Title: Bailey Bridge


1
Bailey Bridge
By Erick Cain
2
What is a Bailey Bridge?
  • A Pre-fabricated Truss Bridge designed for the
    military during WWII.

3
Who Invented the Bailey Bridge and Why ?
  • Sir Donald Bailey
  • Civilian Engineer for the Experimental Bridge
    Establishment (EBE) Royal Engineers
  • Military needed a strong, light weight, easily
    manufactured bridge during WWII.

4
Bailey Bridge Requirements
  • Bridge parts could not weigh more then 600 lbs or
    what 6 men could lift.
  • All parts had to be able to fit in a 3 ton GS
    Lorry.
  • Bridge had to be flexible to carry various size
    loads, and be adaptable to various size gaps.

5
Bailey Bridge Requirements
  • A 150 foot triple-triple Bailey Bridge had to be
    able to carry a Churchill Tank on its transporter
    (70 tons)

6
Why Bailey Bridge Specs are great for
Transportation Departments
  • Versatility
  • Quick and easy to assemble.
  • If needed can be built to carry legal loads.
  • Once purchased inexpensive detour.
  • Many of the same reasons it worked well for the
    military during WWII.

7
Bailey Bridge Drawbacks
  • They are a one lane bridge.
  • Need continual maintenance.
  • Bolt and Nut Tightening
  • Transom Clamp Tightening
  • Timber Plank Checking.

8
Recent Uses of Our Bailey Bridge Parts
  • City of Scio, Oregon Summer 2007.
  • Port of St. Helens
  • Oregon State Parks Pedestrian Bridge.

9
Assembly of Scio Bailey Bridge
  • First we had to locate enough Bailey Bridge for
    the Scio Detour.
  • Oregon National Guard helped us out.

10
Preparation is Key
  • Preparing the site prior to bridge assembly.
  • Ground work for the rollers. (level ground)
  • Proper spacing of the rollers.
  • Enough personnel to assemble.

11
Preparation
  • Ensure enough parts have been delivered to site
    to build the desired structure.
  • If launching bridge ensure enough parts for
    counter weight, and launching nose.

12
Preparation
  • Ensure the clamps and bolts are in proper working
    order
  • Check for unusable floorboards.
  • Ensure all the parts are compatible. MI, MII,
    MIII Bailey Bridge Parts.

13
Tools for Bailey Bridge Construction
14
Tools for Bailey Bridge Construction
15
Tools for Bailey Bridge Construction
16
Importance of Soils
  • Taking in to consideration of the soil when
    constructing the bridge.

17
Building the Launching Nose
  • First several panels are a skeleton frame.
  • Number of panels depend on the length and size of
    bridge being launched
  • Launching frame is separated from the bridge main
    span by the launching link.

18
Assembling the Bridge
  • Begin to assemble the bridge by standing up truss
    panels on the stationary rollers.
  • After truss panels are stood up connect them with
    transoms and transom clamps.

19
Assembling the Bridge
  • Next connect the panels with panel pins and pin
    clips.

20
Assembling the Bridge
  • Next attach
  • Sway Bracing
  • Frame Bracing

21
Building the Bridge
  • After the launching nose begin building the
    actual bridge.
  • Actual Bridge consists of a desired number of
    panels deep and tall up to 3 wide and 3 high.
    (Scio Bridge is a Single Double)

22
Building the Bridge
  • When building the bridge it is important to keep
    on enough counter weight.

23
Building the Bridge
  • Stringers are placed into position after the
    assembly each panel and truss section.
  • The stringers are the support for the floor
    beams.

24
Building the Bridge
  • Launching is done by mostly brute force.
  • Need as many people as possible on each side of
    the bridge to push.
  • Heavy equipment can be utilized to help push and
    pull.

25
Adding the Planking
  • Riding surface is timber planking.
  • Steel Grading is also available, ODOT currently
    does not own any bailey bridge grating.

26
Curb
  • Installing a curb is a important factor in
    holding floor boards in place.

27
Finishing Touches
  • Approaches
  • Ramps
  • Traffic Control

28
(No Transcript)
29
Detour
30
Scio Bridge Final Stats
  • 64,000 vehicles End of June 2007 October 2,
    2007
  • 5000 Pedestrians and Bicycles
  • Open 8 hour day 6 days a week

31
Inexpensive Detour
  • Total Cost of using Bailey Bridge 110,000
  • Linn County estimate over a 1,000,000 if
    standard a standard timber detour bridge was built

32
Storage
  • Currently Old I-205 Rest Stop
  • Store Bailey and Acrow Bridge
  • Any Ideas for storage east of the mountains?

33
Thank You!