Title: P1247176258XqwlZ
1Create Stock Value
Time Value
Risk
Financing
Investment
Cash Flows
Evaluation
Estimating Project Cash Flows
2Investments (Capital Budgeting)
Evaluation
Estimating Project Cash Flows
Classification
Discounted CF Methods
Payback
Accounting Rate of Return
Process
Planning
Size
Generate Ideas
Type of Benefits
Estimate Cash Flows
Dependence
Accept/ Reject
Implement
Post- Audit
3Investments (Capital Budgeting)
Evaluation
Estimating Project Cash Flows
Classification
Discounted CF Methods
Payback
Accounting Rate of Return
Process
Accept/Reject Projects
Mutually Exclusive Projects
Net Present Value (NPV)
Internal Rate of Return (IRR)
Net Present Value (NPV)
Internal Rate Of Return
4Investments (Capital Budgeting)
Evaluation
Estimating Project Cash Flows
Classification
Discounted CF Methods
Payback
Accounting Rate of Return
Process
Accept/Reject Projects
Mutually Exclusive Projects
Net Present Value (NPV)
Internal Rate of Return (IRR)
Net Present Value (NPV)
Internal Rate Of Return
Possibility of Multiple IRR
5Mutually Exclusive Projects
Project Yr0 Yr1 Yr2 Yr3 Yr4 Yr5 A.State of Art
Facility -400 100 110 120 130 140 B.Low
Cost -200 50 60 70 70 80 NPV_A(12) 24.45 NPV_B(
12) 14.30 IRR_A 14.30 IRR_B 15.95
6Mutually Exclusive Projects
Net Present Value (NPV)
Internal Rate Of Return
Why the Possible Conflict
Reinvestment Assumption
Scale Differences
Unequal Useful Life
Early versus Late Projects
7Why the Possible Conflict
NPV
b
IRRa
a
k
k
IRRb
8 Payback
Year 1 2 3 4 5 6 7 8 NCF 2,000 3,000 4,000 3,500
3,000 2,000 1,000 1,000
k10
- Year Cash Flow PV Cash Flow Cumulative
- 2,000 1,818 1,818
- 3,000 2,479 4,298
- 4,000 3,005 7,303
- 3,500 2,391 9,693
- 3,000 1,863 11,556
- 2,000 1,129 12,685
- 1,000 513 13,198
- 8 1,000 467 13,665
Initial investment 12,500. k10 Payback 4
years Discounted Payback(r10)5.84 years NPV
1,165
9 Accounting Rate of Return
After-Tax Cash Flows Project Investment Yr1 Yr
2 Yr3 Yr4 Yr5 A 5,000 800 1,000 350 1,250 3,000
B 7,500 1,250 3,000 2,500 5,000 5,000 C 4,000 60
0 1,200 1,200 2,400 3,000 k12. Target ARR20.
Straight line 5 years. Tax rate35
Projects A B C Total after-tax cash
flow 6,400 16,750 8,400 Total depreciation 5,000
7,500 4,000 Net Income 1,400 9,250 4,400 Average
Net Income 280 1,850 880 Accounting Rate of
Return 11.2 49.3 44.0 Payback 4.53
yrs 3.15 yrs 3.42 yrs NPV -743 3,802 1,574 IRR
7 27 23.37
10Investments (Capital Budgeting)
Evaluation
Estimating Project Cash Flows
Replacement
New Products
Biases
Options
Guidelines
Positive NPV Reasons?
Incremental CF
Ignore sunk costs
Consider Opportunity Costs
Consider WC Investments
Consider Terminal Values
11Investments (Capital Budgeting)
Evaluation
Estimating Project Cash Flows
Replacement
New Products
Biases
Options
Guidelines
Positive NPV Reasons?
