps
  • Questions

3
Introduction
  • Project Initiated at Barr, Pomona, NY Facility in
    May 2008.
  • Stakeholders Involved To Discuss Need For
    Containment Of Compression Processes at the Site.
  • The Following Slides Summarize the discussion on
    Compression Machine Containment Retrofit Design
    Project.

4
Existing Process Conditions
  • Charging and compression of potent compounds in 4
    separate manufacturing suites (Many Legacy
    Processes)
  • Post hoists fitted with drum cones are used to
    charge compression machines
  • Double lined drums are used for product
    containers
  • PAPR/PPE/LEV/Work practice controls and Muller
    caps are used to provide operator protection
  • The maximum concentration of API in the compounds
    to be compressed 2.5
  • OEL for API 40 Nanograms Per Meter Cubed (Eight
    Hour Time Weighted Average)
  • Similar processes equipment at other sites

5
Challenges
  • Hand charging of compression machine feed hopper
    prior to connection of the drum cone
  • Connection of product drum to compression machine
    feed hopper
  • Drum changes
  • Trouble shooting during the process
  • Cleaning of compression machine and integrated
    De-duster/product recovery and associated
    containment solution
  • Equipment dimensions/layout varies in each
    manufacturing suite

6
Project Goal Criteria
  • Goal Implement most effective containment
    solution with minimal cost and least impact to
    production schedules/productivity, and validation
  • Criteria
  • Reduce operator exposure to lt10 µg/m3
    (Potentially lt1 µg/m3) Per Meter Cubed (Eight
    Hour Time Weighted Average)
  • Use existing equipment with minimal modifications
  • Able to be reversible for non-potent compounds
  • Easily transferable
  • all manufacturing suites and other sites

7
Project Goals Criteria
  • Criteria
  • Cost of implementation to be low-moderate
  • Operability of solution must allow the operators
    to continue utilizing PPE procedures if necessary
  • Minimal impact to operability and clean-ability
    of equipment/process
  • Applicable in Compounding as well as compression
    (drum lift glove box).

8
Solutions Discussed - Charging
  • Use Split Butterfly Valves with drum liners to
    charge press
  • Issues
  • High cost to implement - large number of valves
    required
  • Additional post hoist modifications needed for
    charging of drums/containers fitted with split
    valves and drum liners
  • Cleaning and storage of containers (If IBCs Used
    instead of lined drums)
  • Decision Discard
  • Buy new contained tablet press
  • Issues
  • New Contained Press would be as well as
    validation costs to transfer to new presses for
    existing processes.
  • Decision Discard

9
Solutions Discussed - Charging
  • Use flexible split valve to charge compression
    machine
  • Issues
  • High operational cost
  • Unsatisfactory experience with drum sized
    containers
  • Decision Discard

10
Solutions Discussed - Charging
  • Use bag over bag grooved contained transfer
    system to charge
  • Issues
  • Very high capital operational cost
  • Safety concerns of operators working at an
    elevated height to make connections
  • Decision Discard
  • Integrate hard or soft wall isolator to feed port
  • Issues
  • Ergonomics and safety concerns of operators
    working at an elevated height to interface drums
    and charge machine
  • Potential requirement for major post hoist
    modifications
  • Decision Discard

11
Preferred Solution - Charging
Split Butterfly Valve technology was the
preferred solution. To reduce split valve
numbers, a hard wall isolator system interfaced
with the post hoist, using bag in bag out, to
allow interfacing of a drum. This solution would
require only one active and one passive valve.
(Approximately an 80 reduction in the number and
cost for SBVs total compounding/compression).
12
Solutions Discussed Compression
  • Hard Wall Containment Enclose machine in an
    isolator.
  • Issues High cost, spatial requirements
    ergonomics
  • Fit glove ports to access doors
  • Issues Safety and ergonomics
  • Investigate further

13
Solutions Discussed Compression Containment
  • Roll Up Rigid Isolator with flange connector to
    doors
  • Issues Capital cost, cleaning, storage,
    ergonomics
  • Soft Wall Containment Enclose Machine in an
    Isolator or hybrid replace doors with soft wall
    containment.
  • Issues No Major Issues Flexible containment
    already successfully used at site. (Operational
    costs, disposal)

