Title: Financial Management MW
1Financial Management (MW)
- Office of the Chief Financial Officer
- Gwen Sykes
- November 9, 2005
2Background
- This management control issue was introduced in
2001 as a significant area of concern because the
core accounting system was not operational and it
remained open until May 2003 when it was
designated as an Other Weakness based on the
new Internal Control rating schema. - In October 2003, the OCFO had made significant
progress toward improving the Agencys financial
statements, budget and execution documents, and
other accounting reports. At that time, the
deficiency was reduced to a Management Challenge. - In May 2004, it was elevated to a Material
Weakness because the scope of the Core Financial
Management System had the potential to impact the
entire Agency.
2
3Issue
- Since implementation of the Core Financial
Management System, challenges in system
processing, configuration, and capabilities have
surfaced that have resulted in data anomalies
(data integrity) and instances of non-compliance
with prescribed federal accounting policies and
procedures. OCFO was a decentralized
organization that lacked sufficient numbers of
adequately trained staff guided by one set of
NASA-wide policies and procedures. - Root cause
- Conversion from 10 disparate legacy financial
systems supported by over 120 subsidiary systems,
along with over a decade of historical data, to a
single integrated financial management system
highlighted long-standing data and process issues - System processing issues in early stages of
production operation resulted in data integrity
problems, impacting external financial reporting - Introduction of new system and processes has
presented a tremendous learning curve for users
which pre-implementation training did not fully
address - Migration to a single agency-wide core financial
management system requires a single set of
financial management policies and procedures - Reduced staffing levels has deteriorated ability
to maintain sufficient numbers of adequately
trained resources to address post implementation
challenges from the new financial system
implementation and other systemic financial
management challenges
3
4Issue (continued)
- Corrective action taken to date
- Reconciled our differences with FBWT to within
22 million as of 8/30/2005. - Developed a uniform automated tool to assist all
Centers in reconciling FBWT that will be
operational to start FY 2006. - Significant progress made on hiring OCFO staff.
- Issued Monitoring Controls document for Centers
compliance on a monthly basis.
4
5Recommendation
- Recommend that the current deficiency (MW-2004-1)
be closed and a new Material Weakness be opened
with the following description - The implementation of the IFMP Core Financial
system during FY 2003 represented a major
transformation in NASAs financial management
systems and processes. Challenges from this major
change were anticipated, however, it has taken
much longer than expected to stabilize our
overall financial management environment. Since
the completion of the rollout of the new system,
challenges in system processing, configuration,
and capabilities have surfaced that have resulted
in data anomalies (data integrity) and instances
of non-compliance with prescribed federal
accounting policies and procedures. Further, the
OCFO was a decentralized organization that lacked
sufficient numbers of adequately trained staff
guided by one set of NASA-wide policies and
procedures.
5
6Contractor-Held Property (MW)
- Office of the Chief Financial Officer
- Gwen Sykes
- November 9, 2005
7Background
- This deficiency was introduced in February 2003
as a Material Weakness with planned actions to
include monthly reporting by contractors
publication of a Federal Management Regulation
for Property, Plant, and Equipment and
initiation of contractor and accountant training. - In October of 2003, the deficiency was reduced to
an Other Weakness when the OCFO completed the
tasks of defining assets in space and issuing
revised policy. - In October 2004, the deficiency was re-designated
as a Material Weakness when the IG questioned the
accuracy and reliability of property related
accounting data.
2
8Issue
- NASA needs to improve its management controls for
the financial reporting of property, plant and
equipment, and materials including Theme Assets
(formerly Assets-in-Space), contractor-held
property, spare parts and assets under
construction. Lack of proper management controls
can result in inconsistent financial recording
practices that can misstate asset values and
period expenses. - Root cause
- 1) NASAs policies and procedures not fully in
conformance with federal requirements - 2) Inconsistent application of existing policies
and procedures - Corrective action taken to date
- Establishment of Financial Integration Team,
subgroup on PPE composed of the Deputy Chief
Financial Officer, Associate Administrator for
Infrastructure and Administration, and Director
of Procurement. - Presentation to and support received from the
Senior Advisory Group on the overall plan to
improve NASA's PPE internal controls and
financial reporting. - Established PPE Compensating Controls Group
comprised of HQs and Center representatives. - Prepared draft Theme Assets capitalization policy
paper and submitted to OIG and external auditors
for review and comment.