Initial Investment
Periodic Cash Flows
Terminal Value
12Initial Investment
- A projects initial investment may consist of
three components - Cost of acquiring and placing the asset in
service - Net proceeds from the sale of the existing
equipment - Tax consequences of selling an existing asset
13Operating Cash Flows
- The incremental operating cash flows (DOCF), per
period, can be expressed as - DOCF ( DREV - DCOST - DDEP)(1 - TAX) DDEP
DWC - DOCF ( DREV - DCOST)(1 - TAX) TAX DDEP - DWC
- Where
- DREV the change in revenues
- DCOST the change in operating costs
- DDEP the change in depreciation
- DWC the annual increase in working capital
- TAX the marginal tax rate faced by the firm
14Terminal or Salvage Values
- A projects terminal, or salvage value may
consist of one or more of the following elements - Salvage value of equipment
- Recovery of working capital
- Cash flows beyond some initial evaluation period
15Spectrum Manufacturing Company
- Existing Equipment
- Cost 120,000 Depreciation
12,000/Year Book Value 60,000 - Salvage Value Today 10,000 Salvage Value in 5
Years 0 - New Equipment
- Cost 100,000 Depreciation 20,000/Year
- Cash Savings 24,000/Year Salvage Value in 5
Years 0
16Spectrum Manufacturing Company- Initial Investment
- Installed Cost of Computerized Lathe
-100,000 - Salvage Value of Old Lathe
10,000 - Tax Effects from Selling Old Lathe
20,000 - INITIAL INVESTMENT
-70,000
17Spectrum Manufacturing Company - Operating Cash
Flows
- Year 1 Year 2 Year 3 Year 4
Year 5 - Annual Cash Savings 24,000 24,000
24,000 24,000 24,000 - D Depreciation (8,000) (8,000) (8,000)
(8,000) (8,000) - Taxable Income 16,000 16,000 16,000
16,000 16,000 - Taxes_at_40 (6,400) (6,400)
(6,400) (6,400) (6,400) - After-Tax Income 9,600 9,600
9,600 9,600 9,600 - Plus D Depreciation 8,000 8,000
8,000 8,000 8,000 - Annual OCF 17,600 17,600 17,600 17,600
17,600
18Spectrum Manufacturing Company- The Projects NPV
- NPV 17,600 PVIFA 5,10 -70,000
- 17,600(3.7908) - 70,000
- -3,282
19New Product Introduction - Smith Corporation
- NEW PRODUCT FINANCIAL FORECASTS
- ( ALL FIGURES IN 1,000)
- Period
0 1 2 3 4
5 6 - Sales
500 5,500 8,000 14,000 7,000
4,000 - Operating Expenses
800 3,410 4,960 8,680 4,340 2,480
- Product Promotion 3,000 1,000
- Depreciation
1,000 1,000 1,000 1,000 1,000 1,000 - Profit Before Taxes - 3,000 - 2,300
1,090 2,040 4,320 1.660 520 - Taxes _at_ 34 - 1,020 -
782 371 694 1,469 564 177 - Profit After Taxes - 1,980
-1,518 719 1,346 2,851 1,096 343 - Level of Working Capital
250 660 960 1,680 840 480
20New Product Introduction - Smith Corporation
- CAPITAL PROFIT AFTER TAX
WORKING TOTAL PRESENT -
- YEAR EQUIPMENT DEPRECIATION CAPITAL
CASH FLOW VALUE _at_20 - 0 - 6,000 - 1,980
- - 7,980
- 1,980 - 1 - - 518
- 250 - 768
- 640
- 2 - 1,719
- 410 1,309
909 - 3 - 2,346
- 300 2,046
1,184 - 4 - 3,851
- 720 3,131
1,510 - 5 - 2,096
840 2,936
1,180 - 6 - 1,343
360 1,703
570 - 7 660 -
480 1,140
318 -
NPV - 2,948
21Post-Evaluation Period Cash Flow Estimation
- The following equation can be used to estimate
the cash flows beyond some initial evaluation
period - CFn1
- TVn
- (k-g)
22Investments (Capital Budgeting)
Evaluation
Estimating Project Cash Flows
Replacement
New Products
Biases
Options
Guidelines
Positive NPV Reasons?
Inflation
Overoptimism
23Investments (Capital Budgeting)
Evaluation
Estimating Project Cash Flows
Replacement
New Products
Biases
Options
Guidelines
Positive NPV Reasons?
Abandonment (Gold Mine)
Strategic
Add-on Products
Vertical Integration
Related Diversification
24Investments (Capital Budgeting)
Evaluation
Estimating Project Cash Flows
Replacement
New Products
Biases
Options
Guidelines
Positive NPV Reasons?
Economies of Scale or Scope
Cost Advantages
Product Differentiation
Distribution Channels