Push vs. Pull Process Control - PowerPoint PPT Presentation

1 / 44
About This Presentation
Title:

Push vs. Pull Process Control

Description:

Push vs. Pull Process Control IE 3265 POM Slide Set 9 R. Lindeke, Sp 2005 Basic Definitions MRP (Materials Requirements Planning). MRP is the basic process of ... – PowerPoint PPT presentation

Number of Views:138
Avg rating:3.0/5.0
Slides: 45
Provided by: dUmnEdu77
Category:
Tags: control | process | pull | push

less

Transcript and Presenter's Notes

Title: Push vs. Pull Process Control


1
Push vs. Pull Process Control
  • IE 3265 POM
  • Slide Set 9
  • R. Lindeke, Sp 2005

2
Basic Definitions
  • MRP (Materials Requirements Planning). MRP is the
    basic process of translating a production
    schedule for an end product (MPS or Master
    Production Schedule) to a set of time based
    requirements for all of the subassemblies and
    parts needed to make that set of finished goods.
  • JIT Just-in-Time. Derived from the original
    Japanese Kanban system developed at Toyota. JIT
    seeks to deliver the right amount of product at
    the right time. The goal is to reduce WIP
    (work-in-process) inventories to an absolute
    minimum.

3
Why Push and Pull?
  • MRP is the classic push system. The MRP system
    computes production schedules for all levels
    based on forecasts of sales of end items. Once
    produced, subassemblies are pushed to next level
    whether needed or not.
  • JIT is the classic pull system. The basic
    mechanism is that production at one level only
    happens when initiated by a request at the higher
    level. That is, units are pulled through the
    system by request.

4
Comparison
  • These methods offer two completely different
    approaches to basic production planning in a
    manufacturing environment. Each has advantages
    over the other, but neither seems to be
    sufficient on its own. Both have advantages and
    disadvantages, suggesting that both methods could
    be useful in the same organization.
  • Main Advantage of MRP over JIT MRP takes
    forecasts for end product demand into account. In
    an environment in which substantial variation of
    sales are anticipated (and can be forecasted
    accurately), MRP has a substantial advantage.
  • Main Advantage of JIT over MRP JIT reduces
    inventories to a minimum. In addition to saving
    direct inventory carrying costs, there are
    substantial side benefits, such as improvement in
    quality and plant efficiency.

5
Comparisons (cont.)
6
Comparisons (cont.)
7
Focusing on JIT
  • JIT (Just In Time) is an outgrowth of the Kanban
    system developed by Toyota.
  • Kanban refers to the posting board (and the
    inventory control cards posted there) where the
    evolution of the manufacturing process would be
    recorded.
  • The Kanban system is a manual information system
    that relies on various types of inventory control
    cards.
  • Its development is closely tied to the
    development of SMED Single Minute Exchange of
    Dies, that allowed model changeovers to take
    place in minutes rather than hours.
  • The Fundamental Idea of JIT and Lean
    Manufacturing Systems in General (an
    Americanization of the Toyota P. S.) is to
    empower the workers to make decisions and
    eliminate waste wherever it is found

8
The Tenets of JIT/Lean
  • Empower the workers
  • Workers are our intelligent resources allow
    them to exhibit this strength
  • Workers ultimately control quality lets them do
    their job correctly (Poka-Yoke)
  • Dont pit workers against each other eliminate
    piece-work disconnected from quality and allow
    workers to cooperate in teams to design jobs and
    expectations

9
The Tenets of JIT/Lean
  • Eliminate Waste
  • Waste is anything that takes away from the
    operations GOAL (to make a profit and stay in
    business!)
  • Reduce inventory to only what is absolutely
    needed
  • Improve Quality scrap and rework are costly and
    disrupt flow
  • Only make what is ordered
  • Make setups and changes quickly and efficiently
  • Employ only the workers needed
  • Eliminate Clutter it wastes time

10
Features of JIT Systems
  • Small Work-in-Process Inventories.
  • Advantages
  • 1. Decreases Inventory Costs
  • 2. Improves Efficiency
  • 3. Reveals quality problems (see Figure 7-10)
  •  
  • Disadvantages
  • 1. May result in increased worker idle time
  • 2. May result in decreased throughput rate

