LAT Quarterly - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

LAT Quarterly

Description:

height/width = 0.4 large field-of-view. Si-strip detectors: 228 mm pitch, total of ... Heather Kelly. Taro Kotani. Alexander Moiseev. ACD Reliability and ... – PowerPoint PPT presentation

Number of Views:72
Avg rating:3.0/5.0
Slides: 18
Provided by: OrmesL
Category:
Tags: lat | kelly | quarterly | tape | view

less

Transcript and Presenter's Notes

Title: LAT Quarterly


1
GLAST Large Area Telescope LAT Quarterly
Review ACD Subsystem Jonathan Ormes / Rudolph
Larsen NASA GSFC ACD Management
Jonathan.F.Ormes.1_at_gsfc.nasa.gov Rudolph.K.Larse
n.1_at_gsfc.nasa.gov
2
ACD Subsystem
  • Outline
  • LAT and ACD Design Overviews
  • ACD Organization and WBS Charts
  • Tile Detector Assemblies (TDA) Design Status
  • Tile Shell Assembly Design Status
  • Base Electronics Assembly Design Status
  • Studies Requested from February Review
  • Issues, Risks and Mitigations
  • ACD Near Term Milestones
  • Conclusions

3
LAT Design Overview
Instrument
16 towers ? modularity height/width 0.4 ?
large field-of-view Si-strip detectors 228 mm
pitch, total of 8.8 x 105 ch.
hodoscopic CsI crystal array ?
cosmic-ray rejection ? shower leakage
correction XTkr Cal 10 X0 ? shower max
contained GeV segmented plastic scintillator ?
minimize self-veto 0.9997 efficiency
redundant readout
Tracker
Calorimeter
Anticoincidence Detector
3000 kg, 650 W (allocation) 1.75 m ? 1.75 m ?
1.0 m 20 MeV 300 GeV
4
ACD Design Overview
Lip to "hide" thermal blanket and micro-meteorite
shield
Y
X
Tile Shell Assembly (TSA)
Base Electronics Assembly (BEA)
5
ACD Organization Chart
ACD Subsystem Code 600
Jonathan Ormes - Lead Investigator
ACD management Code 700
Rudy Larsen - Manager Cristina Doria-Warner -
Financial Resources Code
400.1 Dennis Wicks - Scheduling
ACD Design and Science support Code 661
Alexander Moiseev,Lead David Thompson, Robert
Hartman
David Bertsch, Jay Norris
ACD Reliability and Quality Assurance Code 303
Patricia. Huber, Lead
ACD Simulations Code 661
Tavi Alverez, Quality Tony DiVenti,
Reliability Nick Virmani,Thom Perry, Parts
(560) Fred Gross, PilarJoy, Materials (543) Bo
Lewis,Jim Anderson, Safety Chris Lorantson,
Contamination
Heather Kelly
Taro Kotani
Alexander Moiseev
Ground Support Facilities Equipment Code
543/564 Thomas Johnson / TBD Electronics Lead
Base Electronics Assembly Code 564
Flight Software R. Schaefer Code 664 moved
to LAT Flight Electronics SLAC
LAT Insrument Integration Test Code 568
Tile Shell Assembly Code 543
Micrometeroid Shield / Thermal Blanket Code 543/
545
Hardware/Software Integration Test Code 543 T.
Johnson, Lead
Mission Operation Data Analysis Code 661
Mission Integration Test Support Code 568
TBD, Lead
Thomas Johnson, Lead
Thomas Johnson, Lead Lou Fantano, Thermal
Lead
D.Sheppard, S. Singh,
John Lindsay, Lead
John Lindsay, Lead
David Thompson, Lead
Scot Murphy
Robert Baker
Tile Detector Assemblies Code 661
A. Moiseev, Lead
Code 600 - Space Sciences
Directorate 661 - Gamma Ray and Cosmic
Ray Astronomy 663 - Instrument Development 664 -
Data Management Programming
Code 543 - Mechanical Engineering
Branch 545 - Thermal Engineering
Branch 564 - Microelectronics and
Signal Processing Branch 568 - Flight Systems
Integration and Test Branch
Code 700.1 - Systems Technology, And
Advanced Concepts Directorate 740 -
Flight Instrument Division
Code 302 - Systems Reliability and Safety
Office 303 - Assurance Management Office
Code 400.1 - STAAC Business Management
Office
6
ACD Work Breakdown Structure
7
Tile Detector Assembly (TDA) Design
8
Tile Detector Assembly (TDA) Design
9
Tile Shell Assembly Design
10
Tile Shell Assembly Design
  • Worked on minimizing the volume of the ACD. This
    was in response to an increase in LAT Grid size
    and an increase in the height of the LAT
    Trackers.
  • Refined the TDA placement on the sides to
    minimize the overall volume of the ACD.
  • Continuing to work on routing of the fibers in
    the tiles.
  • Optimized the design of the shell to increase its
    overall stiffness to 50 Hz
  • Performed several trade studies to determine the
    optimum mounting interface between the shell and
    base frame

