Title: Klabin Bacell S.A.


1
implementation of rlink-pppi at a pulp mill
2
Klabin Group
  • Klabin group is the largest paper manufacturer
    and the second largest pulp manufacturer in
    Brazil, as well as leading 10 out of the 11
    markets for packaging and tissue paper items in
    which it is active.

3
location of klabins sites
4
klabin bacell
  • Klabin Bacell, located in Camaçari, State of
    Bahia, produces dissolving pulp used primarily in
    the textile filaments, acetate grade and food
    industry.

5
the plant
  • the plant is one of the world's most modern
    bleach dissolving pulp plants which works with
    modern technology alternatives and high
    automation degree in its process control, managed
    by an ISO 9002 certified Quality System. It is
    the first industrial unit in its category to
    produce pre-hydrolysis Kraft Dissolving Pulp
    through TCF system (Total Chlorine Free), which
    is by itself one of the most significant
    evidences of its environmental performance.

6
SAP/R3 at Klabin context
  • Almost all sites of Klabin in Brazil run SAP/R3

7
The RLINK project at Klabin Bacell
  • Bacell was the first Klabin mill where PI System
    was installed ( PI 2 System in 1995)
  • The implementation of SAP/R3 4.6c at Bacell
    started in March, 2001 and the go-live happened
    on December 1st
  • RLINK PPPI implementation at Bacell started three
    months later ( June )
  • Project Team
  • Maria Helena Del Grande (Project manager - Klabin
    Bacell)
  • Adroaldo Munhoz (Team Leader - Cybertecnica)
  • Flavio Maeda (Analyst - Cybertecnica)

8
RLINK Cybertecnicas expertise
  • Both Adroaldo and Flavio attended the RLINK class
    at OSI office in Germany
  • The whole implementation of RLINK at Klabin
    Bacell
  • Complementation of the RLINK solution at CSN
    with standard PI monitoring tools (PI-PB and VBA).

9
project overview
  • RLINK PPPI project was divided in two major
    parts
  • migration from PI 2 system to PI 3.3 system
    running in a W2K machine
  • implementation of RLINK PPPI (WNT machine).

10
original pi system configuration
OVMS 7.1
V2.2
PI-HOME
SICP
PI
PI
RDB
Ethernet TCP/IP
Client applications

Dec-Alpha-OVMS
NT 4.0
  • PI-ProcessBook
  • PI-DataLink

V2.2
PI
-
API
-
OVMS
P I - API - OVMS
V 1.3
PI
OVMS
PI - API - NTI
PI
-
IN
-
FI
-
CHIP
-
AXP
PI-IN-YO-CPLUS
PI
-
IN
-
FI
-
CHIP
-
AXP
PI-IN-OS-RELDB-NT
CENTAP
YOKOGAWA (DCS)
SCALES
SCALES
11
actual pi configuration
Windows 2000
PI-HOME
RLINK - PPPI
V3.3
PI
PI
MSQL
Ethernet TCP/IP
Client applications

Dec-Alpha-OVMS
  • PI-ProcessBook
  • PI-DataLink
  • PI ManualLogger

V2.3
PI
-
API
-
OVMS
PI
-
API
-
OVMS
PI
-
IN
-
FI
-
CHIP
-
AXP
PI-IN-YO-CPLUS
CENTAP
YOKOGAWA (DCS)
12
project environment
SAP R/3
PRD DB
DEV DB
Test environment
Production environment
TCP / IP
RLINK 1.4
PI Server 3.3
RLINK 1.4
PI API
  • PI e RLINK
  • Win-NT 4 sp6
  • SQL Server v7
  • SAP GUI
  • RLINK
  • Win-NT 4 sp6
  • SQL Server 7.0
  • SAP GUI

YOKOGAWA (DCS)
13
Registry configuration
14
integration plant floor - erp
ERP - SAP R/3
PP-PI
QM
PM
MM
Client applications
Plant Suite -ServerR/3 Link
Packaging area discrete process
PI System
PROCESSO
MS-SQL
Scales
DCS
Manual Entry
Pulp production area - continuous process
15
data flow diagram
Instructions
Messages
  • Process order info.
  • Process order status
  • status
  • production reporting
  • activities
  • batch characteristics
  • Process Order Info.

