Title: Tank Consultants, Inc.
1Tank Consultants, Inc.
- 4333 West 21st Street
- Tulsa, Oklahoma 74107-3444
- 918-583-3968 Telephone
- 918-583-3966 Fax
- www.tank-consultants.com
2SPCC Tank Integrity Testing
- Presented By Kevin Kupitz
3Who has to test their tanks?
- If you have a facility with an aggregate oil
storage capacity of 1320 gallons you must inspect
all containers 55 gallons and above. - Applies to owners/operators that use oil. This
would include storage capacity of operating
equipment.
4What type of facilities does this include?
- SPCC States
- oil of any kind or in any form, including but
not limited to fats, oils, or greases of
animal, fish or marine mammal origin vegetable
oils, including oils from seeds, nuts, fruits, or
kernels and other oils and greases, including
petroleum, fuel oil, sludge, synthetic oils,
mineral oils, oil refuse, or oil mixed with waste
other than dredged oil
5Facilities such as
- Marinas
- General processing
- Refineries
- Pipelines
- Terminals
- Chemical plants
- Many other facilities
6SPCC plan review
- The original SPCC regulation was effective
beginning January 10, 1974
7Revisions
- The new revision requires owner/operators to test
above ground containers for integrity on a
periodic basis. - Most facilities should have a plan already that
only requires revising.
8Schedule for the new plan
- Must have your SPCC plan amended by August 17,
2004. - Must implement your plan by February 18, 2005.
9Why should I inspect my tanks?
10Why should I inspect my tanks?
- To protect our environment.
- EPA will audit facilities as necessary.
- ND just fined 17 companies for over 400,000.00.
- Oxychem penalty of 137,500.00
11Issues
- Incomplete plan.
- Failure to inspect tanks, valves, piping and
appurtenances. - Failure to conduct integrity testing
- Lack of secondary containment for tanks.
- Inadequate secondary containment.
12What does an O/O have to do to comply?
- SPCC does not refer to or mandate the use of any
industry standard as related to tank inspection.
Although it states - Consider the use of all relevant measures,
including the use of industry standards, as a way
to implement those measures. - The decision in every case as to the
applicability of any standard will be one for the
P.E.
13What industry standards do we need to consider?
- API-653
- Written by tank builders, owners/operators and
repair companies - For self regulation rather than government
regulation - STI SP001-03 was written by
- Tank builders
- At the request of the EPA
14API-653 applies to
- API-650 Welded Steel Tanks for Oil Storage
- API-12C, the predecessor to API-650
- Any unknown standard
- API-653 Certified Inspector
15STI SP001-03 applies to
- Tanks SHOP built to any nationally recognized
standard - UL-142, 2085 and 2244
- API-650 Appendix J
- API-12F
- SwRI 97-04, 93-01
- lt50,0000 gallon tanks.
- STI Trained Inspector.
16What tests do we have to do to comply?
- Perform periodic Integrity Tests.
- Evaluate field constructed containers for Brittle
Fracture during repairs, alterations or change in
service. - Record keeping.
17What constitutes an Integrity Test?
- SPCC states
- You must combine visual inspection with another
testing technique such as hydrostatic testing,
RT, UT, AE or another system of non-destructive
shell testing. - Test each above ground container for integrity
on a regular schedule, and whenever you make
material repairs.
18What does this mean?
- The actual inspection can be in accordance with
STI SP001-03 or API-653 or a combination of both. - Either way, the P.E. must sign off on the
inspection technique.
19The tank inspection will be determined by a few
main variables
- SPCC states
- The frequency of and type of testing must take
into account container size and design (such as
floating roof, skid mounted, elevated, or
partially buried).
20Example tank inspection for Field Erected
Vertical Tank on Grade.
21Example tank inspection for Field Erected
Vertical Tank on Grade.
- Monthly visual check by operator.
- 5 year external by a certified inspector by VT
and UT methods while the tank is full. - 10 year internal inspection incorporating VT, UT
and/or MFL. Check tank bottom. - As an option, the tank could be lifted exposing
all sides of the tank.
22(No Transcript)
23Vertical tank on Grade with Leak Detection.
- Monthly visual check by the operator.
- 5 year external inspection by a certified
inspector with tank full of product. - Internal inspection only when leaks are found or
the integrity is questioned by the certified
inspector.
24Horizontal Tank with all Sides Exposed.
25Horizontal Tank with all Sides Exposed.
- Monthly visual check by operator.
- Perform a 5 year external inspection with the
tank full of product. - Perform thorough Ultrasonic (UT) evaluation on
the lower 60 degrees of the tank. - Perform UT scrubs on the heads of the tank.
26O/O with many tanks
27O/O with many tanks
- Perform an Inventory/walk through inspection.
- Prioritize tanks by condition and location.
- Plan what needs to be done for all tanks to be
integrity tested. - Schedule the integrity Test.
28Test Techniques
- Ultrasonic Thickness Testing (UTT)
- Magnetic Flux Leakage (MFL) Floorscan
- Ultrasonic (UT) Corrosion Scanning (A-scan)
- Magnetic Particle Testing (MT)
- Visual Examination (VT)
29Ultrasonic Thickness Test
30MFL Floorscan
31(No Transcript)
32(No Transcript)
33(No Transcript)
34(No Transcript)
35Ultrasonic Corrosion Scanning
36(No Transcript)
37(No Transcript)
38(No Transcript)
39Visual Inspection
40(No Transcript)
41(No Transcript)
42Holes from Soil Side Corrosion
43Weeps
44Conclusion
- Integrity Testing is accomplished by collecting
the important tank variables and then determining
what industry inspection standards make sense and
then apply them. - Your P.E. must approve them into the plan.
45Just remember, there are more painful things in
life!