3
9Recommendation
- Recommend closing the current Material Weakness
(MW-2004-02 - Contractor-Held Property) and
replacing it with a deficiency that captures the
overall scope of property related challenges. - Recommend responsibility for this Material
Weakness be shared by the OCFO and Institutions
and Management.
4
10Full Cost Integration (OW)
- Office of the Chief Financial Officer
- Gwen Sykes
- November 9, 2005
11Background
- In February 2003, the Associate Administrator for
Earth Science pointed out that full cost
accounting is a major Agency undertaking that
should be monitored and placed on the agenda as a
Management Challenge. - In February 2005, the OCFO recommended the
initial Full Cost Accounting MC be closed based
on actions taken by the FC Steering Committee.
The committee chair ordered that MC-03-03 be
removed as an exception, and instructed that Full
Cost Integration be created as the new MC. - In May 2005, the significance level was elevated
from a Management Challenge to an Other
Weakness, due to a perceived lack of
understanding of full cost policies and
procedures.
2
12Issue
- Full Cost concepts need to be better integrated
into NASA operations. Despite implementing a Full
Cost accounting system and many Full Cost
processes, NASA still lacks the level of cultural
change needed to fully transition to Full Cost
management. - Root cause
- Insufficient stakeholder training
- Unintended consequences and behaviors realized
from initial full cost approaches - Some policies and planned processes were based on
insufficient experience and need to be refined to
reflect lessons learned - Corrective action taken to date
- Completed Full Cost Assessment
- Delivered recommendations to the Financial
Integration Team on improving full cost
implementation - Continuing to improve policy to resolve
operational issues - Developing requirements for multiyear long-term
plan to institutionalize full cost in NASA's
operational culture.
3
13Recommendation
- Recommend this issue remain as currently assigned
(Other Weakness).
4
14Space Shuttle
- Space Operations Mission Directorate
- William H. Gerstenmaier
- November 9, 2005
15Background
- Following loss of Columbia and her crew, the
Deputy Associate Administrator for International
Space Station and Space Shuttle Programs
established a formal "Return-to-Flight Planning
Team", and provided direction for the team to
address actions required before a safe return to
flight could be assured, and other actions
determined necessary to comply with the formal
recommendations of the CAIB. Options and
recommendations from the Return-to-Flight
Planning Team were assessed by the Space Flight
Leadership Council, which was established for
this purpose and was co-chaired by the Associate
Administrator for Space Operations and the Deputy
Chief Engineer for Independent Technical
Authority. Return-to-flight actions were
implemented through the normal Space Shuttle
Program management. The Council abolished on
June 28, 2005, and all actions are now conducted
through the Space Shuttle Program management. - Progress on implementation of Return to Flight
actions is documented in the "Implementation Plan
for Space Shuttle Return to Flight and Beyond"
issued periodically.
2
16Issue
- Technical Deficiencies
- Modeling was not as accurate when the Shuttle
system was originally certified in the late
1970s Debris Transport Analysis was more art
than science (point to point transport) and the
analyses that was done was rarely supported with
rigorous testing (e.g., wind tunnel testing,
impact testing). - All pre-STS-107 flight history seemed to support
the initial certification analyses. - Foam damage to the Orbiter failed to show
positive correlation between liberated debris
mass and TPS (tile) damage. - Post-STS-107 modeling told us where debris might
strike the Orbiter, however, it was impact
testing that defined critical debris (mass)
thresholds for return to flight. This testing
showed us how fragile the Orbiter was to
different materials and masses. At that point,
we knew we would have to eliminate all the
critical debris sources, provide much improved
debris impact monitoring, and determine to what
extent we needed to harden the Orbiter before we
could Return to Flight. - While STS-114 proved we had done a very credible
job of eliminating critical debris, five In
Flight Anomaly foam loss events made it clear
additional work is required before the second RTF
mission to increase our understanding of the
cause of these foam debris events and taking the
appropriate corrective actions. This work is
currently on-going. - Other Deficiencies
- The Final Report of the Columbia Accident
Investigation Board (CAIB) identified a number of
systemic cultural, organizational, and managerial
issues within both the Space Shuttle Program and
NASA as a whole that contributed to the loss of
Columbia on February 1, 2003.