11
River/Inventory Analogy Illustrating the
Advantages of Just-in-Time
Revealing fundamental problems is the noted
competitive advantages of JIT/Lean
12
Features of JIT Systems (continued)
  • Kanban Information Flow System
  •   Advantages
  • 1. Efficient tracking of lots
  • 2. Inexpensive implementation of JIT
  • 3. Achieves desired level of WIP based on
    Number of Kanbans in the system
  •  
  • Disadvantages
  • 1. Slow to react to changes in demand
  • 2. Ignores predicted demand patterns (beyond 2
    months or so)

13
Focus on The Kanban
  • Typically it is a 2-card system
  • The P (production) Card and W (withdrawal) Card
  • Limits on product inventory (number of P W
    cards) are set by management policy
  • The count is gradually lowered until problems
    surface
  • The actual target level (card count) is based on
    short term forecasting of demands

14
Focus on The Kanban
15
Focus on The Kanban the worker as manager
  • P cards cycle from their accumulation post at
    Center 1 to product (when a defined trigger point
    is reached) and then to output queue
  • When trigger level is reached, Ct 1 worker pulls
    product from Ct 1 Wait point queue and replaces
    the Ct 1 W-cards with Ct 1 P-Cards which then are
    loaded to the Ct 1 processors the worker puts
    Ct 1 W-Cards to his/her acc. Post for W-cards
  • Finished Product is pushed into the Ct 1 output
    queue

16
Focus on The Kanban the worker as manager
  • A second worker (Ct 2s worker) watches for
    accumulation of Ct 2 W-Cards
  • When it reaches their trigger level, he/she pulls
    product into Ct 2 Holding area after replacing Ct
    1 P-Cards with their W-Cards and returns Ct 1
    P-Cards to their Acc. Post for Ct. 1 workers
    benefit
  • They also watch for accumulation of Ct. 2 P-Cards
    on their acc. Post and when trigger count is
    reached they pull product from holding area and
    replace Ct 2 W-Cards w/ Ct 2 P-Cards then push it
    into the processors
  • And around and around they go!

17
Focus on The Kanban
  • So how many cards? speaking of which, a card is
    associated with a container (lot) of product so
    the number of P W cards at a station determines
    the inventory level of a product!

18
Focus on The Kanban
  • Lets look at an example
  • 950 units/month (20 productive days) ? 48/day
  • Container size a 48/10 4.8 ? 5
  • L data
  • A. setup is 45 minutes (.75 hour)
  • B. Setup is 3 minutes (.05 hr)
  • Wait time .3 hr/container
  • Transport time .45 hr/container
  • Prod Time 0.09 hr/each .45 hr/container

19
Focus on The Kanban
Requires 32 65 30 pieces in inventory
also, with 45mins set up 10 times a day means
that we consume 450 min or 7.5 hours/day just
setting up!
Here only 22 45 20 pieces and also only
.0510 50 min for setup (.833 hr) per day
20
So, setup reduction impacts Factory Capabilities
Inventory
  • Lets look at the effect of studies comparing cost
    of setup vs. inventory cost like EOQ
  • Then lets see what we can invest to reduce
    inventory levels
  • We will spend money on reducing setup cost (time)
    and see if reduced inventory will offset our
    investment
  • This is the driving force for SMED

21
Focus on the Penalty Factor
  • We can effectively model this a(K) function as
    a logarithmic investment function
  • By logarithmic we imply that there is a an
    increasing cost to continue to reduce setup cost
  • We state, then, that there is a sum of money that
    can be invested to yield a fixed percentage of
    cost reduction
  • That is (for example) for every investment of
    200 the organization can get a 2 reduction in
    Setup cost

22
Focus on the Penalty Factor
  • Lets say that the investment is ? buys a fixed
    percent reduction in K0
  • If we get actually get 10 setup cost reduction
    for ?, then an investment of ? will mean
  • Setup cost drops to 0.9K0
  • A second ? investment will lead to a further 10
    reduction or
  • .9K-.1.9K .81K0
  • This continues K3? .729K0
  • Generalizing