(manual entry)
  • production
  • consumptions
  • activities
  • status
  • Manual production reporting
  • activity info

Campaign Manager
PI System
MS-SQL
  • Process info.
  • Dry rate
  • consumptions
  • activities
  • discrete production information
  • Qty of wood consumed in a process order
  • process information

DCS
SRM
Scales
Packaging line - bales - reels
Wood receiving and preparation
Pulp production plant
16
pulp production stages
Continuous process
Discrete process
PMADE
wood raw materials
liquid effluents
Bits of wood
PMARR
raw materials water
steam
cooking
SBOBI
unbleached pulp
PBRAN
Delignification / bleaching
water raw materials
Bleachedpulp
SFARD
Black liquor
RECUP
raw materials
White liquor
17
Resource networks
  • Continuous process
  • PMADE - wood preparation
  • PMARR - unbleached pulp production
  • PBRAN - bleached pulp production
  • RECUP - recuperation phase
  • Discrete process
  • SFARD - packaging of the final product
    into bales
  • SBOB - packaging of the final product into
    reels

However all sub-plants are of type BPI (PI-Batch
Plant)
18
Activities and materials - PMADE
19
production reporting -data flow
SAP/R3
PI_PROD PI_CONS PI_PHACT PI_PHST PI_CRST
RLINK
PI System
Quantity of energy and water consumed in the PO
quantity of each type of wood consumed in the P.O.
...
PINet Node
Campaign Manager
PI-ProcessBook
DCS
ODBC
SRM
20
bill of materials / recipe relationship
RAW MATERIALS
WOOD MATERIAL1 MATERIAL2 MATERIAL3
MATERIAL4 MATERIAL5 MATERIAL6
Stock of produced material - HALB Five different
materials - one per recipe
CAV_RECEITA_1 CAV_RECEITA_2 CAV_RECEITA_3 CAV_RECE
ITA_4 CAV_RECEITA_5
from DCS tags
INDUSTRIAL WATER ELECTRICAL POWER
.. TO THE NEXT PROCESS PHASE UNBLEACHED PULP
PRODUCTION
21
material tag and common name tables - PMADE
22
activities for wood preparation
  • Organic liquid effluent
  • Inorganic liquid effluent
  • Machine working hours - direct costing
  • Machine working hours - indirect costing
  • Man working hours - direct costing
  • Depreciation

23
campaign manager
24
campaign manager is used...
  • to view general information of all recipes
    available in rlink for the specific resource
    network
  • process order id
  • control recipe id
  • control recipe status in rlink
  • material produced / planned quantity
  • total produced and remaining quantity

25
campaign manager is used...
  • to view further information about the bill of
    material of each Control Recipe
  • material id
  • description
  • quantity programmed to be consumed / produced
  • total quantity already reported to SAP
  • last quantity reported of each material (PI_CONS
    and PI_PROD)
  • timestamp of the last production report (partial
    finish)

26
campaign manager is used...
  • to change the control recipe status

To finish the process order
To partially finish the process order reporting
production to SAP
To interrupt the process order in progress
To start the control recipe when there is no
other process order in progress
27
manual input screen
the manual input box is automatically opened only
when there are materials that need manual
reports of production (all information associated
with .MI tags in material_tag and common_name
tables)
SEND TO PI
Current Time
Timestamo of either the last production report or
the start time of the control recipe
Bacth id sent to SAP with the PI_CONS
Wood consumption in this process order for this
period of time
Produced material
Storage location
28
control recipe status changings
process order current status
first production reported to SAP (partial finish)
timestamp when the process order was started in
RLINK
29
discrete process - packaging area
  • after the production of the Bleached Pulp this
    material (HALB) is available for the next phase
    of the process the drying phase
  • after the bleached pulp has been dried it needs
    to be prepared to be shipped to the customer. The
    final product (FERT) can be shipped into reels or
    bales. Each unit shipped to the customer is
    called Bacell lot

30
the interaction between RLINK and the packaging
line
  • The process control is performed by a software
    that controls the packaging line. It communicates
    with equipments situated in the plant floor such
    as the scale and the printer
  • This application sends and receives data from
    RLINK and PI
  • The process information is continuously sent to
    RLINK in background.

31
the process flow
PI_PROD PI_CONS PI_PHACT PI_BT_CR PI_BT_CL
1. The process control software (SRP) start the
production of a Lot. 2. Each SAP Lot produced is
weighted by the scale 3. When a Lot is closed,
the PCS sends the information of each SAP Lot
directly to RLINK (using customized stored
procedures)
32
questions ??