Title: Yorkshire HAUC
1Yorkshire HAUC
- Delivering the Traffic Management Act 2004
Network Management Duty Intervention
Criteria Code of Practice for Coordination Fixed
Penalty Notices Permits
2Aims of the Traffic Management Act
- Clarity
- Parity
- Tackling congestion reducing disruption
3Why
Network Management Duty
- Potential impact of road congestion on the
economy - - delays cost 15 billion per annum
- DfT survey results
- - 90 of respondents consider road congestion a
serious problem - - Road works are the most annoying problem
4Network Management Duty
- Part 2 - Network Management by Local Traffic
Authorities - Duty
- a) secure the expeditious movement of traffic on
the authoritys road network and - b) facilitate the expeditious movement of
traffic on neighbouring - networks and traffic (including pedestrians).
5Network Management Duty
- In practical terms this means
- Free flowing network
- Reducing the impact of works, special events,
incidents etc - Monitoring and assessing performance
Each authority to appoint Traffic Manager
(statutory post)
6Yorkshire Traffic Managers
Network Management Duty
7Intervention Criteria
Network Management Duty
- A Traffic Director can be appointed and given
powers to - Monitor report on any matter
- Intervene in activities / carry out functions of
the local traffic authority - Recover the cost of intervention
- Intervention will result in penalties (the loss
of CPA stars!!) - Critical PI in the CPA Environment block
8Code of Practice for theCo-ordination of
StreetWorks and Works for Road Purposes
andRelated Matters
New Roads and Street Works Act 1991
9Code of Practice
Aim- to balance the rights of highway
authorities undertakers to carry out works with
the right of road users to expect the minimum
disruption from works
Objectives of Co-ordination
10Code of Practice
The Three Pillars of Co-ordination
Controls
Notices
Tools
11Code of Practice
The Noticing System
- 7 key functions
- Vital component of the co-ordination process
- Enable emergency notices responses
- Triggers inspection regime
- 4. Basis of records for reinstatement
guarantee periods - 5. Location records
- 6. Facilitates charging regime, and
- 7. Essential element of the street authority's
responsibility for - keeping a register.
12Noticing - Registerable Works
Code of Practice
- Covers street works, road works and major Highway
works that requires - breaking up or resurfacing of a street
- opening of the carriageway or cycleway of
traffic sensitive - streets at traffic sensitive times
- any form of traffic control
- reduction in lanes (3 or more lanes)
- temporary traffic reg order / notice or
suspension of pedestrian facilities - reduction in carriageway width of a TSS at TS
times
13Noticing - WORKS CATEGORY SELECTION
NO
NO
NO
14How do you decide what Notice to send?
Code of Practice
- Works Definitions based on durations
- Major Works - 11 days or greater
- Standard Works 4 to 10 days
- Minor Works 1 to 3 days
- Immediate Works (burden of proof with
undertaker) - Remedial Works
Early Starts are allowable
15How do you decide what Notice to send?
Code of Practice
16Noticing Points
Code of Practice
- Revised durations can be submitted but could be
challenged -
- (overrun charges applied where works are not
completed within the agreed duration) - Works Clear for interim reinstatements
- Works Closed for permanent reinstatements
- (permanent reinstatement to complete within 6
months following interim)
17Noticing Rules
Code of Practice
- Compliance with ETON
- Standard descriptions / S74 durations apply /
working day defined - One street One notice
- Works must not start before proposed date unless
otherwise agreed - Trench sharing
- Road closures portable traffic signals
- Frontages
- Error correction
- Notice cancellation
18Controls - Special
Code of Practice
- Street Classifications
- Restrictions
- Directions
19Controls - Street Classification
Code of Practice
- 3 main categories
- Protected streets
- Streets with special engineering difficulties
- Traffic-sensitive streets
Consultation process before designations can be
made
- Other features of a street
20Controls - Restrictions
Code of Practice
21Controls - Restrictions
Code of Practice
Exemptions
- Minor works which do not involve the breaking up
or excavating of - the highway
- Immediate works
- Customer connections
- HSE instruction
- Gas Safety Regulations
Good Practice Discuss with the local authority
any works impacting on restricted streets
Disagreements should be resolved by using
the Dispute resolution procedure
22Controls - Directions
Code of Practice
Section 56 Directions covering the times that
works either proposed, or subsisting can be
carried out
- Subject to 4 Constraints
- 1 undertakers retain right to execute emergency
works - 2 serious traffic disruption would be avoided
- 3 subsisting works causing / likely to cause
serious traffic disruption - 4 noise abatement of prevention legislation takes
