Transcript and Presenter's Notes

Title: Construction Management


1
Euclid Corridor Transportation Project
  • Construction Management
  • Mac McOmber

2
Team Organization
  • Flexible team concept - size varied as dictated
    by work activities
  • Staffing - Minimum 3 members, Maximum 23
  • Team comprised of 7 different firms
  • Washington Division of URS, Lead
  • GCRTA, Resident Engineers
  • ODOT, C03 Team
  • Ralph Tyler Companies, Subcontractor
  • Quality Control Inspection Services,
    Subcontractor
  • Dalia Consultants, Subcontractor
  • Regency Construction Services, Inc, Subcontractor
  • 25 Disadvantaged Business Enterprise Goal

3
Team Organization
  • Teams aligned to Contracts
  • C01 Transit Zone, based at WD-URS office
  • C02 Public Square to Innerbelt, based at WD-URS
    office
  • C03 Innerbelt to E79th, Based at E55th field
    office
  • C04 E79th to Windermere, based at E105th
    Chester field office
  • C05A F I of Stations Project wide, based at RTA
    office
  • C05B Project wide Signals, Communication and
    Power, based at RTA office
  • C06 Hayden/Central Maintenance Facilities
    upgrades, based at Hayden Garage
  • Support/Admin Personnel, Based at WD-URS office

4
Team Organization
Construction Manager
QA/QC Manager
38-C01 R.E.
Inspectors
38-C02 R.E.
Inspectors
Safety Manager
38-C03 R.E.
Inspectors
Scheduling Asst.
38-C04 R.E.
Inspectors
Office Engineer
38-C05A R.E.
Asst. Office Eng.
38-C05B R.E.
38-C06 R.E.
Admin. Asst.
5
Design Phase Services
  • Coordination - Utilities
  • Design review (60, 90, 100)
  • Value Engineering / Constructability
  • Project Controls
  • Baseline Schedule Development
  • A/E Unit Price Estimate Review
  • Project Administrative Setup

6
Construction Services
  • Coordination Utilities, Public Other Projects
  • Construction Inspection
  • Safety Quality Assurance Oversight of the
    Contractor programs
  • Project Controls
  • Scheduling
  • Estimating / Change Orders
  • Document Control

7
Challenges
  • Team Alignment
  • Varied firms, one process
  • Interface/Support Points
  • City of Cleveland vault project
  • Cleveland Water Department 42 water line
    replacement project
  • Water Pollution Control sewer replacement project
  • Cleveland Public Power betterments
  • Cleveland Clinic construction
  • NEORSD projects
  • Speech and Hearing Center
  • New CVS building
  • Utility upgrades/conflicts
  • DEOG ATT Adesta
  • CEI Time Warner Cavalier
  • Forest City SBC Cleveland Thermal

8
Challenges
  • Stakeholders
  • Keep access to allow business to operate
  • Small renovation projects (surprises)
  • Functions
  • Tree lighting ceremony
  • 100 year anniversary of Cleveland Water
    Department
  • Ingenuity festival
  • St. Patricks Day parade
  • 4th of July Concert on the Square

9
Success
  • Safety
  • Project Recordable Rate 2.26
  • Project Days Away Rate of 1.81
  • Two Interim Openings, on schedule
  • No Anticipated litigation
  • All claims settled to date
  • Grand Opening Ceremony slated for 10/25/2008, on
    schedule