Improve Hurricane Protection to the IHNC Partnering Update Brief - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Improve Hurricane Protection to the IHNC Partnering Update Brief

Description:

Goal is to eliminate center pier and one bulkhead ... Advertised Phase One July 2nd. Short-listed to the four most qualified firms: ... – PowerPoint PPT presentation

Number of Views:38
Avg rating:3.0/5.0
Slides: 16
Provided by: johna106
Category:

less

Transcript and Presenter's Notes

Title: Improve Hurricane Protection to the IHNC Partnering Update Brief


1
Improve Hurricane Protection to the IHNC
Partnering Update Brief
  • August 21, 2007

2
Agenda
  • Interim Project Update
  • Permanent Solution Project Update
  • Draft Request for Proposal (RFP) Process
  • Project Cooperation Agreement (PCA)

3
Interim Protection Challenges
  • No option achievable before Hurricane season 2009
  • Raising the walls
  • Constructability challenges
  • Limited Right of Way and room for construction
  • 8.5 miles total of floodwalls and gates
  • 4.2 miles South of I-10 overpass on IHNC
  • Impacts on commercial industry
  • Temporary Barge Gate
  • Constructability challenges
  • Akin to permanent structure
  • Potential for NEPA impacts
  • Impacts on navigation
  • Constrictions
  • Potential for NEPA impacts
  • Impacts on navigation
  • Real Estate

4
Interim Protection Path Ahead
  • Barge Gate
  • Reviewing designs based on updated 100yr
    elevation design criteria
  • Differential head, Impact loads
  • Required Real Estate owned by NASA, Port of New
    Orleans
  • Allows for expedited real estate acquisition
    process
  • ERDC optimizing channel opening for velocity and
    navigation
  • Goal is to eliminate center pier and one bulkhead
  • Eases navigation and environmental impact
    concerns
  • MVN/HPO Environmental determining best method to
    achieve NEPA compliance ERDC analysis is
    crucial
  • HPO Contracting determining best expedited means
    for contract mechanisms
  • MVN HH modeling inundation maps for 4 scenarios
    (Current conditions, With Barge Gate, Walls S of
    I-10 at el. 15, All walls on IHNC at el. 15)
  • Working in conjunction with A-E to refine cost,
    all aspects of design and construction schedules,
    and ways to expedite delivery
  • Final Schedule and Cost analysis to be complete
    once refined designs are complete joint HPO/A-E
    effort
  • Goal remains all efforts complete NLT 31 AUG 07

5
100-yr IHNC Project
  • Provide a 100-year Level of Protection to the
    IHNC from Hurricane-Induced Storm Surges by the
    2011 Season

6
Project Status
  • Advertised Phase One July 2nd
  • Short-listed to the four most qualified firms
  • Tetra Tech, EC, Inc
  • Kiewit Federal Group, Inc
  • Shaw Environmental Infrastructure, Inc
  • Washington Group International, Inc/Interbeton,
    Inc JV
  • Next step Phase Two Draft RFP

7
Timeline (est.)
Phase 1 Request for Proposals
Phase II RFP Issued Sept 24, 2007
Phase 2 Request for Proposals (Issue Sept 07)
Final Funding Notification
Project Cooperation Agreement (PCA) Negotiation
PCA Executed Feb 08
Award Design-Build Construction Contract Mar 08
Contractor Prepares 30 Design by June 08
NEPA / IER complete June 08
PCA Amended (if needed) per 30 Design
Amended PCA Executed
Contractor Completes Design
Real Estate Acquisition complete by Dec 08
Issue Notice to Proceed for Construction 1 Sept 08
Construction
Complete by 1 Jun 2011
8
Draft RFP Process
  • Issue draft RFP to local sponsor and short-listed
    firms this week
  • Meet individually with firms 4-6 Sept
  • Meet with local sponsor Sept 11th to review Draft
    RFP comments
  • Final RFP pre-release meeting with local sponsor
    Sept 18th

9
Phase II Proposals
  • Open to all alternatives
  • No navigation requirement on the MRGO
  • Will modify if Congress doesnt act
  • Concept design complete for deep-draft nav
  • No assumptions for Seabrook
  • Bayou Bienvenue must remain open

10
IHNC Alternative Concepts
Alternative A
11
NEPA Alternatives
12
Evaluation Criteria
  • Most Probable Schedule
  • Technical Solution
  • Management Approach
  • Most Probable Lifecycle Cost
  • Socioeconomic Plan

13
Technical Performance Specs
  • 100-year design elevations
  • Navigable structures
  • Barriers (walls, levees, etc.)
  • Minimize OMRRR
  • Training Requirements
  • Environmental Requirements
  • Construction Management Safety

14
Project Cooperation Agreement (PCA)
  • Project is fully funded by U.S. Government
  • USACE shall afford the Non-federal sponsor (DOTD/
    SLFPAE) the opportunity to review and comment on
    all aspects of the project
  • Non-federal sponsor responsibilities
  • Provide all non-federal government lands
  • Secure commandeering order(s) (if available) to
    all private lands
  • Operate, maintain, repair, rehabilitate, replace
    project
  • Hold and save the Government free from damages

15