14
Solutions Discussed Product Reconcilliation
  • Change vacuum bags in soft wall or rigid
    isolators or down flow booths
  • Issues Capital Cost, space
  • Use better collection bags with 0.2 micron
    filters as well as police filter in front of HEPA
  • Change using glove bag technology
  • Use safe change disposable vacuum cartridges
  • Issues Consumable costs and capital costs of
    the vacuums

15
Solutions Discussed Product Reconcilliation
  • Connect dust collector pot with Lay Flat Tubing
    Using Crimp Cut or SBV for desired containment
  • Issues Cost, Space, HVAC capacity
  • Already in use at some sites

16
Conclusion of Discussion
  • Based on Stated Goal and Criteria Floura LLC was
    tasked with Design and Development of The
    Following Solutions Hard wall drum lift isolator
    to allow bag in/out connection to split valve
  • Flexible enclosure interfaced to compression
    machine doors
  • Drum lift isolator to allow bag in/out connection
    to split valve.

17
Conceptual Drawings
18
Conceptual Drawings
19
Conceptual Drawings
20
Conceptual Drawings
21
Mock-ups
Cone with connection for drum liner
Glove Ports
Flow Control Valve
22
Mock-ups
23
Surrogate Testing of Mockups
24
Surrogate Testing Results - 1st Mock Up
25
Conclusion of 1st Mock Up Testing
  • Update design to incorporate operator comments
  • Based on the experience test results, a report
    was prepared to document these results and the
    next steps
  • Prepare Manufacturing drawings and specification
    drawings and issue for bid

26
Sketches for Prototype
27
Manufacturing Drawings/Sketches for Prototype
28
Manufacturing Drawings for Prototype
29
Prototypes
30
Prototypes
31
Testing
Short Video of Surrogate Testing Played at This
Point
32
Surrogate Testing Results 2nd Mock Up
33
Surrogate Testing Results - 2nd Mock Up
  • Higher concentrations during sampling were caused
    by
  • Holes in inner liner operator tore product bag
    with stainless steel scoop when subdividing
    lactose drums (prior to test start)
  • Bungee cord used to secure outer liner on post
    hoist isolator failed
  • Operator removed tablet reject verification bag
    (fitted to tablet reject chute) - couldnt see
    through it
  • Leaks in the glazing panels on isolator

34
Lessons Learned
  • Drum Connecting Isolator
  • Elastic cords not an effective solution to hold
    liners in position. Band clamp system as
    previously used will provide better liner seal
  • Vision into the enclosure needs to be improved
  • Addition/larger vent filter required to prevent
    pressurization of isolator
  • Glazing panels to be caulked gasket installed by
    vendor was not effective

35
Lessons Learned
  • Flexible Enclosures
  • Zippers on pass-in port not robust design needs
    improvement or substitution
  • Integrated bungee would reduce setup time/need
    for 2 operators.
  • Replace Allen screws on compression machine with
    hand or thumb wheels quick disconnects
  • Improve reject verification, de-duster and
    finished tablet hopper containment/access

36
Drum Lift Glove Box with SBV Contained
Kikusui Tablet Press During 3rd Mock Up
37
3rd Mock Up
  • Mock up ran for about 300 minutes
  • 2 drum changes were performed as is reasonably
    typical for a shift
  • 1 drum was full (about 80kg) and another nearly
    empty (about 14kg)
  • An upper job was also initiated
  • Feed frame was removed as well as several punches
  • Most lessons learned from the 2nd mock up were
    incorporated into this trial
  • Some were not due to cost constraints for the
    trial but will be incorporated into final design

38
3rd Mock Up IH Testing Results
Placebo contained 67.4 lactose
39
IH Sample Results Discussion
  • The bag that was attached to the tablet de-duster
    came off and some tablets spilled on the floor
  • They were vacuumed up immediately
  • The operator tore a thumb in the tablet press
    glove box while removing a thumb screw
  • The operator routinely uses latex and nitrile
    gloves for the same function and cant remember
    tearing those gloves ever before and they are
    much thinner gloves
  • Some visible powder was observed on the SBV
    during disconnection
  • Most likely more than usual as the drum was
    removed while full of powder.

