Equipment planning - PowerPoint PPT Presentation

1 / 48
About This Presentation
Title:

Equipment planning

Description:

EQUIPMENT PLANNING Dr. A.K. Jain EQUIPMENT PLANNING A Good equipment planning includes careful Attention to fixed and movable equipments that will be needed in ... – PowerPoint PPT presentation

Number of Views:1211
Avg rating:3.0/5.0
Slides: 49
Provided by: imsmbahaC
Category:

less

Transcript and Presenter's Notes

Title: Equipment planning


1
Equipment planning
  • Dr. A.K. Jain

2
Equipment planning
  • A Good equipment planning includes careful
    Attention to fixed and movable equipments that
    will be needed in operations
  • The lack of planning will result
  • Wastage of millions of rupees
  • Reduced Operational efficiency
  • Lower standards of patient care

3
Whom responsibility?
  • (a) It is the responsibility of Hospital
    consultant (OR Hospital Administrator in case H.
    consultant not engaged) to determine all the
    items of equipments necessary, then write their
    specification, recommended bids (tender)
    purchase according to hospitals policy.
    (Expendable, non-expendable capitals
    equipments)
  • (b) The Architect is responsible for the Built in
    equipments.

4
When in which stage equipments Planning is done
?
  • (i) Equipments planning is done Early in design
    dev. Stage. This planning involves.
  • (a) A series of Meetings of
  • Medical staff
  • HODs
  • Other Staffs
  • to discuss the needed equipments

5
  • (b) Preparing Room by Room Equipment List
  • (c) Review of this list by
  • Administrator
  • Medical staff
  • Departmental heads
  • Another detailed Equipments planning is necessary
    at final FURNISING while actually EQUIPPING the
    hospitals

6
Designing of Equipments
  • A set of black line points of working Drawing
    (Floor Plans only) should be secured from
    Architect and marked up in advance all Gross
    equipments shown to scale identified
  • It is done in designing phase

7
Nature of equipping the hospitals
  • It is an extensive and exhaustive work because it
    involves not only the degree but a variety of
    technical knowledge.
  • There are innumerable expandable items, which
    should be procured and stoked in sufficient
    quantities.

8
  • There is no preformed procuring system in the new
    hospitals (if compared with an old existing
    running hospital)
  • The problem is compounded by installing
    equipments apart from purchasing them. Important
    considerations are-
  • Timing of delivery
  • Warehousing
  • Unpacking
  • Assembling

9
Imported equipments
  • creates more complex problems like
  • (a) Needs, approvals and licenses.
  • (b) Bureaucratic hurdles needed to be crossed
  • (c) costly items
  • (d) Lead time is longer.
  • (e) Delay can cause losses in millions.

10
Costing
  • In a Modern General Hospital the equipping cost
    is around 40 of total project cost.
  • (a) 20 is invested on mechanical and electrical
    installations
  • (b) 20 is invested on medical equipments

11
Types of equipments
  • (a) Built- in Equipments
  • (b) Depreciable equipments (Non-expandable)
  • (c)Non-depreciable equipments (Expandable)
  • (d) Capital Equipments

12
Built in Equipments
  • Its the Architects Responsibility
  • Included in construction contracts
  • List includes
  • Cabinets counters in
  • Pharmacy
  • Laboratory
  • Other parts of hospitals

13
  • Fixed kitchen Equipments.
  • (lines) (Channels)
  • Elevators
  • Dumb waiters
  • Sterilizers, Boilers
  • Incinerators.
  • Air Conditioning/Deep freezers
  • Surgical lighting etc

14
(B) Non-Expendable Equipments
  • OR Depreciable Equipments
  • Def The Equipments that have a life of 5 yrs of
    gt 5 yrs are k/a Non-Expendable equipments
  • These equipments are not purchased through
    construction contracts
  • These large items of furniture and Equipments
    have a reasonable fixed location in the hospital
    building but are capable of being moved

15
Examples of depreciable equipments
  • (i) Surgical Apparatuses
  • (ii) Diagnostic Therapeutic Equipment
  • (iii) Lab pharmacy Equipment .
  • (iv) Office Equipment
  • Typewriter, Intercoms
  • Computers/Electronic exchanges
  • (v) General use surgicals
  • Refrigerator
  • Physiotherapy equipments
  • Suction machines

16
  • (vi) Diagnostic and Therapeutic Eqpts. Like
  • Sw diathermy, X-Ray machine
  • Cutlery, ECG machine
  • Respirators, Incubators
  • Monitoring Eqpts
  • Ultra sound machine
  • Respirators

17
(c) Expendable (non-depreciable) equipments
  • These Equipments have life span lt 5 yrs
  • Recurring in use low cost equipments.
  • These equipments are purchased through other than
    construction contracts.
  • Examples are
  • Kitchen utensils
  • Chinaware
  • Table ware
  • Surgical instruments
  • Catheters
  • Linen, sheets, Blankets
  • Lamps, Wastebins etc.