3
17Issue (continued)
- Root cause
- The physical cause of the loss of Columbia and
her crew was a breach in the Thermal Protection
System on the leading edge of the wing, caused by
a piece of insulating foam which separated from
the left bipod ramp section of the External Tank
at 81.7 seconds after launch, and struck the wing
in the vicinity of the lower half of Reinforced
Carbon-Carbon panel number 8. - The Final Report of the Columbia Accident
Investigation Board (CAIB) identified a number of
systemic cultural, organizational, and managerial
issues within both the Space Shuttle Program and
NASA as a whole that contributed to the loss of
Columbia on February 1, 2003. - Fifteen Return-to-Flight and fourteen continuing
to fly recommendations are in the CAIB Report.
Four dealt explicitly with management issues, and
many of the other recommendations have important
organizational as well as technical implications.
- The CAIB Report also calls on NASA to prepare a
detailed plan for defining, establishing,
transitioning, and implementing these
recommendations prior to Return to Flight, with
the understanding that the implementation of the
fundamental management changes will continue
beyond the first Shuttle flight after Columbia.
4
18Issue (continued)
- Corrective action taken to date
- In response to the CAIB report, NASA developed
the Implementation Plan for Space Shuttle Return
to Flight and Beyond. The Implementation Plan is
an evolving blueprint for safely and reliably
returning to flight. It explains how NASA is
complying with the recommendations of the CAIB
and other corrective actions. These additional
corrective actions may include other CAIB
observations, self-imposed Shuttle program
initiatives or input from other sources. - On August 17, 2005, the Return to Flight Task
Group released its Final Report. In it, the Task
Group unanimously closed out all but three of the
Board's Return to Flight recommendations. The
Task group noted NASA had made substantial
progress relative to these recommendations, and
emphasized that, "The ability to fully comply
with all of the Board's recommendations does
not imply that the Space Shuttle is unsafe." The
first two Return to Flight missions, STS-114 and
STS-121, will provide the data and flight
experience needed to address the remaining open
issues in these recommendations. This work will
be documented in future updates to the
Implementation Plan.
5
19Issue (continued)
- NASA made the decision to proceed with the launch
of STS-114 on July 26, 2005 based on Return to
Flight Task Group's assessment, the totality of
improvements made to the Space Shuttle system
during Return to Flight, and the vetting of all
these improvements through a rigorous and
multilayered engineering review process,
culminating in the approved Certificate of Flight
Readiness. - Post-flight analysis of STS-114 indicated that,
except for one event, the thermal protection
system on the External Tank performed within
expected parameters. Most of the small foam
shedding events that were observed with the newly
upgraded imagery and sensor capabilities posed
little or no threat to the Orbiter. The one
event of concern was the loss of an approximately
one pound piece of foam from the area of the
External Tank's liquid hydrogen protuberance air
load (PAL) ramp. NASA commissioned two teams
(one lead by the Space Shuttle propulsion
manager, the other an independent "Tiger Team"
reporting directly to the Associate Administrator
for Space Operations) to analyze these foam loss
events and recommend any forward work that would
have to be done prior to the launch of the next
mission, STS-121.
6
20Recommendation
- Until successful completion of STS-121, this item
should remain a material weakness.
7
21Shuttle Impact on ISS Operations
- Space Operations Mission Directorate
- William H. Gerstenmaier
- November 9, 2005
22Background
- Following the Shuttle Columbia accident, February
2003, the ISS Partnership agreed to an interim
operational plan that would allow continued
crewed operation. The plan called for a
reduction of the crew size to two, with the crew
exchanges to be conducted on the scheduled
semi-annual Soyuz flights. Cargo re-supply would
be provided by Russian Progress vehicles. This
is an interim measure until the Space Shuttle
returns to flight. - The first of two Shuttle Return to Flight
missions has been completed, STS-114, launched on
July 26, 2005 and landed on August 9, 2005. -
2
23Issue
- Description of deficiency
- The International Space Station (ISS) was
designed with the Space Shuttle as its prime
support for crew transport, assembly of on-orbit
elements, utilization and operations. Additional
crew and cargo transport is provided by Russia.
