Microturbine CHP Application in the Hotel Business - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

Microturbine CHP Application in the Hotel Business

Description:

Embassy Suites Brea. January 20, 2004. 2. Who is PowerHouse Energy ... Who is Embassy Suites. Embassy Suites, Brea is a full service hotel in the central ... – PowerPoint PPT presentation

Number of Views:89
Avg rating:3.0/5.0
Slides: 21
Provided by: david289
Learn more at: https://www.ornl.gov
Category:

less

Transcript and Presenter's Notes

Title: Microturbine CHP Application in the Hotel Business


1
Microturbine CHP Applicationin the Hotel Business
  • DOE Microturbine
  • Application Workshop
  • Embassy Suites Brea
  • January 20, 2004

2
Who is PowerHouse Energy
  • A Southern California based Distributor and
    Authorized Service Provider of both traditional
    and state-of-the-art energy products
  • Its sole mission is to create a win-win solution
    for its customers by reducing energy costs and
    increasing profits through the use of on-site
    generation equipment while never reducing the
    customers security of supply
  • PHE offers a variety of options for equipment
    ownership. It will install and service the
    equipment to insure seamless energy generation

3
Who is Embassy Suites
  • Embassy Suites, Brea is a full service hotel in
    the central retail district
  • They have 228 guest rooms with a 400 seat
    restaurant with conference/meeting rooms
  • The hotel operates 24 hours X 7 days a week
  • They have room heat pumps, central water
    heating, laundry, swimming pool and spa
  • PHE partnered with the hotel in an energy service
  • The hotel was interested in cost savings

4
Pre-CHP Electrical Load
5
Post CHP Installation
6
Progress Checklist

7
Project Schedule
8
Organization
  • Project Management- Thom McMahon/ Installation,
    Ken Nilsson/Service
  • Funded, Owned and Operated by PowerHouse Energy
  • Project Plan (Actual Date)
  • - Equipment Delivery 12/2002(Same)
  • - System Commissioned 3/2003(5/2003)
  • - Monitoring Underway 5/2003(5/2003)

9
Pictures of Site
10
Pictures of Site
11
PID As Built
12
Installation Improvements
  • Improvements this Site
  • - Ventilation improvements
  • - Metering equipment and pool heat interfaces
    as original installation
  • - Selection of installation contractors
  • - Poor fit of supplied package exhaust ducting
  • Target Improvements-Volume Installations
  • - Standard drawing packages
  • - Experienced installation contractors
  • - Volume material purchases

13
Project Cost Table
14
Electrical Performance
  • Hours of operation to Date 4000 4100
  • Average Electrical Performance 26
  • 65,000kW/9,200 Therms (LHV) (Dec. 2003)
  • Estimated Parasitic Loses in KW- 5kW/hr
  • Power Quality Tests Done as required by Southern
    California Edison for Interconnection acceptance.

15
Thermal Performance
  • Thermal Output used 420,000,Btu/hr
  • Average water Delta T across HTX 12oF
  • Average flow rate through HTX 70gpm
  • CHP Efficiency 55, (26e29t)
  • Expected Peak Total System Efficiency 70
  • Electrical 28 Thermal 40
  • Cooling system N/A

16
Emission Performance
  • No emission testing has been done to date.
  • Emissions appear to be in line with Capstone
    estimates.

17
OM Performance
  • Availability
  • The equipment was unavailable for 612 hours due
    to equipment failure, (2 units including site
    issues). Availability cumulative since start
    94.4. 15 site visits due to equipment, 15 due
    to data acquisition and site issues.
  • Cost of OM (less fuel)
  • The current estimate of annual OM costs
    excluding hot end replacement in total costs is
    7,000 and 0.8cents/kWh, (2 units).

18
Institutional Experience
  • Building department and electric utility
    interconnection approvals were required.
  • Project management overhead costs associated with
    approvals were approximately 2,500.
  • No issues were encountered with either approval
    process.

19
Supplier Support
  • PHE was the supplier that turn keyed the
    installation. Better understanding of radiant
    heat generation for ventilation of product would
    be helpful, 70,000Btu/hr each w/gas compressor.
  • Technical support was very good from Capstone
    with clear documentation.
  • PHE is a Capstone Business Partner with a clear
    understanding of OM costs.
  • PHE took advantage of Capstones promotional two
    unit package with a 3-year back stop warranty of
    0.008/kWh costs.

20
General Experience
  • Indoor installations need to account for radiant
    heat with ventilation. Tight space installations
    may not be able to accommodate product
    improvements.
  • PHE has gone on to do several other hotel
    installations, honing design and contractor work.
    Current installation costs by PHE are now within
    1-2 of planned or budget costs.
  • Suggested development areas, monitoring
    capability of kW, thermal and gas use in unit.
    Reliability of electrical components.
Write a Comment
User Comments (0)
About PowerShow.com