18
Preparing the equipment list
  • The list of expandable and non-expandable items
    is prepared by H. consultant H. Administrator
  • Steps in preparing the list are
  • (i) consider each Room as a separate Eutily in
    the plane
  • (ii) Make a compressive Room by Room eqpments

19
List with additional items required
  • Detailed specifications must be given
  • During design stage
  • Should test the space needed for each item of the
    eqpts on the list in drawings

20
Important consideration
  • Hospital interest lies in purchasing minimum
    needed Equpts Hospital consultant can help in
    it.

21
Selecting the equipments
  • Selection of Technical, Scientific and Medical
    Eqpts requires careful Analysis of the needs of
    each department and conscientions study that will
    result in selection of needed equpts.
  • The present day High-tech medical eqpt. is
    mind-boggling to even medical experts that the H.
    consultant and H. Admi. may be easily stumped out

22
  • Departmental heads satisfied with the Type
    should be fully satisfied with the Type Quality
    of eqpt. So they should consulting before
    selections of equpts.
  • Indiscrimnatory procurements of eqpts. may be a
    wastage and liability to the hospital.

23
Timing of purchase, order delivery
  • Are exceedingly important
  • (i) Delivery Instructions should be keyed to the
    building completion schedules
  • (ii) H. Adm may ask a central General store space
    adjoining room form temporary storage of eqpts
    from contractor 6 months before opening 3
    months before completion schedule

24
  • (iii) These spaces can be used as work center for
    equipping operation.
  • Time schedule and Performance Agreements will be
    helpful in their concern
  • If there is Delay in construction, the supplier
    should be notified to delay supplies.
  • The storage places should be protected from
    weather, Theft and damage but should not obstruct
    the construction

25
Syllabus
  • Preparing eqpts list for the new hospitals
  • (a) Building equipment (In built eqpts)
  • (b) Non expendable (Depreciable)
  • Locally available
  • Imported
  • Expendable equpt (no depreciable)
  • Capital equipments CT scan/MRI

26
Equipment planning
  • Hospitals planning include careful Attention to
    Fixed and immovable eqpts that will be needed in
    operation
  • Lack of planning's can involve
  • Wastage of lakhs of rupees
  • Reduced operative efficiency
  • Low standards of pt. care

27
Responsibility of
  • It is the Responsibility of Hospital consultant
    (OR H. Administrator in case H. Consultant not
    engaged) to determine all the items of eqpts
    necessary, write their speciation, recommend bids
    the purchase accerding to hospital policy. The
    domains of hospitals consultant/Adm. Is
    expendable, non expandable capital eqpts.
  • The Architect is responsible for the Built in
    equipments

28
When the planning is done
  • First Equipment planning is dore early in the
    design development stage. The planning involves
  • (i) A series of meetings medical staff, HODs
    other staff to discuss the needed equpts
  • (ii) Preparing Room by Room eqpt list
  • (iii) Review of this list by Administrator
    medical departmental staff.
  • Another detailed equipment planning in necessary
    at Actual Furnishing equipping the hospital

29
Designing the equipment
  • A set of black line points of working drawings
    (floor plans only) should be secured from
    Architect market up in advance, All Gross shown
    to seale identified
  • Done in Designing phase

30
Nature of equipping work
  • It is an exhaustive work because it involves not
    only degree but a variety of technical knowledge.
  • There are innumerable expendable items which
    should be procured stocked in sufficient
    Quantities
  • No well procuring system in a new hospital (c/f
    purchasing in an running hospital)
  • This problem is compounded by timing of delivery,
    ware housing, unpacking Assembling installing
    eqpt apart from purchasing

31
Imported eqpts
  • Poses more complex problem
  • (a) Needs Approvals license
  • (b) Burecratie hurdles needed to be crossed
  • (c) Costly items
  • (d) lead time will be longer
  • (e) Delay can cause loss in lakhs

32
(No Transcript)
33
(No Transcript)
34
(No Transcript)
35
(No Transcript)
36
(No Transcript)
37
(No Transcript)
38
(No Transcript)
39
(No Transcript)
40
(No Transcript)
41
(No Transcript)
42
(No Transcript)
43
(No Transcript)
44
(No Transcript)
45
(No Transcript)
46
(No Transcript)
47
(No Transcript)
48
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com