Following the Space Shuttle Columbia accident,
the Shuttle fleet was grounded. This has impacted
the number of crew that can be supported onboard
the ISS, temporarily halted assembly of the
Station, and significantly reduced the available
up and down mass support for Station operations
and utilization. - Root cause The grounding of the STS fleet
resulted in this impact on ISS operations. -
3
24Issue
- Corrective action taken to date
- Established an understanding with the ISS
partnership to (1) rely on Russian vehicles for
crew and cargo support until Shuttle returns to
flight and (2) reduce the crew size from 3 to 2
to reduce the logistics burden, given the reduced
capability of the Russian vehicles compared to
the Space Shuttle. - Successfully completed the ISS objectives for the
STS-114 mission - Flew the combined Space Shuttle/ISS stack in a
new configuration designed to minimize the threat
of orbital debris and micrometeorite impact
damage. - Transferred more than 15,000 pounds worth of
supplies and hardware to the ISS, including food,
water, nitrogen, lithium hydroxide canisters, and
scientific equipment. - Returned more than 7,200 pounds worth of expended
hardware and unneeded supplies from the ISS back
to Earth. Returning this hardware allows for
failure analysis and possible reuse of Russian
Elektron (oxygen generation) and Kurs (for
docking of Russian Soyuz and Progress vehicles)
hardware, as well as U.S. components like a
Control Moment Gyroscope (CMG), Global
Positioning System sensor, and spacesuit.
4
25Issue
-
- Repaired and/or replaced two of the ISSs four
CMGs (which provide attitude control for ISS),
restoring the Station to its full capability. - Installed the External Stowage Platform-2, an
external platform for storing components and
assisting astronauts in conducting EVAs from the
ISS, transferred the Human Research Facility-2
rack to the U.S. Destiny module on the ISS
(increasing the scientific capabilities of the
Station), and deployed and retrieved the
Materials International Space Station Experiment
Passive Experiment Containers from the outside of
the ISS. - Reboosted the orbit of the ISS and conducted a
fly-around and completed photographic survey of
the ISS prior to reentry. - Between STS-114 and STS-121, we will continue to
rely on Russian crew and cargo services. ISS
assembly will resume with STS-115.
5
26Recommendation
- Until successful completion of STS-121, this item
should remain a management challenge.
6
27Information Technology Security
- Office of the Chief Information Officer
- Scott Santiago
- November 9, 2005
28Background
- The NASA OIG, through their audits of NASAs IT
Security Program, had identified a large number
of findings over the years that led them to
recommend that IT Security be declared a
Material Weakness. - NASA has been working since FY 2003 to correct
the findings of those audits and to correct
systemic problems with - ITS Policy and Procedural Requirements
- ITS Compliance Execution
- Because of the work in progress, NASA management
has determined that IT Security be an Other
Weakness.
2
29Issue
- Root Cause
- NASA IT Security, while improving, needs more
effective implementation, monitoring, and
enforcement. In addition, NASAs policy and
procedures have not kept up with OMB direction
regarding implementation of the Federal
Information Security Management Act (FISMA). - OMB continues to focus attention on IT Security,
which requires NASA to make significant changes
in how IT Security is managed.
3
30Issue
- Corrective action taken to date
- Rewrote NASA IT Security policy and requirements
documents to reflect NIST Guidance as directed by
OMB, pending approval. - Establishing a central database of all NASA
systems and IT Security plans status and added a
module to CATS for tracking all IT Security
weaknesses according to FISMA. - Established a certification and accreditation
(CA) program as Directed by OMB NIST SP 800-37
Guide for the Security Certification and
Accreditation of Federal Information Systems. - Expanded the NASA ITS training program.
4
31Issue
- Corrective action taken to date
- Improved Incident reporting and tracking
- Establishing centrally-managed monitoring of the
NASA network - Establishing centrally managed security services
to correct known security weaknesses in managing
sensitive information and to meet HSPD-12
requirements - Established Agency metrics (ITS Scorecard) based
on internal and external ITS performance
requirements
5
32Recommendation
- Continue to categorize NASAs IT Security Program
as an Other Weakness (OW) until changes are
implemented and they begin to demonstrate the
required results.
