QUIZ 1 - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

QUIZ 1

Description:

QUIZ #1 10 Minutes Construction Engineering 221 Construction Contracts Construction Contract Types What are the two main divisions of construction contracts? – PowerPoint PPT presentation

Number of Views:53
Avg rating:3.0/5.0
Slides: 19
Provided by: publicIa3
Category:
Tags: quiz

less

Transcript and Presenter's Notes

Title: QUIZ 1


1
QUIZ 1
  • 10 Minutes

2
Construction Engineering 221
  • Construction Contracts

3
Construction Contract Types
  • What are the two main divisions of construction
    contracts?

4
First Main Division
  • Competitive bid contracts
  • Lump-sum
  • Unit-price

5
Second Main Division
  • Negotiated contracts
  • Lump-sum
  • Unit-price
  • Cost-plus-fee (most common w/ negotiated)

6
Award of Competitive-Bid Contract
  • Award contract to the lowest responsible bidder
  • What is meant by the term lowest responsible
    bidder?

7
lowest responsible bidder
  • Lowest bidder whose offer best responds in
    quality, fitness and capacity to fulfill the
    particular requirements of the proposed work and
    with the necessary qualifications to complete the
    job in accordance with the terms of the contract.
    In open competitive bidding by public and
    private owners the bid will go to the lowest
    responsible bidder.

8
COST-PLUS-FEE CONTRACTS
  • Contract value is NOT guaranteed
  • Used when design and drawings are NOT complete
  • Owner pays reimbursable costs plus a fee
  • Fee is usually a percentage of total
    reimbursable cost (2 to 6)

9
Reimbursable Costs
  • Defined by very detailed contract language
  • Subcontract bidding and letting procedures
  • Definitions of what types of costs can be
    reimbursed
  • Payments to Subcontractor per subcontract
  • Contractors field labor, material and equipment
    costs
  • Definitions of what types of cost that will NOT
    be reimbursed
  • Contractors main office overhead and staff
  • Salaries of contractors officers

10
Contractors Fee in Cost-Plus Contract
  • Determined by taking into account
  • Degree of risk
  • Nature and complexity
  • Geographical location
  • Equipment and manpower requirements
  • Estimated construction time
  • Final fee usually negotiated to be competitive
    (what will the market bear)

11
Cost Reimbursable Contracts
  • CostPlus-Fee as a Percentage-of-Cost
  • Fee may be on a sliding scale (smaller percentage
    as the cost of the project increases)
  • Fee of 10 for contract values lt50,000
  • Fee of 5 for contract values 50,000 to 500,000
  • Fee of 3 for contract values gt500,000

12
Cost Reimbursable Contracts (cont.)
  • Cost-Plus-Fixed-Fee Contracts
  • Incentive contracts (bonus-penalty)
  • Share of the cost savings up to a maximum
  • Bonus for each day finished early, or penalty for
    each day finished late
  • Guaranteed Maximum Cost (upset price)

13
Contact Documents
  • The construction contract is comprised of a
    number of different documents. Most construction
    documents include
  • Invitation to bid
  • Instructions to bidders
  • General Conditions
  • Supplementary Conditions
  • Technical Specifications
  • Drawings
  • Addenda
  • Proposals
  • Bid Bond
  • Agreement
  • Performance bond
  • Labor and material payment bond

14
Construction Contract Conflicts
  • What if there is a conflict between the drawing
    and the specifications? Which is considered the
    governing document?
  • And what if a construction requirement is found
    in only the drawings and not in the
    specification? Is it still a requirement?

15
Retainage
  • What is retainage and why is it necessary?

16
Retainage or Retention
  • A percentage of the payment to the contractor
    that is withheld each month
  • Usually is 10
  • Owner may reduce below 10 after SUBSTANTIAL
    COMPLETION
  • Paid by owner to contractor after FINAL
    COMPLETION of the project
  • Serves as an incentive for contractor to complete
    ALL work per contract

17
Other Contractual Terms
  • Substantial Completion
  • Beneficial Occupancy of the project
  • Warranty Period
  • Contact time
  • Calendar days vs. working days
  • time is of the essence

18
Other Contractual Terms
  • Liquidated Damages
  • Used as a PENALTY for late completion
  • Used in lieu of a determination of actual damages
    suffered by the owner
  • Must be a REASONABLE penalty based on a forecast
    of actual damages the owner would suffer if the
    contractor is in breach of contract by finishing
    late
Write a Comment
User Comments (0)
About PowerShow.com