11
Base Electronics Assembly
12
Base Electronics Assembly Design
  • Photomultiplier tubes competitive procurement
    action initiated
  • baseline tube identified with flight heritage
  • 10 Qual units 1/02 40 EM units 6/02 210 FM
    units 3/03
  • Level IV Requirements Document recently drafted
  • Reliabilty Requirements balanced against cost
    have driven the Electronics Design
  • Topology of the Event Processor Board established
    with each board servicing 18 PMTs
  • Boards are no longer interconnected
  • Trigger Primitives are generated in the LAT
  • ACD Science team is investigating tile /
    electronics channel failure modes, effects and
    mitigations
  • Progress was made in the ACD to LAT electrical
    interface definition

13
Studies Requested at February Review
  • RD Testing Identify optimum design in terms of
    tile efficiency and light collection and map the
    response (light yield, efficiency) of a
    fiber/tile configuration in detail.
  • Determine testing methodology and construct test
    configuration -complete
  • Determine optimum fiber spacing in tile -complete
  • Determine optimum groove depth -complete
  • Determine tile thickness effects on light yield
    (linear with thickness?)
  • Determine edge effects -complete-no measureable
    effect
  • Determine tile uniformity
  • Determine effects of fiber end treatments
    (Alized ends)
  • Determine fiber length effects -complete, using
    low attenuation light transmission fibers
  • Determine MIP light yield, of PEs, and PMT
    gain requirements -complete
  • Production Testing Develop and implement test
    procedure and fixture to verify performance of
    every tile.
  • Experience derived from RD Testing will
    determine testing methodology and requirements
  • Milestones
  • Remaining RD Testing Completed September 1
  • Production Test Plan Completed September 1

14
Issues, Risks and Mitigations
  • Accelerated schedule - Issue risk to readiness
    for the LAT Preliminary Design Review.
    Mitigation hold the ACD Design Peer Review as
    scheduled and work all action items assigned.
  • Revised cost estimate - Issue threat to LAT
    budget
  • We are still over the proposal cost. Mitigation
    Complete redesign of ACD electronics shared use
    of LAT resources further ACD descope.
  • Mass constraint - Issue risk to efficiency,
    redundancy, and margin of the Anticoincidence
    Detector. Mitigation careful design additional
    mass request
  • Thermal blanket/micrometeoroid shield
    performance - Issue risk to durability of ACD
    over its lifetime. Mitigation agreement for
    design help from Johnson Space Center, which
    specializes in protection against penetrations.
  • Light collection from scintillator tiles -
    Issue affects efficiency throughout the life of
    the mission. Mitigation Tests to optimize the
    light collection and use of clear optical fiber
    transmission lines.

15
Issues, Risks and Mitigations
  • Gaps between scintillator tiles - Issue Lowers
    Background rejection efficiency. Mitigation
    cover gaps with scintillating tapes in one
    dimension and overlap detector tiles in the
    other.
  • Electronics Cost - Different cost estimates
    within GSFC and between GSFC and SLAC. Mitigation
    is all parties meet to understand differences and
    reach agreement.
  • Reliability Requirements - To yield higher
    reliability number Micrometeoroid Shield may need
    thickening which could lead to higher background.
    Mitigation is more analyses are needed.
  • Background entering at the edge of the bottom of
    the ACD - Mitigation
  • is further analyses needed. Preliminary look
    says its not a problem.
  • LAT other subsystems ability to compensate for
    loss of effective area - Mitigation is also
    further analyses.

16
ACD Near Term Milestones
17
Conclusions
  • ACD Design Peer Review shows significant progress
    in preparing for the October LAT Instrument
    Review
  • Respondees to the Peer Review Action Items have
    been identified along with an internal GSFC due
    date of September 21.
  • Major open issue is ACD cost.
Write a Comment
User Comments (0)
About PowerShow.com