6
33Competition in Contracting
- Institutions and Management
- Office of Procurement
- Tom Luedtke
- November 9, 2005
34Background
- In FY 04, the OIG issued a report stating NASA
continues to be challenged in promoting
competition in contracting - Audits and reviews performed over a 24 month
period found several instances where competition
was not pursued and the lack of competition was
not adequately justified - OIG stated basic management controls are needed
to provide reasonable assurance that competition
is maximized where practical
2
35Issue
- Description of deficiency
- Per the OIG, NASA continues to be challenged in
promoting competition in contracting, and - Basic management controls are needed to provide
reasonable assurance that competition is
maximized where practical and justifications for
noncompetitive procurements meet regulatory
requirements. - Root cause
- Federal and NASA procurement policies require the
use of competition to the fullest extent possible - Audit and reviews performed found several
instances where competition was not pursued and
lack of competition was not adequately justified
3
36Issue (cont)
- Corrective action taken to date
- All previously opened recommendations have been
closed - Office of Procurement has issued new guidance for
establishing reasonable response time in synopses
for commercial procurements - Survey teams have focused on the documentation of
efforts made to remove or overcome any barriers
to competition - Centers utilize Resource Consultants, Inc. for
the purpose of providing Contracting Officer
Technical Representative (COTR) certification
training and refresher training. COTR
certification class includes a section on
competition in contracting
4
37Recommendation
- Competition in contracting should be removed from
the list.
5
38Access to NASA Facilities Technology
- Office of Security and Program Protection
- Clint Herbert, Deputy Assistant Administrator
- November 9, 2005
39Background
- NASA's previous photo-ID issuing policy and
procedures had numerous shortcomings that needed
to be revamped in order to ensure that only
authorized persons gain access to NASA
facilities. Each Centers photo-ID producing
equipment produced a differing photo-ID then that
established under the previous NASA standards. To
compound the issue, some former employees have
been non-compliant in returning their badges, and
continue to gain access to NASA facilities
uninhibited. Current NPR establishes new
standards for both equipment and photo-ID
topology.
2
40Issue
- Description of deficiency
- NASA's current photo-ID issuing policy and
procedures have numerous shortcomings that must
be revamped in order to ensure that only
authorized persons gain access to NASA
facilities. To compound the issue, some former
employees have been non-compliant in returning
their badges, and continue to gain access to NASA
facilities uninhibited. This leaves NASA
extremely vulnerable to security breaches by
individuals who no longer have a need to access
NASA facilities and by adversaries who could
easily produce a counterfeit NASA photo-ID. NASA
also recognizes its vulnerabilities relating to
issuing NASA photo-IDs, accessing, and accounting
for foreign national (FN) (non-U.S. citizens)
visitors, contractor employees, and other FN
assignees. - Root Cause
- While NPR 1600.1 sets specific standards for
photo-IDs, non-standardized equipment causes the
appearance of photo-IDs (e.g., color, font,
topography) to vary from Center to Center, making
it impossible for any one Center to positively
identify another Center's badge as being
authentic. Multiple badge types at the agency
have led to problems with managing access to NASA
facilities technology. - Corrective Action Plan (CAP)
- Standardize the NASA photo-ID generating,
issuing, and accountability technology to ensure
consistency and uniformity. The ultimate goal of
the OneNASA - photo-ID system is to upgrade the
system to current technologies, establish an
enterprise architecture deter counterfeiting, and
prohibit unauthorized individuals (anyone other
than current NASA employees/contractors) from
freely accessing NASA facilities. STATUS Systems
procured and deployed at all Centers, IATO
issued, generation and issuance of CS photo-IDs
to has begun at NASA Centers and is scheduled to
begin at HQs mid/end November. Issuance of
contractor photo-IDs to commence shortly
thereafter.
3
41Recommendation
- Remove from issues list and closeout.
- Rationale New NPR issued, new OneNASA
Photo-IDs being issued at all Centers.
