Title: McKinney Healthy Lakes
1McKinney Healthy Lakes Streams
Eldorado Lakes (Site 5A) - Sediment Removal
Project
McKinney, Texas June 11, 2008
2Purpose of Meeting
- Discuss the project to remove and dispose of
sediment from Eldorado Lake (Site 5A). Sediment
will be removed from the Main Lake, and Lower and
Middle Lakes located upstream of the Main Lake. -
3McKinney Healthy Lakes Streams
Final Master Plan
McKinney, Texas February 2006
4Background
- The Master Plan provides the Citys plan of
action to restore, maintain or improve the health
of the 18 floodwater-retarding structures
(lakes) and about 77 miles of streams within the
city limits of the City of McKinney and its
Extraterritorial Jurisdiction (ETJ).
5Background (continued)
- Significant Points
- Most of the dams are in need of upgrade in order
to extend their useful life. - Most have significant amounts of sediment.
- Significant erosion in the streams.
6Comegys Creek Erosion
7Background (continued)
- Significant Points
- ? A dedicated City Drainage crew has completed
improvements on several drainage projects. - Removal of sediment from Site 5A identified as a
high priority project. - Six dams have been upgraded to current design
criteria. (One is currently under construction by
TEI Construction Inc.)
8A Lake Full of Sediment
9McKinney Healthy Lakes Streams
Eldorado Lakes (Site 5A) - Sediment Removal
Project
McKinney, Texas June 11, 2008
10Existing Conditions
- Significant Points
- Site 5A was constructed in 1958 as a low hazard
floodwater retarding structure with a 50 year
design life. - The Lower Lake was created as part of the golf
course. - The Middle Lake was created as part of the
development. - Sediment has previously been removed.
11Section of a Typical Floodwater Retarding
Structure Storage in Pool
12Existing Conditions
- Significant Points
- A recent study indicates there are about 80,500
cubic yards(50 ac ft) of sediment in the three
lakes. - The Lower and Middle Lakes are nearly full of
sediment. The water is stagnant and provide
breeding habitat for mosquitoes and creates odor
problems during hot weather. - The average depth of the Main Lake is about 4.5
feet. - The dam was modified in 2006 to meet current
design criteria.
13Lake Above Eldorado (Site 5A)
14Description of the Project
? About 80,500 cubic yards of sediment will be
removed from the three lakes and transported to a
disposal site on City-owned property near the
airport. ? A combination of excavation and
hydraulic dredging may be used to remove the
sediment. ? The contractor will discuss their
plan of action.
15(No Transcript)
16Location Map
17Practices to Minimize Adverse Impacts
- Three Tiers of Practices
- Tier 1 Above the 5A Dam
- Tier 2 Below the Site 5A Dam
- Tier 3 Operational
18Practices to Minimize Adverse Impacts
- Tier 1 Above the 5A Dam
- ? The Main Lake will be drained and capture any
disturbed material. - ? A safety fence will be installed.
- ? Silt fences will be installed around the two
principal spillways.
19Practices to Minimize Adverse Impacts
- Tier 1 Above the 5A Dam
- ? Low flows will be diverted away from
construction activities. - ? A tire washing rack will be required.
- ? A final grading plan will be required.
20Practices to Minimize Adverse Impacts
- Tier 2 Below the Site 5A Dam
- Silt fences will installed in the three
reflecting ponds below the dam.
21Practices to Minimize Adverse Impacts
- Tier 3 - Operational
- ? Cease operations if significant stream flow
increases or significant rainfall is predicted. - ? Monitor water quality downstream of the filter
fences in the Main Lake and the reflecting
ponds.
22Other Significant Points
- ? Project duration - 180 days, excluding bad
weather days - ? Monday thru Friday 7 to 7
- ? Saturday 8 until 5
- ? No Holiday Work
- There will be increased noise levels and possibly
odors - Arrangements have been made to provide suitable
irrigation water for the golf course - The Golf course will remain open
23Other Significant Points
- Fish and Wildlife
- Some unavoidable adverse impacts to fish and
wildlife. - Limited fishery at present. Some will move
downstream when the Lake is drained. - Restocking of the Lake is being considered.
- Adverse impacts to wildlife minimal and
temporary.
24End Results
- Health of Three Lakes Improved
- Sediment will be removed
- Depth of water will be increased
- Life of the lakes will be extended significantly
- Breeding ground for mosquitoes reduced
- Stagnant water reduced
- Quality of fish and wildlife improved