precedence
23Controls - Directions
Code of Practice
Section 56A Directions covering restrictions
on placing apparatus in the street
- Subject to 3 Constraints
- It applies only to new apparatus
- it can only be used where disruption would be
reduced by installing - the apparatus in an alternative street
- it is reasonable
24Controls - Directions
Code of Practice
Section 66 covering avoidance of unnecessary
delay or obstruction
- Works to be completed as quickly as possible
- S66 notice can direct either to reduce or remove
obstruction - Must comply within 24 hours
25Code of Practice
- Applying Co-ordination Tools
- Co-ordination meetings
- - Sharing information as early as possible
- - Regular input and attendance
- - Sharing forward plans and programmes
- - Flexibility of programmes
- - Cross boundary working
26Fixed Penalty Notices (FPNs) Offences
Code of Practice
- Failure Code
- 01 Advance notice
- 02 Starting notice
- 03 Cancellation
- 04 Immediate (emergency works)
- 05 Reinstatement
- 06 Actual start revised duration
- 07 Works clear or closed
27Fixed Penalty Notices (FPNs) Offences
Code of Practice
- Amount of Penalty
- When a FPN is given the
- Amount of penalty is 120 (36 calendar days)
- Discounted amount 80 (if paid within 29
calendar days)
FPN must be issued within 91 calendar days
following the offence must have evidence
28Fixed Penalty Notices (FPNs) What do we
need to do to avoid an FPN?
Code of Practice
Right 1st Time
29Draft Code of Practicefor Permits
Traffic Management Act
Code of Practice for Permits
30Key features of Permit Schemes
Permits
- Requires approval from Secretary of State
-
- Can apply to all or some of the authoritys
network - Schemes can be in partnership between authorities
- Schemes can be in common with others
- Fees applied to every permit
- Disapplication modifications to sections of
NRSWA
31General Principles
Permits
- Key differences
- Promoters are required to book occupation of a
street - Start end dates fixed for Cat 0,1,2 and traffic
sensitive streets - Some flexibility on CAT 3 4 non-traffic
sensitive of start date - Timing of work more strictly controlled
- Conditions can be applied
32Permit application and response times
Permits
33Conditions
Permits
- Permit to include any constraints proposed in
application - Timing duration
- Road space
- Traffic management provisions
- Methodology
- Consultation publicity
- Environmental conditions
- Local conditions
- Immediate activities
34Variations
Permits
- Changing circumstances Activity Promoter /
Permit Authority - Extensions allowable
- Multiple excavations
- Circumstances beyond the authorities control
- No formal mechanism for suspension or
postponement - Cancellation notice
35Permits Maximum Fees
Permits
Note the scheme must operate on a cost neutral
basis on a year on year basis. Utility Impact
Assessment Required
36Permits Fixed Penalty Notices
Permits
- The penalties
- No permit - 500 (29 day payment discount to
300) - Condition breach - 120 (discounted amount 80)
37Permits
- KPIs for permit schemes
- Mandatory
- No. of permit and permit variation applications
received, the number granted and the number
refused - 2. No. of conditions applied by condition type
38Permits
- KPIs for permit schemes
- Optional (Must select at least 2 No optional
KPIs) - 3. No.of approved extensions
- 4. No. of occurrences of reducing the application
period - 5. No. of agreements to work in section 58 and
section 58A restrictions - 6. The proportion of times that a permit
authority intervenes on applications that would
normally be expected to be deemed - 7. No. of inspections carried out to monitor
conditions
39Implementation Timetable
40- From 1st April 2008
- Directions as to timing of street works and
placing of apparatus - Notices of street works
- Restriction on works following substantial road
works - Restriction on works following substantial street
works - Duty to notify street authority of reinstatement
41- From 12th May 2008
- Fixed penalty offences
- Permits (some time later Sheffield to progress
early)
42Traffic Management Act
- So, ..Street works Several elements some
significant effects - Changes to work categories duration based
- Notice periods longer advanced notice for S54
S55 - Definition of Registerable Activities
captures much more - S56 Direct both day and time of day
- S56A Direct (deny) routes for apparatus
- S58 Restrict access after Substantial Road
works 3 to 5 years - S58A Restrict access after Substantial Street
works up to 1 year - FPN offences potential for significant cost
consequences - Permit schemes more control by LHA fees
43Traffic Management Act
- and, ..Street works What do we need to do
- Improve data quality
- Improve timeliness
- Scenario planning with local authorities (e.g.
FPN offences) - Improve test our processes
- Prepare for Permit schemes
- Improve awareness
- Prepare our resources for implementation