4
42Declassification Review ProcessManagement
Challenge (MC)
- Office of Security and Program Protection
- Clint Herbert, Deputy Assistant Administrator
- November 9, 2005
43Background
- NASA had a significant backlog of permanent
records containing classified national security
information (CNSI) that needed to be reviewed for
continued classification pursuant to EO 12958
amended. NASA faces a December 2006 deadline to
insure that all permanent records containing CNSI
that are 25-years old or older are subjected to
classification review. Poor records management
practices prevented the identification of records
subject to Section 3.3 of EO 12958 amended
resulting in NASAs inability to identify its
total universe to be considered for
declassification. The identified root causes had
significantly impeded the classification review
programs efforts. EO 12958 as amended contains
a sliding-window requirement for NASA to conduct
yearly classification reviews of permanent
records containing CNSI.
2
44Issue
- Deficiency Description
- NASA has a significant backlog of permanent
records containing classified national security
information (CNSI) that must be reviewed for
continued classification pursuant to EO 12958
amended. NASA faces a December 2006 deadline to
insure that all permanent records containing CNSI
that are 25-years old or older are subjected to
classification review. Poor records management
practices prevents the identification of records
subject to Section 3.3 of EO 12958 amended
resulting in NASAs inability to identify its
total universe to be considered for
declassification. The identified root causes have
significantly impeded the classification review
programs efforts. EO 12958 as amended contains
a sliding-window requirement for NASA to conduct
yearly classification reviews of permanent
records containing CNSI. - Root Causes
- Insufficient staffing
- Historically poor records management
- Insufficient funding
- Lack of Declassification Guides
- Insufficient resident expertise to perform
classification reviews for older programs - Insufficient support from senior management
(commitment of resources) - Corrective Action Plan (CAP)
- A comprehensive CAP has been developed and has
been distributed to the OC, all Mission
Directorates, and Center Security Offices on 2
November 2005.
3
45Recommendation
- Closeout. NASA has made significant progress in
declassification efforts and is now positioned to
meet the December 31, 2006 deadline.
4
46Staffing at NASA Headquarters
- Institutions and Management
- Jeffrey E. Sutton
- November 9, 2005
47Background
- NASA Headquarters managers have reported
difficulty in recruiting and hiring personnel
with the experience needed to address key areas.
During a pre-audit review, the NASA HQ policy
staff found errors in the delegated examining
(DE) activities that were significant enough to
warrant withdrawing the DE authority from the HQ
Human Resources Office. An OPM audit
substantiated NASA's initial findings and
identified additional errors and deficiencies in
the DE actions. OPM also found deficiencies in
competitive promotion actions in instances when
the vacancy was announced under both DE and merit
promotion procedures. As a result, the absence
of an effective recruitment capability at HQ has
led to significant important vacancies in the
Office of the CFO and other HQ organizations.
Delays in staffing the CFO Office stymies
progress in mitigating the declared material
weaknesses in financial management and contractor
held property.
2
48Issue
- Deficiency Description
- The absence of an effective recruitment
capability at HQ has led to significant important
vacancies in the Office of the CFO and other HQ
organizations. Delays in staffing the CFO Office
stymies progress in mitigating the declared
material weaknesses in financial management and
contractor held property. - Root Cause
- Withdrawal of DE authority was caused by
inadequate staffing and training of staff,
leadership and organizational inefficiencies, and
poor or non-existent operational procedures.
These root causes led to improper personnel
processing, poor customer service and violation
of OPM regulations. - Corrective Action Plan (CAP)
- The CAP focuses on establishing proper operating
procedures creating oversight of operations
staff creating new customer service standards
hiring additional staff contractors provision
of basic HR training in NASA STARS recruiting
staffing procedures regulations reorganization
of the HQ HR office to a consulting model
providing more effective efficient management
leadership.
3
49Recommendation
- Close this Management Challenge
4
50Open OIG Audit Recommendations
- Institutions and Management
- Jeffrey E. Sutton
- November 9, 2005
51Background
- By early 2000, the number of open OIG
recommendations had become unmanageable. In
December 1998 there were approximately 76 in
October 2001 there were 523 open and 40
unresolved recommendations. - The Operations Council placed this item on the
list to bring visibility. - Significant work by both the new NASA OIG and
management has resulted in a steady downward
trend. - By October 31, 2005 there were 37 open and no
unresolved recommendations.