23
Focus on the Penalty Factor
  • With that shape we can remodel the a(K)
    logarithmically
  • a(K) bln(K0) ln(K)
  • where
  • Reverting back to G(Q,K) function and
    substituting Q

24
Focus on the Penalty Factor
  • Finding the K after the minimization
  • To determine what we should do, determine G(K)
    using K0 and K

25
Lets try one
  • K0 1000
  • ? 95 for each 7.5 reduction in setup cost
  • Annual quantity 48000
  • Holding cost 4.50
  • MARR is 13

26
Continuing
  • Investment to get to K
  • Testing for decision
  • No investment (K K0)
  • At Min K

27
SMED
28
Some terms
  • SMED single minute exchange of dies which means
    quick tooling change and low setup time (cost)
  • Inside Processes ? setup functions that must be
    done inside the machine or done when the
    machine is stopped
  • Minimally these would include unbolting departing
    fixtures/dies and positioning and bolting new
    fixture/dies to the machine

29
More Terms
  • Outside Setup ? activities related to tooling
    changes that can be done outside of the machine
    structure
  • These would include
  • Bringing Tooling to Machine
  • Bringing Raw Materials to Machine
  • Getting Prints/QC tools to machine
  • Etc.

30
Focus on SMED
  • When moving from No Plan or Step 1 to Step 2
    (separating Inside from Outside activities)
    investments would be relatively low to accomplish
    a large amount of time (cost) saving
  • Essentially a new set of change plans and a small
    amount of training to the Material Handlers so
    that they are alerted ahead of time and bring the
    tooling out to the machine before it is needed

31
Moving to Step 3 and Step 4
  • Require investments in Tooling
  • Require Design Changes
  • Require Family tooling and adaptors
  • Require common bolstering attachments
  • In general requiring larger and larger
    investments in hardware to achieve smaller and
    smaller time (cost) savings in setup

32
Therefore, we can say SMED is
  • In reality the essence of a Logarithmic setup
    reduction plan!

33
Lets Look into Line Balancing
  • This is a process to optimize the assignment of
    individual tasks in a process based on a planed
    throughput of a manufacturing system
  • It begins with the calculation of a system Takt
    or Cycle time to build the required number of
    units required over time
  • From takt time and a structured sequential
    analysis of the time and steps required to
    manufacture (assembly) a product, compute the
    number of stations required on the line
  • Once station count is determined, assign feasible
    tasks to stations one-at-a-time filling up to
    takt time for each station using rational
    decision/assignment rules

34
Line Balancing
  • Feasible tasks are ones that have all
    predecessors completed (or no predecessors) and
    take less time that the remaining time at a
    station
  • Feasibility is also subject to physical
    constraints
  • Zone Restriction the task are physically
    separated taking to much movement time to
    accomplish both within cycle (like attaching
    tires to front/back axles on a bus!)
  • Incompatible tasks the Grinding/Gluing
    constraint

35
Some of the Calculations
  • Takt (Cycle) Time
  • Minimum Workstations reqr

36
Efficiency Calculations
37
Lets Try One
Times A 25s B 33sC 33s D 21s E 40s F40s G
44s H 19s
A
B
C
Production Requirement is 400/shift
G
H
D
E
F
38
Calculation of Takt Time Optimal Station count
39
To Perform Assignment we need Assignment Rules
  • Primary Rule
  • Assign task by order of those having largest
    number of followers
  • Secondary Rule
  • Assign by longest task time

40
Primary Assignment Rule
41
Line Balancing Assignments
42
The Line Balance
A
B
C
WS 5
WS 3
G
H
WS 1
WS 6
D
E
F
WS 2
WS 4
43
Checking Efficiencies
44
Dealing with Efficiencies
  • We investigate other Rules application to
    improve layout
  • 1st by followers then by longest time then most
    followers
  • Alternating!
  • Consider line duplication (if not too expensive!)
    which lowers demand on a line and increases Takt
    time
  • The problem of a long individual task
  • In Koeln, long time stations were duplicated
    then the system automatically alternated
    assignment between these stations
Write a Comment
User Comments (0)
About PowerShow.com