Title: Improve Hurricane Protection to the IHNC Partnering Update Brief
1Improve Hurricane Protection to the IHNC
Partnering Update Brief
2Agenda
- Interim Project Update
- Permanent Solution Project Update
- Draft Request for Proposal (RFP) Process
- Project Cooperation Agreement (PCA)
3Interim Protection Challenges
- No option achievable before Hurricane season 2009
- Raising the walls
- Constructability challenges
- Limited Right of Way and room for construction
- 8.5 miles total of floodwalls and gates
- 4.2 miles South of I-10 overpass on IHNC
- Impacts on commercial industry
- Temporary Barge Gate
- Constructability challenges
- Akin to permanent structure
- Potential for NEPA impacts
- Impacts on navigation
- Constrictions
- Potential for NEPA impacts
- Impacts on navigation
- Real Estate
4Interim Protection Path Ahead
- Barge Gate
- Reviewing designs based on updated 100yr
elevation design criteria - Differential head, Impact loads
- Required Real Estate owned by NASA, Port of New
Orleans - Allows for expedited real estate acquisition
process - ERDC optimizing channel opening for velocity and
navigation - Goal is to eliminate center pier and one bulkhead
- Eases navigation and environmental impact
concerns - MVN/HPO Environmental determining best method to
achieve NEPA compliance ERDC analysis is
crucial - HPO Contracting determining best expedited means
for contract mechanisms - MVN HH modeling inundation maps for 4 scenarios
(Current conditions, With Barge Gate, Walls S of
I-10 at el. 15, All walls on IHNC at el. 15) - Working in conjunction with A-E to refine cost,
all aspects of design and construction schedules,
and ways to expedite delivery - Final Schedule and Cost analysis to be complete
once refined designs are complete joint HPO/A-E
effort - Goal remains all efforts complete NLT 31 AUG 07
5100-yr IHNC Project
- Provide a 100-year Level of Protection to the
IHNC from Hurricane-Induced Storm Surges by the
2011 Season
6Project Status
- Advertised Phase One July 2nd
- Short-listed to the four most qualified firms
- Tetra Tech, EC, Inc
- Kiewit Federal Group, Inc
- Shaw Environmental Infrastructure, Inc
- Washington Group International, Inc/Interbeton,
Inc JV - Next step Phase Two Draft RFP
7Timeline (est.)
Phase 1 Request for Proposals
Phase II RFP Issued Sept 24, 2007
Phase 2 Request for Proposals (Issue Sept 07)
Final Funding Notification
Project Cooperation Agreement (PCA) Negotiation
PCA Executed Feb 08
Award Design-Build Construction Contract Mar 08
Contractor Prepares 30 Design by June 08
NEPA / IER complete June 08
PCA Amended (if needed) per 30 Design
Amended PCA Executed
Contractor Completes Design
Real Estate Acquisition complete by Dec 08
Issue Notice to Proceed for Construction 1 Sept 08
Construction
Complete by 1 Jun 2011
8Draft RFP Process
- Issue draft RFP to local sponsor and short-listed
firms this week - Meet individually with firms 4-6 Sept
- Meet with local sponsor Sept 11th to review Draft
RFP comments - Final RFP pre-release meeting with local sponsor
Sept 18th
9Phase II Proposals
- Open to all alternatives
- No navigation requirement on the MRGO
- Will modify if Congress doesnt act
- Concept design complete for deep-draft nav
- No assumptions for Seabrook
- Bayou Bienvenue must remain open
10IHNC Alternative Concepts
Alternative A
11NEPA Alternatives
12Evaluation Criteria
- Most Probable Schedule
- Technical Solution
- Management Approach
- Most Probable Lifecycle Cost
- Socioeconomic Plan
13Technical Performance Specs
- 100-year design elevations
- Navigable structures
- Barriers (walls, levees, etc.)
- Minimize OMRRR
- Training Requirements
- Environmental Requirements
- Construction Management Safety
14Project Cooperation Agreement (PCA)
- Project is fully funded by U.S. Government
- USACE shall afford the Non-federal sponsor (DOTD/
SLFPAE) the opportunity to review and comment on
all aspects of the project - Non-federal sponsor responsibilities
- Provide all non-federal government lands
- Secure commandeering order(s) (if available) to
all private lands - Operate, maintain, repair, rehabilitate, replace
project - Hold and save the Government free from damages
15Questions/Comments