Title: Interstate 435 and Front Street Interchange Improvements
1Interstate 435and Front Street Interchange
Improvements
- This presentation will probably involve audience
discussion, which will create action items. Use
PowerPoint to keep track of these action items
during your presentation - In Slide Show, click on the right mouse button
- Select Meeting Minder
- Select the Action Items tab
- Type in action items as they come up
- Click OK to dismiss this box
- This will automatically create an Action Item
slide at the end of your presentation with your
points entered.
2Project Location
3Purpose and Need for this project
- To provide safety improvements at the northbound
and southbound exits from I-435, within the
interchange on Front Street and the entrance ramp
onto southbound I-435.
4(No Transcript)
5Initial Concepts We Reviewed
Single Point (SPUI) Half-Cloverleaf
Roundabout Tight Urban Diamond (TUDI)
6Single Point (SPUI)
7Problems with a Single Point design
- Required extensive reconstruction of I-435.
- Costs for additional right-of-way and
construction were very high, about31 million. - We had concerns about how long it would take
trucks to clear such a large intersection. - Based on 2002 estimates.
8Half-Cloverleaf
9Problems with a Half- Cloverleaf design
- Required large amounts of new R/W.
- Costs for additional right-of-way and
construction were very high, about37 million. - We had concerns about the trucks being able to
accelerate from the loop ramps onto the freeway. - Based on 2002 estimates.
10 11Problems with a Roundabout design
- Did not perform as well as other alternatives.
- We had concerns about the operation of the trucks
in the roundabout (two trucks likely would not
enter a roundabout at the same time, reducing
capacity). - Costs for additional right-of-way and
construction, about 10 million. - Based on 2002 estimates.
12Tight Urban Diamond (TUDI)
13Problems with a Tight Urban Diamond design
- Required considerable reconstruction of I-435.
- Did not work as well as the SPUI or
half-cloverleaf. - Costs for additional right-of-way and
construction were high, about28 million. - Based on 2002 estimates.
14Initial Design
15Initial Design
- The existing interchange is very similar to a
TUDI, with I-435 over Front Street. - The initial preliminary design included
- Adding lanes to the off ramps with double and
triple left turn lanes. - Adding lanes to Front Street between Universal
and Corrington with traffic lanes behind the
bridge piers.
16Problems with the initial design
- The life of the capacity improvements were
limited. This design would probably fail within
10 to 15 years. - The Levels of Service were D, E and F.
- Costs for additional right-of-way and
construction were still somewhat high, about 11
to 12 million. - This design has 45 conflict points within the
entire interchange. - Based on 2005 estimates.
17Conflict Point Diagram - TUDI
18Problems with the initial design
- Triple left turn lanes were needed for the
northbound to westbound movement. This is not
desirable with 11 trucks during peak hour. (Off
peak has about 30 trucks.) - Seven lanes were needed under the bridges,
requiring construction of lanes and retaining
walls behind the bridge piers in existing sand
fills. This would be difficult to build. - The trucks required large turning radii to
achieve capacity improvement. This limited
vehicle storage between the signals.
19A Practical Design Solution
- A Diverging Diamond Interchange or DDI
20Diverging Diamond Design
Link to DDI overhead video Link to one of the
drive thru videos
21Advantages of using a DDI at this Location
- The DDI doubles the capacity of the left turn
lanes and eliminates the need for the triple left
turn. The double left turn should be safer than a
triple with high truck volumes. - Levels of Service are A, B and C.
- This design reduces the number of lanes required
under the bridge to four, eliminating the need to
build retaining walls.
22Advantages
- This also reduces the number of lanes needed on
Front Street beyond the interchange. - This DDI design has more storage room between the
ramp signals. - (550 vs 350)
- This design will also provide better sight
distance. Drivers on the ramps dont have to
look through bridge columns to see on-coming
traffic.
23Advantages
- It incorporates roadway features which calm
traffic and reduce speeds while maintaining
capacity. This should result in fewer and less
severe crashes. - Although wrong way entry into opposing lanes is
possible, wrong way entry onto the ramps and the
interstate will be almost eliminated. - The DDI has 21 conflict points compared to 45
with the initial design.
24Conflict Point Diagram - DDI
25Advantages
- The smaller ramp intersections mean vehicles will
have shorter clearance times resulting in less
exposure and safer conditions. - The DDI design has reduced the cost of the
project.
26Estimated Costs Initial DDI
- Construction
- MoDOT 6,763,000 4,097,000
- Kansas City 103,000 71,000
- Right of Way
- MoDOT 1,823,000 625,000
- Kansas City 2,045,000 667,000
- Utility Relocations
- MoDOT 600,000 312,000
- Total Costs 11,334,000 5,772,000
- Based on 2005 estimates.
27Disadvantages of a DDI
- Driver expectations.
- We need more extensive public involvement.
- Pedestrians have to cross free-flowing ramps (or
the crossings need to be signalized as at this
location). - There is very limited accident history available.
- We need additional signing, lighting and pavement
markings.
28 DDI
Length of Construction
TUDI
Two construction seasons
29Conclusion
- The DDI will improve safety and capacity of the
existing interchange, at less cost and with a
shorter construction schedule. - It will also provide valuable information on
function and safety that will allow MoDOT and
FHWA to determine if use of the DDI design at
other locations is feasible.