40
Lessons Learned from the 3rd Mock Up
  • Drum Lift Glove Box Isolator
  • Handling small quantities could be done in small
    drums or full drums with boxes in the bottom
  • Not likely to happen but this will make it easier
    to reach
  • Sealing the inner and outer bag is a 2 person job
  • Clamps for both could make it a one person job
  • The inner bag can be difficult to seal to the
    drum cone with a full drum of powder
  • Use clamps to hold the bag out of the way on the
    bottom of the glove box instead of on the drum
    cone

41
Lessons Learned from the 3rd Mock Up
  • Tablet Press Isolator
  • 2 glove ports are needed on the left side for
    cleaning
  • Better access is needed for lower punch access
  • May be a perfect place for a glove bag
  • Design so feed frame slides instead of lifting
    out of the way
  • Better ergonomically and reduces the front
    isolator door profile by 5 from over 13 ¾ to
    about 8 ¾
  • Seal the upper glove box chamber to the die table
    so that both areas are separated
  • Need to see where and how large the pass through
    needs to be based on the punch holder cases

42
Current Status/Next Steps
  • Drum lift Isolator and Compression Machine feed
    funnel design with lessons learned modifications
    has been sent out to bid
  • Modify the tablet press door Isolator/glove ports
    design with lessons learned and perform ergonomic
    testing before finalizing the design and sending
    to bid.
  • Make final decision regarding soft wall around
    existing doors or hybrid (some flexible with some
    rigid containment)
  • Make improvements for containment/access for
    de-duster, rejects and finished tablets hopper
  • Make business decision regarding product recovery
    solution
  • Use cyclone with bag out collection or SBV
  • Use contained HEPA vacuum (contained weighing/
    disposal)

43
Compression Containment Cost Considerations
  • Assuming each is just as effective from a
    containment and operational perspective a
    business decision needs to be made between the 2
    approaches
  • Each tablet press produces about 200-250 batches
    per year
  • Soft wall containment tablet press isolator is
    1300-1500 ea
  • A batch campaign averages 5 batches per campaign
    so the average batch cost is 260-300
  • Therefore the cost of consumables for the soft
    wall will run 52,000-75,000 per press per year
  • Flanges and supports for the soft wall isolator
    can also be estimated at 5,000 per press
  • Assuming a rigid isolator (glove box doors
    interlock upgrades) costs between 50,000-75,000
    per press
  • 50k DPP 1.1-1.6 years, ROI 80-106, IRR 64-97
  • 75k DPP 1.7-2.4 years, ROI 50-78, IRR 37-61
  • Assuming 5,000 in consumables for rigid isolator
    hybrid
  • 50k DPP 1.2-1.9 years, ROI 57-84, IRR 51-82
  • 75k DPP 1.9-2.8 years, ROI 34-61, IRR 29-52

44
Status on Goals/Objectives/Criteria
  • We believe we have developed a concept for the
    most effective, least cost, least impact to
    manufacturing and validation solution for our
    processes (Met our target criteria)
  • Need to implement lessons learned with tablet
    press isolator before finalizing design
  • Finalize designs receive bids present to
    management for implementation
  • Mock up testing shows IH target of lt10µ/m3 with
    the potential for 1 µg/m3 should be readily
    achieved for final product

45
Any Questions?
Contact Details
Robert Mc Cafferty North American IH Manager
Teva Pharmaceuticals, Inc. Tel 201 930
3411Fax 201-930-3316Mobile 201-312-7522 E-mail
rmccafferty_at_barrlabs.com
Hari Floura President Floura LLC. Tel
609-259-7136Fax 609-249-5541Mobile
908-896-1698 E-mail hari_at_flourallc.com
Write a Comment
User Comments (0)
About PowerShow.com