2
523
53Recommendation
- Continue to give this appropriate management
attention, but no longer report it as a
Management Challenge
4
54Open GAO Audit Recommendations
- Institutions and Management
- Jeffrey E. Sutton
- November 9, 2005
55Background
- As a result of an increase in GAO audit activity
specific to NASA, highly visible and politically
sensitive GAO audits (e.g., Mission Management
Aircraft), and continued Congressional interest
in the health of NASAs financial management, the
Operations Council agreed to add the status of
GAO audit recommendations as a Management
Challenge in order to keep senior management
appraised of GAO audit activity.
2
563
57Recommendation
- Continue to carry this as a Management Challenge
- Work with the appropriate offices and management
to address the open and unresolved
recommendations - Re-institute regular meetings with the
Administrators office to provide status of GAO
recommendations
4
58Mission Management Aircraft (OW)
- Infrastructure and Administration
- Jeffrey Sutton
- November 9, 2005
59Background
- GAO audit of Agencys FY03 and FY04 Mission
Management Aircraft (MMA) operations highlighted
control deficiencies with respect to management
of NASAs MMA. - MMA operations were also questioned in several
prior GAO and NASA IG audit reports.
2
60Issue
- Inadequate documentation and periodic review of
MMA mission requirements - Issued NPR 7900 Interim Change for HQ approval of
all mission required flight designations - Supporting PAE review of MMA requirements
- Insufficient HQ oversight
- Augmenting HQ AMD staff for MMA
- Instituted annual HQ review of Center MMA
operations - Lack of integrated IT system to capture and
report aircraft cost utilization - Funding NASA Aircraft Information System (NAMIS)
- Facilitating Aircraft Cost Accounting PAT
3
61Recommendation
- Continue to carry this as an Other Weakness
4
62NASA Rules Review
- Institutions and Management
- Jeffrey E. Sutton
- November 9, 2005
63Background
- Each OIC at Headquarters was tasked to review all
their rules and regulations, to cancel any
documents that were no longer required, and to
strip the remaining documents of any and all
instructions that are advisory, ambiguous, or
just guidance.
2
64Issue
- Deficiency Description
- Agency and Headquarters directives that are
merely advisory in nature cause uncertainty about
their application to the workforce. Any
documents that are no longer required are to be
cancelled or stripped of any instructions that
are advisory, ambiguous, or just guidance. - Root Cause
- Decision-making processes that operate outside
the organization's rules (from p. 177 of CAIB
Report) - Corrective Action Plan (CAP)
- Phase 1 Complete document inventories to show
which directives to retain and which to cancel.
Completed 2/15/04. - Phase 2 Edit the retained directives as follows
(Completed 3/12/04) - (1) delete requirements and supporting
information that are no longer needed - (2) delete references that are not specific to
the content of the document - (3) boldface requirements to clearly distinguish
them from explanatory material or supporting
text - (4) correct administrative errors.
- Phase 3 Establish a clear document hierarchy
apply a holistic - approach to NASA rules define and establish
criteria for documenting requirements and define
and establish processes for review and
enforcement. Completed 3/1/05
3
65Recommendation
- Close this Management Challenge
4
66Space Exploration and the Iran Nonproliferation
Act of 2000 (INA)
- Office of Strategic Communications
- Joe Davis
- November 9, 2005
67Background
- The INA was signed into law by President Clinton
in 2000. - The International Space Station (ISS) and human
space flight activities were singled out as the
only cooperative program and used as leverage
because in 2000 Russia was highly dependent on US
fundingthat is no longer the case. - INA Section 6 restricts USG payments, in cash or
in kind, to certain Russian entities for work
related to human space flight, including the ISS.
- NASA, as part of an interagency effort, engaged
Congress to develop a legislative solution to INA
that would allow the Agency to purchase of goods
and services from Russia, including essential
Soyuz crew rescue services, to continue U.S.
permanent presence aboard the International Space
Station (ISS).
2
68Working Towards a Solution
- On July 12, 2005, the Administration submitted to
Congress a proposed amendment to the INA and
recommended that the amendment be added to NASA
authorization legislation or another appropriate
legislative vehicle. - On September 19, 2005, the Senate, by Unanimous
Consent, passed S. 1713, allowing NASA to procure
required goods and services from Russia to ensure
the continued safe operation of the ISS until
January 1, 2012. - On October 26, 2005, the House of
Representatives, by voice vote, passed an amended
version of S. 1713 which added sanctions language
related to Syria and Iran. However, the measure
still allows NASA to procure Russian space goods
and services to support the assembly and
operation of the ISS between now and January 1,
2012. - The House-amended S. 1713 was received in the
Senate on October 27, 2005. Unanimous Consent
clearance is in process and we are awaiting final
passage.
3
69Recommendation
- Recommend removal of INA action from the internal
deficiencies list, as passage of an amendment
securing relief is imminent.
4
70Internal Controls on Releasing Program/Project
Cost Estimates
- Office of the Chief Engineer
- Keith Hudkins
- November 9, 2005
In coordination with OCFO, PAE, Legislative
Affairs Mission Directorates
71Action
- Responsible Office Office of the Chief Engineer
- Description Clarify/establish the internal
controls for releasing estimated Cat 1 Program
and Project life cycle cost from pre-formulation
through the life of the program. - Objective Today Approve concept
Different than action in the last meeting
minutes
2
72Concept for a Solution
- A controlled process for releasing cost estimates
- Add requirement for PAE and the Mission
Directorate to agree with Program Assumptions for
the cost estimate - Add requirement for a Council (SMC or PMC) to
reconcile any differences - Add requirement for all Cat 1 New Starts (i.e.,
JWST, Constellation, Shuttle Upgrade) to be
communicated using PAE cost estimates in terms
of assumptions, cost ranges and schedules for a
firm commitment - Add requirement to keep these cost estimates and
assumptions under configuration control
3
73Lifecycle and Cost Estimates
SRR P-NAR Cost Est Update
PDR NAR Firm Cost Commitment
PAE Cost Est.
FAD
Pre Formulation
PAE Mission Dir Assumptions
CADRe (lite)
CADRe (full up)
Note Proposed addition listed in red italics
4
74Recommendation
Forward Action
Work with OCFO, PAE, Mission Directorates to
implement concept in Agency Policy
5
75Back Up Slides
6
76Action Plan
- We collaborated with OCFO, PAE, Legislative
Affairs, and Mission Directorates to draft a
process to control and communicate early
program/project cost estimates - Plan to update NPR 7120.5, NASA Cost Estimation
Handbook, and NASA Strategic Management and
Governance Handbook as required - Plan to implement and monitor the process for
early cost estimates
7
77Background
- Following GAO Report GAO-04-642, May 2004 NASA
has increase improved its guidance and controls
for cost estimates - Release of NASA Cost Estimation Handbook,
December 2004 - Inclusion of Cost Estimate requirements in
updated NPR 7120.5C, NASA Program and Project
Management Processes and Requirements - Cost Analysis Data Requirement (CADRe)
- Concern over the cost growth for the James Webb
Space Telescope from Pre-Phase A through
mid-Phase B raised this issue to an ICC Action
Item (1,072M growth) - Both Program and Independent Cost Estimates were
conducted in FY04 FY05
8
78Background
- Key Reference Material
- 1. NASA - Lack of Disciplined Cost-Estimating
Processes Hinders Effective Program Management,
GAO-04-642, Report to the Committee on Science,
House of Representatives, May 2004. - 2. NASA Cost Estimation Handbook, December 2004
(available at http//www.ceh.nasa.gov/) - 3. Letter, Implementation of Cost Management
Initiatives, Fred Gregory, December 23, 2004 - 4. NPR 7120.5C, NASA Program and Project
Management Process and Requirements, March 22,
2005 - 5. NASA Special Review of the James Webb Space
Telescope, July 28, 2005
9
79Partial List of Participants
- Mary Kerwin
- David Graham
- Arlene Moore
- Joe Hammaker
- John Kelly
- Mike Blythe
- Keith Hudkins
- Margaret Kieffer
- Jo Gunderson
- Stan Fishkind
- Lisa Guerra
- Rob Anderson
- Ken Ledbetter
10